Webinar on

Innovations in PQ interventions
21st May 2015
Amit Raje
Managing Director,
Aartech Solonics Limited

PQ in India An Overview

Ref: http://eoimages.gsfc.nasa.gov/images/imagerecords/55000/55167/earth_lights.jpg

Put your logo


here

Discussion Points
Key PQ Real Time Issues for Industries /
High End Consumers
Some Innovations in PQ in India including
Real Life Examples and Case Studies

Put your logo


here

Connecting the Dots


Does this look familiar
Process Trips / Downtimes ?
Equipment Damage Out of Spec Use ?
Safety Violating Incidents / Accidents ?
Unanticipated Bills to Pay ?
Unproductive Efficiency Building / Cost Cutting
Measures ?

Put your logo


here

PQ Real Time Issues for Industries /


High End Consumers
Process Continuity

Seamless Transfer to Online Standby Source


Reliability of Backups
Uninterrupted Power Systems
Spurious Trips

Safety / Operational Flexibility


Short Circuit Levels

Tariff / Regulatory Compliance


Dynamic Reactive Power Compensation
Harmonic Filtering
5

Put your logo


here

Process Continuity
Fast Bus Transfer Systems
Power Generation / Continuous Process Industries

BTS 2000 Fast Bus Transfer Systems - Aartech


30+ Years of Rich Experience, R&D
400+ Bus Transfer Systems executed all over India.
Total Installation Impact > 50000 MW

GTB

EHV BUS

GT

STB

ST
ST I/C

UAT

GENERATOR
BTS

UAT I/C
UNIT
BOARD

STATION
BOARD

TIE-1
M

TIE-2
(NC)

Fig. 1. Thermal power plant: Main-Tie BTS configuration.

Put your logo


here

NORMAL SOURCE
VOLTAGE PHASOR
(VNORMAL)
MOTOR BUS
VOLTAGE PHASOR
(VBUS)

VOLTAGE COLLAPSE
AND PHASE DECAY
CHARACTERISTICS
OF THE MOTOR BUS

Spin down characteristics of an open circuit motor bus

Put your logo


here

Reliable Engine Starting


Railways, Defense, Heavy Earth Moving Equipment, Marine, DG Sets, Fire
Pumping Engines, Fleet Applications

Put your logo


here

Put your logo


here

10

Put your logo


here

Uninterrupted Power
Data Centers, Textile, CNC Machining, Fire Protection,

PureWave Offline Medium Voltage


UPS Solutions for Whole Facility
Protection from M/s S&C Electric, USA
Data Centres
Mission Critical Applications

FaraDigm Short Duration UPS


Discrete DC/AC UPS solutions for 5-30
second backup before Safe Shut Down /
Ride-through for Power Quality Events such
as Voltage Sags / Changeovers

11

Put your logo


here

Fault Current Limiting


Power T&D, Cement, WHR Generation, Wind

CLiP Current Limiting


Protectors
Fault Current Limiters
M/s G&W Electric Co. USA

12

Put your logo


here

Dynamic Reactive Power Management


PureWave DSTATCOM
S&C Electric Co. USA

Mining Operation 17 x 75-250 HP Motors


=> 8-12% Voltage Flicker
+/- 2MVAR DSTATCOM + 2MVAR Cap Bank

Wood Processing 3 x 400 HP Motors


=> 6% Voltage Flicker
+/- 2MVAR DSTATCOM

I
+

Inverter sizes +1 to +32 MVAR in 1MVAR increments


Shunt capacitors or reactors can shift
the range
2-4 millisecond response time
Short-term overload of 330% for 2
seconds

+
Source

Vs

Vdstat
-

13

DSTATCOM

Put your logo


here

+52

DSTATCOM Output (MVAR)


+16

-16

Switched Cap Banks


+6

Output Comparison SVC vs DSTATCOM with


330% Short-Term Overload

+4

0 Cap

3.50

MVAR

Cap Bank 3

Cap Bank 2
Bank 1

+2

3.00

DSTATCOM

2.50

SVC

0
0
+112

2.00

Total Continuous Output

1.50
1.00
0.50

+40

0.00
1.0

0.9

0.8

0.7

0.6

0.5

0.4

0.3

Voltage (p.u.)

-16

14

Put your logo


here

Case Study..
FaraDigm Short Duration UPS
Textile OEM supplies Regular Battery Based Online UPS
along with Equipment
End User has to invest in Battery Replacement every 2-3
years, approx. Rs 60-70k / UPS
Actual Need is for 15-30 seconds (and not 15-30
minutes) as Safe Shutdown / Diesel Gen Sets are
available as backup Scope for Innovation !!
Short Duration Battery Less UPS offers 10 Year Lifetime,
with 3 Year ROI, Compact, Low Footprint, Weight,
Portability, WYSIWYG Solution.
15

Put your logo


here

Case Study

BTS 2000 Fast Bus Transfer System


Helps avoid Power Cuts, Loss of Revenue,
Process Downtime, Material Wastage,
Equipment Stress, Personnel Anxieties and
Safety Hazards
Potentially Single Operation ROI !

16

Put your logo


here

ESMI Initiative (Prayas, Pune)

Finalist at Google Impact Challenge, 2013


www.watchyourpower.org

17

Put your logo


here

Thanks !
Amit Raje
Email: amitraje@aartechsolonics.com
Mobile: +91-9993091164

18