ASSIGNMENT
CCE&C
Ans to Q No-1
1.
that cannot be readily charged to any one project, but represent the cost of operating the
construction company. The job overhead costs include all overhead expenses that will be incurred
as a result of executing a specific project. The major difference between the two is that the home
office overhead costs are incurred regardless of any specific project.
2.
Home Office OH.
The following items should be included in a home office overhead
budget:a.
Office.
Rent (if owned, the cost plus return on investment), electricity, heat,
water, office supplies, postage, insurance (fire, theft, liability), taxes (property),
b.
c.
d.
3.
2
c.
The
cost
of
temporary
buildings includes all tool sheds, workshop, and material storage spaces. The cost of
building and maintaining, barricades and providing signal lights in conjunction with
d.
e.
f.
g.
h.
i.
estimator must include the cost for the survey in the estimate.
Protection of Property. Miscellaneous items that should be contemplated include
the possibility of the damaging adjacent buildings, such as breaking windows, and
the
Ans to Q No-2
1.
2.
Labour Hours.
A labour hour is defined as one worker working for one hour.
Adjusted Labour Hours.
The number of labour hours needs to be modified to take into
consideration how the project that is being bid deviates from the standard condition. This is done
by using a productivity factor. The mathematical means by which the productivity factor is applied.
Adjusted labour hours = Labour hours X Productivity factor
Adjusted labour hours
3.
and workers and scarce, less-trained craft persons are accepted. These less-trained
persons will require more time or labour hours to complete the required task, and a
3
productivity factor
and hire and only the most qualified workers. This will result in producing more
b.
work per labour hour, and a productivity factor less than one is used.
Climatic Conditions.
Cold, hot, winds, rain, snow, and combinations of these all
c.
d.
per labour hour just due to the difficulty of managing the resources.
Other Considerations. Workers seldom work a full 60 minutes during the hour.
Studies of the actual amount of time worked per hour averaged 30 to 50 minutes.
4.
Data.
a.
= 20,000 Sq Ft / Floor.
b.
=20,000 x 3 =60,000 Sq Ft
c.
2.
Req
3.
Solution.
3x storey building
Ans to Q No-4
1.
2.
3.
4.
5.
5
Ans to Q No-5
RL of
Ground
41.0
40.90
40.50
40.80
RL of Formation
Difference
Remarks
42.00
41.75
41.50
41.25
1.00
0.85
1.00
0.45
3.75/6
0.625
Average
Filling
5.5/5
1.1
Average
Cutting
5.
6.
7.
8.
9.
1200
1250
1300
1350
1400
40.60
40.70
41.20
41.40
41.30
41.00
40.75
40.50
40.25
40.00
0.40
0.05
0.70
1.15
1.30
10.
11.
1450
1500
41.00
40.60
39.75
39.50
1.25
1.10
Width of Road
8m
1250 m3
2200 m3
6
Ans to Q No-6
1.
Data.
a.
Footing Concrete
b.
Reinforcement
c.
Column size
d.
Reinforcement bars =
2.
e.
Req
Lateral ties
=
# 2 bar 10 c/c
Concrete and steel for footing / column
3.
Solution
a.
b.
8 # 7 bars
Foundation
(1)
(2)
Steel
Steel
(a)
Longitudinal = 8 # 7 bars = 8x (16 +1) = 136 RFT
Weight
= 136 RFT x 2.044 = 277.984 lbs
(b)
Lateral
# 2 bars
(1)
Length of one tie = 1.5 + 1.5+ 0.25 = 3.25 RFT
(2)
No of ties = 16 x 12 = 21 Nos
10
(3)
Total length = 21 x 3.25 = 68.25 RFT
(4)
Wt
=
68.25 x 0.167 lbs / RFT = 11.397 lbs
(c)
Foundation + Column
(1)
Concrete = 76.05 + 36
= 112.05 Cu Ft
(2)
Steel = 265.72 + 277.984+ 11.397
= 555.101 lbs
Ans to Q No-7
1.
b.
Shorter Side
c.
= 36 (2 x 9) 2 (1)
2
= 32.25
Total length of excavation = 62.75 + 32.25 = 95 RFT
d.
7
2 (a) PCC (1: 5 : 10) below foundation bed
PCC = 95 x 2 x 1) = 190 Cu Ft
Cement = 190 = 11.87 Cu Ft = 9.5 OR 10 Bags
16
Sand = 190 x 5 = 59.37 Cu Ft
16
Crush = 190 x 10 = 118.75 Cu Ft
16
2 (b) Foundation wall brick masonry in CM (1:6)
2 (c)
Bricks Work =
95 x 2 x 1.5 2 = 185 Cu Ft
Bricks
Masonry
Cement
Sand
3877 = 76.95 Cu Ft
50
76.95 x 1 = 10.99 Cu Ft = 10.99 = 8.79 OR 9 Bags
7
1.25
76.95x 6 = 65.94 Cu Ft
7
Cement
Sand
Crush
32.25
Width
20.75
Total Material=
Cement
Sand
Crush
Steel
334.59 x 2 = 95.58 Cu Ft
7
334.59 x 4 = 191.16 Cu Ft
7
32.25 + 1 = 65.5 Nos = 66 x 20.75 Ft = 1359.5 Rft
0.50
20.75 + 1 = 42.1 + 1 = 43 x 32.25 = 1386.75 Rft
0.50
=
Total Steel
8
=
5633.77 Lbs
ASSIGNMENT # 2
CCE&C
SUBMITTED TO
MAJ YOUSAF JAMAL
SUBMITTED BY
M.MOAAZ MUNIR