Anda di halaman 1dari 2

IME 605, 2015-16

LP Formulation Problems
1. Distributing Goods through a Distribution Network
The DISTRIBUTION LTD. CO. produces a product at two different factories, and then ships
them to two warehouses from either factory. The distribution network available for shipping this
product is shown in Fig. 1, where F1 and F2 are the two factories, W1 and W2 are the two
warehouses, and DC is a distribution center. The amounts to be shipped from F1 and F2 are
shown to their left, and the amounts to be received at W1 and W2 are shown to their right. Each
arrow represents a feasible shipping lane. Thus, F1 can ship directly to W1 and has three possible
routes (F1 DC
W2, F1
F2
DC
W2, and F1
W1
W2) for shipping to W2.
Factory F2 has just one route to W2 (F2 DC W2) and one to W1 (F2 DC W2 W1).
The cost per unit shipped through each shipping lane is shown next to the arrow. Also shown
next to F1 F2 and DC W2 are the maximum amounts that can be shipped through these lanes.
The other lanes have sufficient shipping capacity to handle everything these factories can send.
Formulate the problem as a linear program to minimize the total shipping cost.

Figure 1. The distribution network for Distribution Ltd. Co.

2. Job-Training Problem
A machine tool company conducts a job-training program for machinists. Trained machinists are
used as teachers in the program at a ratio of one for every ten trainees. The training program lasts
for one month. From past experience it has been found that out of ten trainees hired, only seven
complete the program successfully (the unsuccessful trainees are released). Trained machinists
are also needed for machining and the company's requirements for the next months are as
follows:
January
100
February
150
March
200
In addition, the company requires 250 trained machinists by April. There are 130 trained
machinists available at the beginning of the year. Payroll costs per month are:
Each trainee
$400
Each trained machinist
$700 (Machining or teaching)
Each trained machinist idle $500
Set up the linear programming problem that will produce the minimum cost hiring and training
schedule and meet the company's requirements.

3. Roster Planning
The production manager of a chemical plant is attempting to devise a shift pattern for his
workforce. Each day of every working week is divided into three eight-hour shift periods (00:0108:00, 08:01-16:00, 16:01-24:00) denoted by night, day and late respectively. The plant must be
manned at all times and the minimum number of workers required for each of these shifts over
any working week is as below:
Night
Day
Late

Mon Tue Wed Thu


5
3
2
4
7
8
9
5
9
10
10
7

Fri
3
7
11

Sat
2
2
2

Sun
2
5
2

The union agreement governing acceptable shifts for workers is as follows:


Each worker is assigned to work either a night shift or a day shift or a late shift and once
a worker has been assigned to a shift they must remain on the same shift every day that
they work.
Each worker works four consecutive days during any seven day period.
In total there are currently 60 workers. Formulate the production manager's problem as a linear
program.

Anda mungkin juga menyukai