Facultad De Ingeniera
Departamento De Obras Civiles
Planificacin de proyectos
Construccin
Embalse Ancoa
Profesor: Miguel ngel Mellado
23 de septiembre de 2015
Integrantes:
Carlos Allende
G.
Jos Almendra
C.
Mauricio
Fuentes D.
Contenido
Resumen con descripcin del Proyecto............................................................................................
Mtodo constructivo presas material suelto:........................................................................
1. Instalacin de faenas:.............................................................................................
1
2. Red vial......................................................................................................................
3. Roce, descepe, escarpe y limpieza.......................................................................
4. Construccin de la Atagua....................................................................................
5. Excavaciones............................................................................................................
6. Drenaje, iluminacin y ventilacin de las excavaciones...................................
7. Tnel de desviacin.................................................................................................
8. Construccin del Plinto...........................................................................................
9. Pantalla de hormign..............................................................................................
10.
Evacuador de crecidas.........................................................................................
11.
Instalacin de equipos.........................................................................................
12.
Pruebas de control...............................................................................................
13.
El proyecto de esta represa no es nuevo, el proyecto nace en la dcada de los 50, donde se
llev acabo pero la falta de estudios y tecnologa no permitieron que siguiera adelante. El
proyecto tena una capacidad de 100 millones de m3.
El proyecto paso a denominarse (se conoce as hasta el da de hoy) embalse Ancoa. El
proyecto fallo por filtraciones, trataron de repararse pero no se pudo, por lo que el proyecto
fue abandonado.
En el ao 2001 la direccin de obras hidrulicas llamo a licitacin para la renovacin de
este proyecto. En el sondeo a terreno se previ que uno de los aspectos ms importantes es
el tema de la impermeabilizacin de la base.
El estudio de factibilidad concluyo el ao 2004
Se consider el diseo de la presa Ancoa Alto 1, con capacidad de 80 millones de m3. El
proyecto incluye las siguientes obras:
Normas INN
Fuerza
Motriz
de
la
2. Red vial
El Contratista deber reubicar caminos cada vez que sea necesario para sus
obras y sealizar adecuadamente los desvos, cruces y todo otro sitio de
peligro. Todos estos cambios no debern hacerse sin antes contar con la
aprobacin de los organismos competentes (Direccin de Vialidad del M.O.P.,
Municipalidad u otro)
el suelo, fuera de los lmites de la excavacin o bien que esta perturbacin sea
mnima, adems los materiales excavados se clasificarn para su pago en roca
y material comn. Se debe tener especial cuidado en construir obras de
drenaje necesarias para la evacuacin de las aguas, para proteger la obra en
ejecucin.
7. Tnel de desviacin
Su funcin es desviar el caudal del ro durante la construccin de la presa y el
sistema de evacuacin de crecidas, proporcionando seguridad para el
desarrollo de estas faenas, debe haber concluido las obras de toma, entrada y
salida del tnel, instalacin de tuberas de entrada de riego al interior del tnel,
obras de cierre de primera etapa o tapn en la caverna de vlvulas, para as
poder ser desviado el ro por el tnel de desviacin.
9. Pantalla de hormign
Consiste en una superficie de hormign armado H30, de espesor variable, se
construir de abajo hacia arriba, es obligatorio el vibrado por inmersin, cubre
toda la cara de aguas arriba de la presa y est limitada por otras estructuras
de hormign que la complementan.
10.
Evacuador de crecidas
7
11.
Instalacin de equipos
12.
Pruebas de control
Todos los materiales y equipos que formarn parte del suministro deben ser
inspeccionados, estos materiales y equipos deben tener las exigencias de las
E.T.E. y las Normas respectivas, se inspeccionan entre otros materiales, piezas
soldadas, fundidas, armados, pinturas, embalajes.
13.
Desviacin de aguas
1.1.3.1 Construccin de atagua
1.1.3.2 Desviacin de agua para trabajos superficial
1.1.3.3 Agotamiento de agua para trabajos superficiales
1.1.3.4 Desviacin de aguas para trabajos subterrneos
1.1.3.5 Agotamiento de aguas para trabajos subterrneos
Movimiento de tierra superficial
Excavaciones
1.2.1.1 Excavacin para zonas de inundacin
1.2.1.2 Excavacin para plinto
1.2.1.3 Excavacin para para pantalla de Hormign
1.2.1.4 Excavacin para evacuador de crecidas
Rellenos
1.2.2.1 relleno plinto
1.2.2.2 Relleno Pantalla de hormign
1.2.2.3 Enrocado para proteccin (Zona 4)
Compactaciones
1.2.3.2 Compactacin relleno pantalla
1.2.3.1 Compactacin relleno plinto
Movimiento de tierra Subterrneo
Excavaciones
1.3.1.1 Excavaciones subterrneas
1.3.1.2 Clasificacin material excavado
Refuerzo Excavaciones
1.3.2.1 Instalacin de marcos
10
Estructuras
Preparacin superficies
1.5.1.1 Preparacin superficie
1.5.1.2 Preparacin superficie plinto
11
Equipamiento
1.7.2.1 Instalacin de equipamiento
Prueba de servicios
1.7.3.1 Pruebas de servicio
Recepcin y puesta en marcha
Cierre tnel de desviacin
1.8.1.1 Cierre tnel de desviacin
Retiro de instalacin de faena
1.8.2.1 Retiro de instalacin de faena y escombros
Recepcin y puesta en marcha
1.8.3.1 Trmino y proteccin
1.8.4.1 Recepcin y puesta en marcha
1
2
3
4
5
6
7
8
9
1
0
1
1
1
2
1
3
1
4
Actividad
Instalacin de campamentos
Conexin a servicios bsicos
Instalacin laboratorio de suelos
Instalacin laboratorio de hormigones
Preparacin de caminos hacia el terreno
Roce
Excavacin de escarpe
Limpieza general del terreno
Construccin de atagua
Desviacin de agua para trabajos
superficiales
Agotamiento para trabajos superficiales
Desviacin de agua para trabajos
subterraneos
Sucesor
2(CC=10;TT=5)
3(CC=3;TT=3) ; 4(CC=3;TT=3) ; 5(TC=0)
9(TC=5)
9(TC=5)
6(TC=0)
7(CC=10;TT=3)
8(TC=0)
9(TC=0)
10(TC=10) ; 12(TC=10)
11(CC=5;TT=5)
14(TC=0) ; 15(TC=0) ; 16(TC=0) ;
17(TC=0)
13(CC=5;TT=5)
24(TC=0)
13
1
5
1
6
1
7
1
8
1
9
2
0
2
1
2
2
2
3
2
4
2
5
2
6
2
7
2
8
2
9
3
0
3
1
3
2
3
3
3
4
3
5
3
6
3
7
3
8
3
9
24(TC=0) ; 33(TC=0)
24(TC=0) ; 18(TC=0)
24(TC=0) ; 32(TC=0)
21(TC=0)
34(TC=0)
Relleno plinto
Compactacin relleno pantalla de
Hormign
22(TC=0)
56(TC=0)
24(TC=0) ; 25(TC=0) ; 26(TC=0) ;
27(TC=0) ; 28(TC=0)
Instalacin de marcos
Hormign proyectado
Ventilacin excavaciones
60(TC=0)
Iluminacin excavaciones
60(TC=0)
Sistema comunicacin
Moldaje Fundacin Evacuador de
crecidas
60(TC=0)
36(CC=5 ; TT=5)
34(TC=0)
35(CC=5 ; TT=5)
39(CC=5 ; TT=5)
42(TC=0)
40(CC=5 ; TT=5)
41(TC=0)
14
4
0
4
1
4
2
4
3
4
4
4
5
4
6
4
7
4
8
4
9
5
0
5
1
5
2
5
3
5
4
5
5
5
6
5
7
5
8
5
9
6
0
6
1
6
2
6
3
6
4
43(TC=0)
44(TC=0)
45(TC=0)
46(TC=0)
47(TC=0)
48(TC=0)
49(TC=0)
50(CC=5 ; TT=5)
Moldaje Plinto
51(CC=5 ; TT=5)
52(CC=5 ; TT=5)
53(CC=5 ; TT=5)
Enfierradura Plinto
54(CC=5 ; TT=5)
55(CC=5 ; TT=5)
56(TC=5)
Hormigonado plinto
56(TC=5)
56(TC=5)
Terminaciones de Estructura
57(TC=5)
Limpieza de superficies
58(TC=0)
Aplicaciones Antioxidos
58(TC=1)
Pinturas
58(TC=1)
instalacin de tuberias
61(CC=2 ; TT=2)
instalacion de equipamiento
62(TC=0)
Pruebas de servicio
63(TC=0)
64(TC=0)
65(TC=0)
15
6
5 termino y proteccion
6
6 recepcion y puesta en marcha
66(TC=0)
Cantidades de obra
1
2
3
4
5
6
7
8
9
1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
1
9
2
0
2
1
2
Actividad
Instalacin de campamentos
Conexin a servicios bsicos
Instalacin laboratorio de suelos
Instalacin laboratorio de
hormigones
Preparacin de caminos hacia el
terreno
Roce
Excavacin de escarpe
Limpieza general del terreno
Construccin de atagua
Desviacin de agua para trabajos
superficiales
Agotamiento para trabajos
superficiales
Desviacin de agua para trabajos
subterraneos
Agotamiento para trabajos
subterraneos
Cantida
d
1
1
1
Unida
d
Gral
Gral
Gral
1 Gral
13.560
13.560
24.408
81.360
1
ml
ml
m3
m2
Gral
1 Gral
1 Gral
1 Gral
1 Gral
159.15
0 m3
19.322 m3
27.899 m3
18.354 m3
4.698 m2
5.597 m2
Relleno plinto
Compactacin relleno pantalla de
Hormign
Compactacin relleno plinto
65.476 m2
28.110 m2
27.852 m2
16
2
2
3
2
4
2
5
2
6
2
7
2
8
2
9
3
0
3
1
3
2
3
3
3
4
3
5
3
6
3
7
3
8
3
9
4
0
4
1
4
2
4
3
4
4
4
5
4
6
Excavaciones subterrneas
63 m3
1 Gral
Instalacin de marcos
1 Gral
1 Gral
1 Gral
Hormign proyectado
1 Gral
Ventilacin excavaciones
1 Gral
Iluminacin excavaciones
1 Gral
Sistema comunicacin
Moldaje Fundacin Evacuador de
crecidas
1 Gral
1.300 m2
3.030 m2
6.078 m2
31.520 kg
40.200 kg
222.60
0 kg
780 m3
1.818 m3
3.000 m2
5.550 m2
6.300 m2
950 ml
3.647 m3
1.850 ml
2.100 ml
17
4
7
4
8
4
9
5
0
5
1
5
2
5
3
5
4
5
5
5
6
5
7
5
8
5
9
6
0
6
1
6
2
6
3
6
4
6
5
6
6
2.400 m2
Moldaje Plinto
1.350 m2
40.000
157.60
0
201.00
0
1.113.0
00
m2
kg
kg
kg
1.850 m3
550 m3
18.000 m3
1 Gral
Limpieza de superficies
6.300 m2
Aplicaciones Antioxidos
6.300 Gral
Pinturas
6.300 m2
instalacin de tuberias
2.100 ml
instalacion de equipamiento
Pruebas de servicio
1 Gral
prueb
20 as
1 Gral
1 Gral
termino y proteccion
1 Gral
1 Gral
18
Presupuesto
Actividad
Cantidad Unidad
1 Instalacin de campamentos
2 Conexin a servicios bsicos
3 Instalacin laboratorio de suelos
Instalacin laboratorio de
4 hormigones
Preparacin de caminos hacia el
5 terreno
6 Roce
13.560 ml
13.560 ml
7 Excavacin de escarpe
24.408 m3
81.360 m2
9 Construccin de atagua
Desviacin de agua para trabajos
10 superficiales
Agotamiento para trabajos
11 superficiales
Desviacin de agua para trabajos
12 subterraneos
Agotamiento para trabajos
13 subterraneos
14 Excavacin zona de inundacin
1 Gral
1 Gral
1 Gral
1 Gral
1 Gral
Precio
2.637.00
0
639.500
639.500
396.000
594.000
3.240.00
0
1.899.00
0
9.058.50
0
1 Gral
1 Gral
1 Gral
1 Gral
159.150 m3
19.322 m3
27.899 m3
18.354 m3
18.900.0
00
4.725.00
0
6.300.00
0
4.725.00
19
4.698 m2
5.597 m2
20 Relleno plinto
Compactacin relleno pantalla de
21 Hormign
65.476 m2
27.852 m2
23
24
25
26
27
28
29
30
31
Excavaciones subterrneas
Clasificacin material excavado
Instalacin de marcos
Colocacin pernos de roca
Instalacin de mallas de alambre
Hormign proyectado
Ventilacin excavaciones
Iluminacin excavaciones
Sistema comunicacin
Moldaje Fundacin Evacuador de
32 crecidas
33 Moldaje Fundacin Plinto
Moldaje Fundacin Pantalla de
34 hormigon
Enfierradura Fundacin Evacuador
35 de crecidas
36 Enfierradura Fundacin Plinto
Enfierradura Fundacin Pantalla de
37 hormigon
Hormigonado Fundacin
38 Evacuador de crecidas
28.110 m2
63
1
1
1
1
1
1
1
1
m3
Gral
Gral
Gral
Gral
Gral
Gral
Gral
Gral
1.300 m2
3.030 m2
6.078 m2
31.520 kg
40.200 kg
222.600 kg
780 m3
1.818 m3
3.000 m2
5.550 m2
43
44
45
46
47
48
6.300
950
1.850
2.100
2.400
1.350
3.647 m3
m2
ml
ml
ml
m2
m2
0
261.000
522.000
1.174.50
0
2.700.00
0
2.700.00
0
1.125.00
0
985.500
234.000
711.000
189.000
486.000
1.080.00
0
1.080.00
0
1.260.00
0
1.575.00
0
5.670.00
0
10.620.0
00
21.240.0
00
21.240.0
00
3.105.00
0
4.140.00
0
4.657.50
0
108.000
162.000
162.000
864.000
540.000
20
40.000 m2
157.600 kg
201.000 kg
1.113.00
0 kg
1.850 m3
550 m3
18.000 m3
56 Terminaciones de Estructura
1 Gral
57 Limpieza de superficies
6.300 m2
58 Aplicaciones Antioxidos
6.300 Gral
59
60
61
62
63
64
65
66
6.300
2.100
1
20
1
1
1
1
Pinturas
instalacin de tuberias
instalacion de equipamiento
Pruebas de servicio
Cierre tunel desviacion
Retiro instalacion y faena
termino y proteccion
recepcion y puesta en marcha
m2
ml
Gral
pruebas
Gral
Gral
Gral
Gral
5.076.00
0
1.386.00
0
1.827.00
0
8.127.00
0
7.080.00
0
5.310.00
0
23.010.0
00
1.215.00
0
1.890.00
0
1.728.00
0
1.890.00
0
441.000
201.325.
000
21
WBS
Date 22SEP15
Page 1
PLAN - Represa
--------------------------------------------------------------------------------
Structure: x.x.x
WBS Code
Title
1 Represa
1.1 Obras previas
1.1.1 Instalacin de faena
1.1.2 Preparacin del terreno
1.1.3 Desviacin de aguas
1.2 Movimiento de tierra superficial
1.2.1 Excavaciones
1.2.2 Rellenos
1.2.3 Compactaciones
1.3 Movimiento de tierra Subterraneo
1.3.1 Excavaciones
1.3.2 Refuerzo excavaciones
1.3.3 Instalacin de servicios
22
1.4 Fundaciones
1.4.1 Moldaje
1.4.2 Enfierradura
1.4.3 Hormigonado
1.5 Estructuras
1.5.1 Preparacin superficies
1.5.2 Preparacin juntas
1.5.3 Moldaje
1.5.4 Enfierradura
1.5.5 Hormigonado
1.5.6 Terminaciones
1.6 Tuberas y equipamiento
1.6.1 Tuberas
1.6.2 Equipamiento
1.6.3 Prueba de servicios
1.7 Recepcin y puesta en marcha
1.7.1 Cierre tunel de desviacin
1.7.2 Retiro de instalacin de faena
1.7.3 Recepcin y puesta en marcha
SR-01 Fechas de Inicio y Trmino
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:41
Classic Schedule Report - Sort by ES, TF
23
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----1.1.1.1
60 60
Instalacin de campamentos
1.1.1.2
20 20
1.1.1.3
10 10
1.1.1.4
10 10
47
1.1.2.1
20 20
1.1.2.2
1.1.2.3
10 10
Excavacin de escarpe
1.1.2.4
10 10
1.1.3.1
40 40
Construccin de atagua
1.1.3.2
20 20
1.1.3.4
10 10
30
1.1.3.5
30
Roce
47
24
1.3.1.1
Excavaciones subterrneas
1.3.2.4
10 10
1.3.2.1
1.3.2.2
1.3.2.3
1.1.3.3
1.2.1.1
21 21
1.2.1.3
12 12
1.2.1.2
11 11
1.2.1.4
10 10
1.3.2.5
20 20
1.4.1.1
10 10
1.4.2.1
18 18
1.4.1.2
10 10
1.4.2.2
18 18
Hormign proyectado
30
39
44
44
44
10
11
39
53
53
35
35
25
1.4.3.2
10 10
1.4.3.1
1.3.1.2
1.3.3.1
15 15
1.3.3.2
1.3.3.3
1.2.2.2
35
53
39
47
49
26
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:41
Classic Schedule Report - Sort by ES, TF
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----1.2.2.3
1.5.1.1
1.5.1.2
1.2.3.2
1.4.1.3
21 21
1.4.2.3
28 28
1.5.2.1
1.5.2.2
1.5.3.1
10 10
42
53
35
53
35
53
27
1.5.4.1
80 80
1.4.3.3
19 19
1.5.3.2
1.5.4.2
77 77
1.5.1.3
1.5.2.3
1.5.3.3
29 29
1.5.4.3
96 96
1.5.5.3
87 87
1.5.5.1
29 29
53
1.5.5.2
12 12
Hormigonado plinto
1.2.2.1
15 15
Relleno plinto
1.2.3.1
1.6.1.1
20 20
Terminaciones de estructuras
1.6.1.2
10 10
Limpieza de superficies
Moldaje plinto
Enfierradura plinto
53
35
35
35
35
35
28
1.6.1.3
10 10
Aplicacin de antixidos
1.6.1.4
Pinturas
1.7.1.1
Instalacin de tuberas
1.7.2.1
20 20
Instalacin de equipamiento
1.7.3.1
10 10
Pruebas de servicio
1.8.1.1
20 20
1.8.2.1
20 20
1.8.3.1
40 40
29
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:42
Schedule Report with Activity Budgets
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
BUDGET
EARNED
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----1.1.1.1
60 60
Instalacin de campamentos
48420000.00
1.1.1.2
20 20
10 10
1.1.1.4
10 10
20 20
1.1.2.2
Roce
47
.00
47
.00
.00
1.1.2.1
.00
1.1.1.3
.00
30
5346000.00
1.1.2.3
10 10
.00
Excavacin de escarpe
32400000.00
1.1.2.4
10 10
.00
1.1.3.1
40 40
10 10
Construccin de atagua
20 20
.00
1.3.2.3
30
.00
Excavaciones subterrneas
30
.00
44
.00
.00
4927500.00
1.3.2.2
30
.00
1125000.00
1.3.2.1
1.3.1.1
1.1.3.5
1.1.3.2
.00
16740000.00
1.1.3.4
44
.00
44
31
1170000.00
1.3.2.4
10 10
.00
Hormign proyectado
1710000.00
1.1.3.3
10 10
.00
1.2.1.4
11 11
12 12
21 21
1.3.2.5
20 20
.00
10
.00
11
.00
15120000.00
1.2.1.1
.00
10395000.00
1.2.1.3
.00
9450000.00
1.2.1.2
39
39
.00
32
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:42
Schedule Report with Activity Budgets
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
BUDGET
EARNED
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----1.4.1.1
10 10
1.4.2.1
18 18
10 10
18 18
10 10
1.4.3.1
35
35
.00
35
.00
53
.00
28350000.00
1.4.3.2
.00
10800000.00
1.4.2.2
53
.00
22680000.00
1.4.1.2
53
.00
33
1.3.1.2
1.3.3.3
.00
15 15
1.2.2.2
1.2.3.2
1.5.2.1
53
.00
35
.00
53
.00
42
.00
5400000.00
28980000.00
39
15525000.00
1.5.1.2
.00
3654000.00
1.5.1.1
47
.00
1305000.00
1.2.2.3
.00
49
.00
882000.00
1.3.3.1
1.3.3.2
.00
34
1.4.1.3
21 21
1.4.2.3
28 28
10 10
80 80
1.5.3.2
19 19
Moldaje plinto
53
35
.00
53
.00
4860000.00
1.4.3.3
35
.00
.00
8640000.00
1.5.4.1
.00
972000.00
1.5.3.1
.00
1.5.2.2
.00
35
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:42
Schedule Report with Activity Budgets
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
BUDGET
EARNED
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----1.5.4.2
77 77
Enfierradura plinto
.00
1.5.1.3
1.5.2.3
29 29
1.5.4.3
96 96
1.5.5.3
87 87
.00
.00
.00
.00
1134000.00
1.5.3.3
35
.00
36
1.5.5.1
29 29
1.5.5.2
12 12
15 15
Hormigonado plinto
Relleno plinto
20 20
1.6.1.2
10 10
10 10
Limpieza de superficies
Aplicacin de antixidos
20 20
.00
Instalacin de equipamiento
.00
.00
Instalacin de tuberas
.00
2646000.00
1.7.2.1
Pinturas
.00
17010000.00
1.7.1.1
17280000.00
1.6.1.4
35
.00
18900000.00
1.6.1.3
Terminaciones de estructuras
.00
35
.00
5400000.00
1.6.1.1
35
.00
17617500.00
1.2.3.1
53
.00
9720000.00
1.2.2.1
.00
37
1.7.3.1
10 10
Pruebas de servicio
.00
1.8.1.1
20 20
20 20
40 40
.00
.00
1.8.3.1
1.8.2.1
.00
.00
------------ -----------SUBTOTAL
482059000.00
.00
============ ============
REPORT TOTAL
482059000.00
.00
38
-1---------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:34
Schedule Report - Detailed Precedence Analysis
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- -----
1.1.1.1
60 60
..1.1.1.2
20 20
..1.1.1.2 * 20 20
..1.1.1.1
0 PR SS 10 Instalacin de campamentos
0 PR FF
60 60
..1.1.1.1 * 60 60
Instalacin de campamentos
5 Instalacin de campamentos
1.1.1.2
20 20
..1.1.1.3
10 10
47
..1.1.1.3 * 10 10
47
..1.1.1.4
10 10
47
..1.1.1.4 * 10 10
47
39
..1.1.2.1 * 20 20
0 SU
..1.1.1.2
20 20
0 PR SS
..1.1.1.2 * 20 20
0 PR FF
1.1.1.3
10 10
..1.1.3.1
40 40
0 SU
Construccin de atagua
..1.1.1.2
20 20
0 PR SS
..1.1.1.2 * 20 20
0 PR FF
1.1.1.4
10 10
..1.1.3.1
40 40
0 SU
Construccin de atagua
..1.1.1.2 * 20 20
0 PR
1.1.2.1
..1.1.2.2 *
20 20
0 SU
..1.1.2.1 * 20 20
1.1.2.2
0 PR
47
Roce
47
Roce
40
..1.1.2.3 * 10 10
0 SU SS 10 Excavacin de escarpe
..1.1.2.3
0 SU FF 3 Excavacin de escarpe
10 10
..1.1.2.2 *
0 PR SS 10 Roce
..1.1.2.2
0 PR FF
1.1.2.3
10 10
3 Roce
Excavacin de escarpe
0
0
..1.1.2.4 * 10 10
0 SU
..1.1.2.3 * 10 10
0 PR
Excavacin de escarpe
1.1.2.4
10 10
..1.1.3.1 * 40 40
0 SU
Construccin de atagua
..1.1.1.3
10 10
0 PR
..1.1.1.4
10 10
0 PR
..1.1.2.4 * 10 10
0 PR
47
47
41
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:34
Schedule Report - Detailed Precedence Analysis
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----1.1.3.1
40 40
Construccin de atagua
..1.1.3.2 * 20 20
0 SU
..1.1.3.4 * 10 10
0 SU
..1.1.3.1 * 40 40
0 PR
Construccin de atagua
1.1.3.2
20 20
0
30
..1.1.3.3
..1.1.3.3 *
..1.1.3.1 * 40 40
1.1.3.4
10 10
0 PR
Construccin de atagua
30
42
..1.1.3.5
30
..1.1.3.5 *
30
..1.1.3.4
10 10
0 PR SS
30
..1.1.3.4 * 10 10
0 PR FF
30
1.1.3.5
..1.3.1.1 *
0 SU
Excavaciones subterrneas
..1.1.3.5 *
0 PR
1.3.1.1
..1.3.1.2
0 SU
..1.3.2.1 *
0 SU
..1.3.2.2 *
0 SU
..1.3.2.3 *
0 SU
..1.3.2.4 * 10 10
..1.3.1.1 *
1.3.2.4
10 10
..1.3.2.5 * 20 20
Excavaciones subterrneas
0 SU
0 PR
0 SU
Hormign proyectado
Excavaciones subterrneas
Hormign proyectado
30
0
44
44
44
39
30
30
30
30
39
39
43
..1.3.1.1 *
1.3.2.1
..1.3.2.5
..1.3.1.1 *
1.3.2.2
..1.3.2.5
..1.3.1.1 *
1.3.2.3
..1.3.2.5
0 PR
20 20
0 SU
Excavaciones subterrneas
0 PR
20 20
Excavaciones subterrneas
0 PR
0 SU
44
30
0 SU
20 20
Excavaciones subterrneas
44
30
39
39
30
44
39
44
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:34
Schedule Report - Detailed Precedence Analysis
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----..1.1.3.2
20 20
0 PR SS
..1.1.3.2 * 20 20
0 PR FF
1.1.3.3
..1.2.1.1 * 21 21
0 SU
..1.2.1.2 * 11 11
0 SU
..1.2.1.3 * 12 12
0 SU
..1.2.1.4 * 10 10
0 SU
11
..1.1.3.3 *
1.2.1.1
..1.3.1.2 *
21 21
0 PR
0 SU
10
45
..1.1.3.3 *
1.2.1.3
12 12
0 PR
..1.3.1.2
0 SU
..1.1.3.3 *
0 PR
1.2.1.2
..1.3.1.2
11 11
..1.4.1.2 * 10 10
..1.1.3.3 *
1.2.1.4
..1.3.1.2
10 10
..1.4.1.1 * 10 10
0 SU
0 SU
0 PR
0 SU
0 SU
..1.3.2.2
0 PR
..1.3.2.3
0 PR
0
35
0 PR
20 20
10
1.3.2.5
0 PR
..1.3.2.1
..1.3.2.4 * 10 10
Hormign proyectado
11
53
44
44
44
39
39
46
..1.3.3.1 * 15 15
0 SU
39
47
..1.3.3.2 *
0 SU
..1.3.3.3 *
0 SU
..1.2.1.4 * 10 10
1.4.1.1
10 10
0 PR
49
11
53
..1.4.2.1 * 18 18
53
..1.4.2.1
53
..1.4.1.1 * 10 10
0 PR SS
53
..1.4.1.1
10 10
0 PR FF
53
1.4.2.1
18 18
18 18
53
..1.4.3.1
53
..1.4.3.1 *
53
47
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:34
Schedule Report - Detailed Precedence Analysis
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----..1.2.1.2 * 11 11
1.4.1.2
10 10
0 PR
10
35
..1.4.2.2 * 18 18
35
..1.4.2.2
35
..1.4.1.2 * 10 10
0 PR SS
35
..1.4.1.2
10 10
0 PR FF
35
1.4.2.2
18 18
..1.4.3.2
10 10
35
..1.4.3.2 * 10 10
35
..1.4.2.2
0 PR SS
18 18
18 18
35
35
48
..1.4.2.2 * 18 18
1.4.3.2
..1.5.1.2 *
..1.4.2.1
0 PR FF
10 10
0 SU
35
35
35
18 18
0 PR SS
53
..1.4.2.1 * 18 18
0 PR FF
53
1.4.3.1
..1.5.1.1 *
0 SU
..1.2.1.1 * 21 21
0 PR
53
53
..1.2.1.2
11 11
0 PR
..1.2.1.3
12 12
0 PR
..1.2.1.4
10 10
0 PR
11
..1.3.1.1
0 PR
1.3.1.2
..1.2.2.1
15 15
Excavaciones subterrneas
0 SU
Relleno plinto
..1.2.2.2 *
0 SU
..1.2.2.3 *
0 SU
..1.3.2.5 * 20 20
0 PR
10
35
30
0
42
39
49
1.3.3.1
15 15
..1.5.3.3
29 29
0 SU
..1.3.2.5 * 20 20
0 PR
1.3.3.2
..1.5.3.3
39
47
29 29
0 SU
..1.3.2.5 * 20 20
0 PR
1.3.3.3
..1.5.3.3
29 29
0 SU
39
39
49
50
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:34
Schedule Report - Detailed Precedence Analysis
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----..1.3.1.2 *
0 PR
..1.2.3.2 *
0 SU
..1.3.1.2 *
0 PR
1.2.2.2
1.2.2.3
..1.5.3.3
..1.4.3.1 *
1.5.1.1
29 29
0 SU
0 PR
42
53
53
51
..1.5.2.1 *
0 SU
..1.4.3.2 * 10 10
1.5.1.2
0 PR
..1.5.2.2 *
..1.2.2.2 *
1.2.3.2
1.4.1.3
53
35
35
0 SU
35
0 PR
..1.4.1.3 * 21 21
..1.2.3.2 *
21 21
0 SU
0 PR
..1.4.2.3 * 28 28
..1.4.2.3
..1.4.1.3 * 21 21
0 PR SS
..1.4.1.3
0 PR FF
28 28
21 21
52
1.4.2.3
28 28
..1.4.3.3
19 19
..1.4.3.3 * 19 19
..1.5.1.1 *
1.5.2.1
0 PR
..1.5.3.1 * 10 10
..1.5.1.2 *
0 SU
0 PR
..1.5.3.2 *
0 SU
Moldaje plinto
..1.5.2.1 *
0 PR
53
53
1.5.2.2
53
35
35
35
53
53
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:34
Schedule Report - Detailed Precedence Analysis
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----1.5.3.1
10 10
53
..1.5.4.1 * 80 80
53
..1.5.4.1
53
..1.5.3.1 * 10 10
0 PR SS
53
..1.5.3.1
10 10
0 PR FF
53
1.5.4.1
80 80
..1.5.5.1
29 29
53
..1.5.5.1 * 29 29
53
..1.4.2.3
28 28
0 PR SS
..1.4.2.3 * 28 28
0 PR FF
80 80
53
54
1.4.3.3
19 19
..1.5.1.3 *
0 SU
..1.5.2.2 *
0 PR
1.5.3.2
Moldaje plinto
35
0 SU SS 0 Enfierradura plinto
35
..1.5.4.2
0 SU FF 0 Enfierradura plinto
35
..1.5.3.2 *
0 PR SS
0 Moldaje plinto
35
..1.5.3.2
0 PR FF
0 Moldaje plinto
35
1.5.4.2
77 77
..1.5.5.2
12 12
0 SU SS 0 Hormigonado plinto
35
..1.5.5.2 * 12 12
0 SU FF 0 Hormigonado plinto
35
..1.4.3.3 * 19 19
0 PR
1.5.1.3
..1.5.2.3 *
0 SU
Enfierradura plinto
35
..1.5.4.2 * 77 77
77 77
35
55
..1.5.1.3 *
1.5.2.3
0 PR
..1.5.3.3 * 29 29
..1.2.2.3
..1.3.3.1
15 15
..1.3.3.2
..1.3.3.3
..1.5.2.3 *
1.5.3.3
0 SU
0 PR
42
39
0 PR
47
0 PR
0 PR
29 29
0 PR
..1.5.4.3 * 96 96
..1.5.4.3
..1.5.3.3 * 29 29
0 PR SS
..1.5.3.3
0 PR FF
96 96
29 29
49
56
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:34
Schedule Report - Detailed Precedence Analysis
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----1.5.4.3
96 96
..1.5.5.3
87 87
..1.5.5.3 * 87 87
..1.5.4.3
96 96
0 PR SS
..1.5.4.3 * 96 96
0 PR FF
1.5.5.3
87 87
..1.6.1.1 * 20 20
0 SU
Terminaciones de estructuras
..1.5.4.1
80 80
0 PR SS
53
..1.5.4.1 * 80 80
0 PR FF
53
1.5.5.1
29 29
53
57
..1.6.1.1
20 20
0 SU
Terminaciones de estructuras
..1.5.4.2
77 77
0 PR SS
0 Enfierradura plinto
35
..1.5.4.2 * 77 77
0 PR FF
0 Enfierradura plinto
35
1.5.5.2
12 12
Hormigonado plinto
35
35
..1.2.2.1 * 15 15
0 SU
Relleno plinto
..1.6.1.1
20 20
0 SU
Terminaciones de estructuras
..1.3.1.2
0 PR
..1.5.5.2 * 12 12
1.2.2.1
..1.2.3.1 *
0 PR
15 15
0 SU
..1.2.2.1 * 15 15
1.2.3.1
..1.6.1.1
20 20
..1.2.3.1
0 PR
Hormigonado plinto
Relleno plinto
Relleno plinto
0 SU
0 PR
Terminaciones de estructuras
35
35
35
35
35
35
58
..1.5.5.1
29 29
0 PR
..1.5.5.2
12 12
0 PR
Hormigonado plinto
..1.5.5.3 * 87 87
0 PR
1.6.1.1
20 20
..1.6.1.1 * 20 20
0 PR
Terminaciones de estructuras
Limpieza de superficies
..1.6.1.3 * 10 10
0 SU
Aplicacin de antixidos
..1.6.1.2 * 10 10
0 PR
Limpieza de superficies
1.6.1.3
..1.6.1.4 *
10 10
0 SU
Limpieza de superficies
Aplicacin de antixidos
Pinturas
53
35
0 SU
10 10
Terminaciones de estructuras
..1.6.1.2 * 10 10
1.6.1.2
59
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:34
Schedule Report - Detailed Precedence Analysis
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----..1.6.1.3 * 10 10
1.6.1.4
0 PR
Aplicacin de antixidos
..1.7.1.1 *
0 SU
Instalacin de tuberas
..1.6.1.4 *
0 PR
Pinturas
1.7.1.1
Pinturas
Instalacin de tuberas
..1.7.2.1 * 20 20
0 SU SS 0 Instalacin de equipamiento
..1.7.2.1
0 SU FF 0 Instalacin de equipamiento
20 20
..1.7.1.1 *
0 PR SS
0 Instalacin de tuberas
..1.7.1.1
0 PR FF
0 Instalacin de tuberas
60
1.7.2.1
20 20
Instalacin de equipamiento
..1.7.3.1 * 10 10
0 SU
Pruebas de servicio
..1.7.2.1 * 20 20
0 PR
Instalacin de equipamiento
1.7.3.1
10 10
Pruebas de servicio
..1.8.1.1 * 20 20
0 SU
..1.7.3.1 * 10 10
0 PR
Pruebas de servicio
1.8.1.1
20 20
..1.8.1.1 * 20 20
0 PR
..1.8.3.1 * 40 40
0 SU
..1.8.2.1 * 20 20
0 PR
0 SU
20 20
..1.8.2.1 * 20 20
1.8.2.1
61
1.8.3.1
40 40
62
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:36
Schedule Report with Resource Usage
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----1.1.1.1
60 60
AYU
Instalacin de campamentos
Ayudante
162.00 HH /DAY
MAS1
9720
Maestro de primera
54.00 HH /DAY
MAS2
3240
Maestro de segunda
54.00 HH /DAY
PLUM
3240
Grua pluma
18.00 HM /DAY
1080
1.1.1.2
20 20
1.1.1.3
10 10
47
63
AYU
Ayudante
27.00 HH /DAY
MAS1
Maestro de primera
9.00 HH /DAY
PLUM
MAS2
10 10
AYU
PLUM
270
MAS2
90
Grua pluma
5.00 HM /DAY
50
Maestro de segunda
9.00 HH /DAY
20 20
AYU
90
Ayudante
126.00 HH /DAY
MAS1
2520
Maestro de primera
18.00 HH /DAY
AYU
47
Maestro de primera
9.00 HH /DAY
Ayudante
MAS1
90
27.00 HH /DAY
1.1.2.2
50
Maestro de segunda
9.00 HH /DAY
1.1.2.1
90
Grua pluma
5.00 HM /DAY
1.1.1.4
270
Roce
360
Ayudante
64
189.00 HH /DAY
MAS1
Maestro de primera
27.00 HH /DAY
1.1.2.3
10 10
1701
AYU
243
Excavacin de escarpe
Ayudante
216.00 HH /DAY
RETRO
2160
Retroexcavadora
54.00 HM /DAY
540
1.1.2.4
10 10
MAS2
Maestro de segunda
99.00 HH /DAY
AYU
180
990
Ayudante
297.00 HH /DAY
2970
180
65
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:36
Schedule Report with Resource Usage
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----1.1.3.1
40 40
MAS1
Construccin de atagua
1080
Maestro de segunda
27.00 HH /DAY
AYU
Maestro de primera
27.00 HH /DAY
MAS2
1080
Ayudante
81.00 HH /DAY
3240
720
Retroexcavadora
45.00 HM /DAY
1800
MOTNI Motoniveladora
27.00 HM /DAY
MIX
1080
Mixers
120
1080
66
1.1.3.2
20 20
1.1.3.4
10 10
30
1.1.3.5
30
1.3.1.1
Excavaciones subterrneas
RETRO
30
Retroexcavadora
9.00 HM /DAY
1.3.2.4
10 10
MAS1
Hormign proyectado
MAS1
180
360
44
Maestro de primera
9.00 HH /DAY
AYU
39
Ayudante
36.00 HH /DAY
1.3.2.1
Maestro de primera
18.00 HH /DAY
AYU
18
45
Ayudante
18.00 HH /DAY
90
67
PLUM
Grua pluma
9.00 HM /DAY
45
1.3.2.2
1.3.2.3
MAS1
MAS2
AYU
1.2.1.1
21 21
90
90
Ayudante
36.00 HH /DAY
44
Maestro de segunda
18.00 HH /DAY
44
Maestro de primera
18.00 HH /DAY
1.1.3.3
180
68
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:36
Schedule Report with Resource Usage
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----RETRO
Retroexcavadora
432.00 HM /DAY
9072
MOTNI Motoniveladora
108.00 HM /DAY
1.2.1.3
12 12
2268
MOTNI Motoniveladora
36.00 HM /DAY
RETRO
Retroexcavadora
144.00 HM /DAY
1.2.1.2
11 11
RETRO
432
1728
10
Retroexcavadora
108.00 HM /DAY
1188
MOTNI Motoniveladora
27.00 HM /DAY
297
69
1.2.1.4
10 10
RETRO
11
Retroexcavadora
108.00 HM /DAY
1080
MOTNI Motoniveladora
27.00 HM /DAY
270
1.3.2.5
20 20
1.4.1.1
10 10
MAS2
AYU
MAS1
53
3240
3240
35
Maestro de segunda
180.00 HH /DAY
AYU
Ayudante
180.00 HH /DAY
MAS2
810
Maestro de primera
AYU
10 10
810
180.00 HH /DAY
1.4.1.2
53
Ayudante
81.00 HH /DAY
18 18
39
Maestro de segunda
81.00 HH /DAY
1.4.2.1
1800
Ayudante
70
180.00 HH /DAY
1.4.2.2
18 18
MAS1
35
Maestro de primera
225.00 HH /DAY
AYU
4050
Ayudante
225.00 HH /DAY
1.4.3.2
1800
10 10
MIX
4050
35
Mixers
120
1.4.3.1
MIX
1080
53
Mixers
48
71
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:36
Schedule Report with Resource Usage
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----BOMBA Bomba para hormign
54.00 HM /DAY
1.3.1.2
1.3.3.1
15 15
1.3.3.2
MAS1
39
47
Maestro de primera
126
Maestro de segunda
18.00 HH /DAY
AYU
18.00 HH /DAY
MAS2
432
126
Ayudante
18.00 HH /DAY
126
72
1.3.3.3
1.2.2.2
MAS1
MAS1
AYU
42
Maestro de primera
252
Ayudante
144.00 HH /DAY
360
36.00 HH /DAY
1.5.1.1
90
Ayudante
72.00 HH /DAY
1.2.2.3
Maestro de primera
18.00 HH /DAY
AYU
49
1008
53
Retroexcavadora
54.00 HM /DAY
1.5.1.2
135
270
35
252
Retroexcavadora
72.00 HM /DAY
504
73
1.2.3.2
36
MOTNI Motoniveladora
54.00 HM /DAY
1.4.1.3
21 21
MAS2
AYU
MAS1
3780
Ayudante
180.00 HH /DAY
28 28
Maestro de segunda
180.00 HH /DAY
1.4.2.3
108
3780
Maestro de primera
Ayudante
74
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:36
Schedule Report with Resource Usage
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- -----
1.5.2.1
MAS2
AYU
AYU
35
162
Ayudante
27.00 HH /DAY
MAS2
Maestro de segunda
27.00 HH /DAY
10 10
90
MAS2
1.5.3.1
90
Ayudante
18.00 HH /DAY
53
Maestro de segunda
18.00 HH /DAY
1.5.2.2
162
53
Maestro de segunda
75
144.00 HH /DAY
AYU
Ayudante
144.00 HH /DAY
1.5.4.1
1440
80 80
MAS1
1440
53
Maestro de primera
Ayudante
1.4.3.3
19 19
MIX
Mixers
228
1.5.3.2
Moldaje plinto
MAS2
Maestro de segunda
90.00 HH /DAY
AYU
77 77
MAS1
35
810
Ayudante
90.00 HH /DAY
1.5.4.2
2052
810
Enfierradura plinto
35
Maestro de primera
Ayudante
76
1.5.1.3
Retroexcavadora
81.00 HM /DAY
1.5.2.3
AYU
189
Ayudante
27.00 HH /DAY
MAS2
Maestro de segunda
27.00 HH /DAY
29 29
567
MAS2
1.5.3.3
287
189
Maestro de segunda
77
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:36
Schedule Report with Resource Usage
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----AYU
Ayudante
1.5.4.3
96 96
MAS1
Maestro de primera
Ayudante
1.5.5.3
87 87
MIX
53
Mixers
1131
1.5.5.1
29 29
78
MIX
Mixers
116
1.5.5.2
12 12
MIX
1044
Hormigonado plinto
35
Mixers
36
1.2.2.1
15 15
MAS1
Relleno plinto
AYU
35
1215
Ayudante
324.00 HH /DAY
Maestro de primera
81.00 HH /DAY
1.2.3.1
324
4860
35
36
MOTNI Motoniveladora
54.00 HM /DAY
1.6.1.1
20 20
MAS1
108
Terminaciones de estructuras
Maestro de primera
79
270.00 HH /DAY
1.6.1.2
10 10
AYU
Limpieza de superficies
10 10
MAS2
AYU
2880
Ayudante
MAS2
2880
Pinturas
Maestro de segunda
315.00 HH /DAY
AYU
Maestro de segunda
288.00 HH /DAY
7560
Aplicacin de antixidos
288.00 HH /DAY
1.6.1.4
Ayudante
756.00 HH /DAY
1.6.1.3
5400
2835
Ayudante
315.00 HH /DAY
2835
80
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
19:36
Schedule Report with Resource Usage
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- ----ACTIVITY ORIG REM
ID
DUR DUR
ACTIVITY DESCRIPTION
CODE
EARLY EARLY
START FINISH
LATE
LATE TOTAL
----- ----- ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- -----
1.7.1.1
Instalacin de tuberas
MAS1
Maestro de primera
63.00 HH /DAY
AYU
378
Ayudante
63.00 HH /DAY
378
1.7.2.1
20 20
Instalacin de equipamiento
1.7.3.1
10 10
Pruebas de servicio
1.8.1.1
20 20
81
1.8.2.1
20 20
1.8.3.1
40 40
82
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:44
Resource Control - Detail by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.1.1.1
Instalacin de campamentos
RD 60 ES 22SEP15 EF 14DEC15 LS 22SEP15 LF 14DEC15 TF 0
AYU
HH
9720.00
.0
.00
.00
9720.00
9720.00
.00
MAS1
HH
3240.00
.0
.00
.00
3240.00
3240.00
.00
MAS2
HH
3240.00
.0
.00
.00
3240.00
3240.00
.00
PLUM
HM
1080.00
.0
.00
.00
1080.00
1080.00
.00
1.1.1.2
17280.00
.0
.00
.00
17280.00
17280.00
.00
TOTAL :
1.1.1.3
.00
.0
.00
.00
.00
.00
.00
83
AYU
HH
270.00
.0
.00
.00
270.00
270.00
.00
MAS1
HH
90.00
.0
.00
.00
90.00
90.00
.00
PLUM
HM
50.00
.0
.00
.00
50.00
50.00
.00
MAS2
HH
90.00
.0
.00
.00
90.00
90.00
.00
1.1.1.4
500.00
.0
.00
.00
500.00
500.00
.00
AYU
HH
270.00
.0
.00
.00
270.00
270.00
.00
MAS1
HH
90.00
.0
.00
.00
90.00
90.00
.00
PLUM
HM
50.00
.0
.00
.00
50.00
50.00
.00
MAS2
HH
90.00
.0
.00
.00
90.00
90.00
.00
1.1.2.1
500.00
.0
.00
.00
500.00
500.00
.00
AYU
HH
MAS1
HH
2520.00
.0
.00
.00
2520.00
2520.00
360.00
.0
.00
.00
360.00
360.00
.00
.00
1.1.2.2
2880.00
.0
.00
.00
2880.00
2880.00
.00
Roce
RD
AYU
MAS1
HH
HH
1701.00
.0
.00
.00
1701.00
1701.00
243.00
.0
.00
.00
243.00
243.00
.00
.00
84
1.1.2.3
1944.00
.0
.00
.00
1944.00
1944.00
.00
Excavacin de escarpe
RD 10 ES 2FEB16 EF 15FEB16 LS 2FEB16 LF 15FEB16 TF 0
AYU
HH
2160.00
.0
.00
.00
2160.00
2160.00
.00
RETRO
HM
540.00
.0
.00
.00
540.00
540.00
.00
TOLVA
HM
180.00
.0
.00
.00
180.00
180.00
.00
1.1.2.4
2880.00
.0
.00
.00
2880.00
2880.00
.00
.00
MAS2
AYU
TOLVA
HH
HH
HM
990.00
.0
.00
.00
990.00
990.00
2970.00
.0
.00
.00
2970.00
2970.00
.00
180.00
180.00
.00
180.00
.0
.00
.00
4140.00
.0
.00
.00
4140.00
4140.00
.00
85
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:44
Resource Control - Detail by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.1.3.1
Construccin de atagua
RD 40 ES 1MAR16 EF 25APR16 LS 1MAR16 LF 25APR16 TF 0
MAS1
HH
1080.00
.0
.00
.00
1080.00
1080.00
.00
MAS2
HH
1080.00
.0
.00
.00
1080.00
1080.00
.00
AYU
HH
3240.00
.0
.00
.00
720.00
720.00
.00
720.00
RETRO
HM
1800.00
.0
.00
.00
1800.00
1800.00
.00
MOTNI
HM
1080.00
.0
.00
.00
1080.00
1080.00
.00
BOMBA
HM
120.00
.0
1080.00
.00
3240.00
HM
Cam
.00
3240.00
TOLVA
MIX
.0
.00
.00
.0
.00
.00
120.00
.00
120.00
1080.00
1080.00
.00
.00
1.1.3.2
10200.00
.0
.00
.00
10200.00
10200.00
.00
TOTAL :
.00
.0
.00
.00
.00
.00
.00
86
1.1.3.3
TOTAL :
1.1.3.4
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.1.3.5
.00
.00
.00
.00
TOTAL :
1.2.1.1
.0
.00
.0
.00
.00
.00
RETRO
HM
9072.00
.0
.00
.00
9072.00
9072.00
.00
MOTNI
HM
2268.00
.0
.00
.00
2268.00
2268.00
.00
1.2.1.2
11340.00
.0
.00
.00
11340.00
11340.00
.00
RETRO
HM
1188.00
.0
.00
.00
1188.00
1188.00
MOTNI
HM
297.00
.0
.00
.00
297.00
297.00
.00
.00
1485.00
.0
.00
.00
1485.00
1485.00
.00
87
1.2.1.3
MOTNI
HM
432.00
.0
.00
.00
432.00
432.00
RETRO
HM
1728.00
.0
.00
.00
1728.00
1728.00
.00
.00
1.2.1.4
2160.00
.0
.00
.00
2160.00
2160.00
.00
RETRO
HM
1080.00
.0
.00
.00
1080.00
1080.00
MOTNI
HM
270.00
.0
.00
.00
270.00
270.00
.00
.00
1350.00
.0
.00
.00
1350.00
1350.00
.00
88
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:44
Resource Control - Detail by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.2.2.1
Relleno plinto
RD 15 ES 7NOV16 EF 25NOV16 LS 26DEC16 LF 13JAN17 TF 35
MAS1
AYU
HH
HH
1215.00
4860.00
.0
.0
.00
.00
.00
.00
1215.00
4860.00
1215.00
.00
4860.00
.00
1.2.2.2
6075.00
.0
.00
.00
6075.00
6075.00
.00
MAS1
AYU
HH
HH
90.00
.0
.00
.00
90.00
90.00
360.00
.0
.00
.00
360.00
360.00
.00
.00
1.2.2.3
450.00
.0
.00
.00
450.00
450.00
.00
89
MAS1
AYU
HH
HH
252.00
.0
.00
.00
252.00
252.00
1008.00
.0
.00
.00
1008.00
1008.00
.00
.00
1.2.3.1
1260.00
.0
.00
.00
1260.00
1260.00
.00
TOLVA
HM
36.00
.0
MOTNI
HM
108.00
.00
.0
.00
.00
36.00
.00
108.00
36.00
.00
108.00
.00
1.2.3.2
144.00
.0
.00
.00
144.00
144.00
.00
36.00
.00
TOLVA
HM
36.00
.0
MOTNI
HM
108.00
.00
.0
.00
.00
.00
36.00
108.00
108.00
.00
1.3.1.1
144.00
.0
.00
.00
144.00
144.00
.00
.00
Excavaciones subterrneas
RD
RETRO
HM
9.00
.0
.00
.00
9.00
9.00
TOLVA
HM
18.00
.0
.00
.00
18.00
18.00
.00
1.3.1.2
27.00
.0
.00
.00
27.00
27.00
.00
90
TOTAL :
1.3.2.1
.00
.0
.00
.00
.00
.00
.00
MAS1
AYU
HH
HH
PLUM
HM
45.00
90.00
.0
.0
45.00
.00
.00
.0
.00
.00
.00
.00
45.00
90.00
45.00
.00
90.00
45.00
.00
45.00
.00
1.3.2.2
180.00
.0
.00
.00
180.00
180.00
.00
TOTAL :
.00
.0
.00
.00
.00
.00
.00
91
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:44
Resource Control - Detail by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.3.2.3
MAS1
HH
90.00
.0
.00
.00
90.00
90.00
.00
MAS2
HH
90.00
.0
.00
.00
90.00
90.00
.00
180.00
.0
.00
.00
180.00
180.00
AYU
HH
.00
1.3.2.4
360.00
.0
.00
.00
360.00
360.00
.00
Hormign proyectado
RD 10 ES 11MAY16 EF 24MAY16 LS 5JUL16 LF 18JUL16 TF 39
MAS1
AYU
HH
HH
180.00
360.00
.0
.00
.0
.00
.00
.00
180.00
360.00
180.00
.00
360.00
.00
1.3.2.5
540.00
.0
.00
.00
540.00
540.00
.00
92
TOTAL :
1.3.3.1
.00
.0
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.3.3.2
.00
.0
.00
.00
.00
MAS1
HH
126.00
.0
.00
.00
126.00
126.00
.00
MAS2
HH
126.00
.0
.00
.00
126.00
126.00
.00
AYU
HH
126.00
.0
.00
.00
126.00
126.00
.00
1.3.3.3
378.00
.00
.00
378.00
378.00
.00
TOTAL :
1.4.1.1
.0
.00
.0
.00
.00
.00
.00
.00
MAS2
AYU
HH
HH
810.00
810.00
.0
.0
.00
.00
.00
.00
810.00
810.00
810.00
810.00
.00
.00
1.4.1.2
1620.00
.0
.00
.00
1620.00
1620.00
.00
93
MAS2
AYU
HH
HH
1800.00
1800.00
.0
.0
.00
.00
.00
.00
1800.00
1800.00
1800.00
1800.00
.00
.00
1.4.1.3
3600.00
.0
.00
.00
3600.00
3600.00
.00
MAS2
AYU
HH
HH
3780.00
3780.00
.0
.0
.00
.00
.00
.00
3780.00
3780.00
3780.00
3780.00
.00
.00
7560.00
.0
.00
.00
7560.00
7560.00
.00
94
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:44
Resource Control - Detail by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.4.2.1
MAS1
AYU
HH
HH
3240.00
3240.00
.0
.0
.00
.00
.00
.00
3240.00
3240.00
3240.00
3240.00
.00
.00
1.4.2.2
6480.00
.0
.00
.00
6480.00
6480.00
.00
MAS1
AYU
HH
HH
4050.00
4050.00
.0
.0
.00
.00
.00
.00
4050.00
4050.00
4050.00
4050.00
.00
.00
1.4.2.3
8100.00
.0
.00
.00
8100.00
8100.00
.00
95
MAS1
AYU
HH
HH
22680.00
.0
22680.00
.00
.0
.00
.00
22680.00
.00
22680.00
22680.00
.00
22680.00
.00
1.4.3.1
45360.00
.0
.00
.00
45360.00
45360.00
.00
MIX
Cam
BOMBA
48.00
HM
.0
432.00
.00
.0
.00
.00
48.00
.00
48.00
432.00
.00
432.00
.00
1.4.3.2
480.00
.0
.00
.00
480.00
480.00
.00
MIX
Cam
BOMBA
HM
120.00
.0
1080.00
.00
.0
.00
.00
120.00
.00
120.00
1080.00
.00
1080.00
.00
1.4.3.3
1200.00
.0
.00
.00
1200.00
1200.00
.00
MIX
Cam
BOMBA
HM
228.00
.0
2052.00
.00
.0
.00
.00
228.00
.00
228.00
2052.00
.00
2052.00
.00
1.5.1.1
2280.00
.0
.00
.00
2280.00
2280.00
.00
96
TOLVA
HM
135.00
.0
.00
.00
135.00
135.00
.00
RETRO
HM
270.00
.0
.00
.00
270.00
270.00
.00
1.5.1.2
405.00
.0
.00
.00
405.00
405.00
.00
TOLVA
HM
252.00
.0
.00
.00
252.00
252.00
.00
RETRO
HM
504.00
.0
.00
.00
504.00
504.00
.00
1.5.1.3
756.00
.0
.00
.00
756.00
756.00
.00
TOLVA
HM
287.00
.0
.00
.00
287.00
287.00
.00
RETRO
HM
567.00
.0
.00
.00
567.00
567.00
.00
854.00
.0
.00
.00
854.00
854.00
.00
97
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:44
Resource Control - Detail by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.5.2.1
MAS2
AYU
HH
HH
90.00
90.00
.0
.0
.00
.00
.00
.00
90.00
90.00
90.00
90.00
.00
.00
1.5.2.2
180.00
.0
.00
.00
180.00
180.00
.00
MAS2
AYU
HH
HH
162.00
162.00
.0
.0
.00
.00
.00
.00
162.00
162.00
162.00
.00
162.00
.00
1.5.2.3
324.00
.0
.00
.00
324.00
324.00
.00
98
MAS2
AYU
HH
HH
189.00
.0
189.00
.0
.00
.00
.00
.00
189.00
189.00
189.00
.00
189.00
.00
1.5.3.1
378.00
.0
.00
.00
378.00
378.00
.00
MAS2
AYU
HH
HH
1440.00
1440.00
.0
.0
.00
.00
.00
.00
1440.00
1440.00
1440.00
1440.00
.00
.00
1.5.3.2
2880.00
.0
.00
.00
2880.00
2880.00
.00
810.00
.00
Moldaje plinto
RD
MAS2
AYU
HH
HH
810.00
810.00
.0
.0
.00
.00
.00
.00
810.00
810.00
810.00
.00
1.5.3.3
1620.00
.0
.00
.00
1620.00
1620.00
.00
MAS2
AYU
HH
HH
24534.00
24534.00
.0
.0
.00
.00
.00
.00
24534.00
24534.00
24534.00
24534.00
.00
.00
1.5.4.1
49068.00
.0
.00
.00
49068.00
49068.00
.00
99
MAS1
AYU
HH
HH
15840.00
15840.00
.0
.0
.00
.00
.00
.00
15840.00
15840.00
15840.00
15840.00
.00
.00
1.5.4.2
31680.00
.0
.00
.00
31680.00
31680.00
.00
Enfierradura plinto
RD 77 ES 21JUL16 EF 4NOV16 LS 8SEP16 LF 23DEC16 TF 35
MAS1
AYU
HH
HH
20097.00
20097.00
.0
.0
.00
.00
.00
.00
20097.00
20097.00
20097.00
20097.00
.00
.00
1.5.4.3
40194.00
.0
.00
.00
40194.00
40194.00
.00
MAS1
AYU
HH
HH
111456.00
111456.00
.0
.0
.00
.00
.00
.00
111456.00
111456.00
111456.00
111456.00
.00
.00
222912.00
.0
.00
.00
222912.00
222912.00
.00
100
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:44
Resource Control - Detail by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.5.5.1
MIX
Cam
BOMBA
HM
116.00
.0
1044.00
.00
.0
.00
.00
116.00
.00
116.00
1044.00
.00
1044.00
.00
1.5.5.2
1160.00
.0
.00
.00
1160.00
1160.00
.00
Hormigonado plinto
RD 12 ES 20OCT16 EF 4NOV16 LS 8DEC16 LF 23DEC16 TF 35
MIX
BOMBA
Cam
HM
36.00
.0
324.00
.00
.0
.00
.00
36.00
.00
324.00
36.00
.00
324.00
.00
1.5.5.3
360.00
.0
.00
.00
360.00
360.00
.00
101
MIX
Cam
BOMBA
1131.00
HM
.0
10179.00
.00
.0
.00
.00
1131.00
.00
1131.00
10179.00
.00
10179.00
.00
1.6.1.1
11310.00
.0
.00
.00
11310.00
11310.00
.00
5400.00
.00
Terminaciones de estructuras
RD 20 ES 18JAN17 EF 14FEB17 LS 18JAN17 LF 14FEB17 TF 0
MAS1
HH
5400.00
.0
.00
.00
5400.00
1.6.1.2
5400.00
.0
.00
.00
5400.00
5400.00
.00
Limpieza de superficies
RD 10 ES 15FEB17 EF 28FEB17 LS 15FEB17 LF 28FEB17 TF 0
AYU
HH
7560.00
.0
.00
.00
7560.00
7560.00
.00
1.6.1.3
7560.00
.0
.00
.00
7560.00
7560.00
.00
Aplicacin de antixidos
RD 10 ES 1MAR17 EF 14MAR17 LS 1MAR17 LF 14MAR17 TF 0
MAS2
AYU
HH
HH
2880.00
2880.00
.0
.0
.00
.00
.00
.00
2880.00
2880.00
2880.00
2880.00
.00
.00
1.6.1.4
5760.00
.0
.00
.00
5760.00
5760.00
.00
Pinturas
RD
MAS2
HH
2835.00
.0
.00
.00
2835.00
2835.00
.00
102
AYU
HH
2835.00
.0
.00
.00
2835.00
2835.00
.00
1.7.1.1
5670.00
.0
.00
.00
5670.00
5670.00
.00
378.00
.00
Instalacin de tuberas
RD
MAS1
AYU
HH
HH
378.00
378.00
.0
.0
.00
.00
.00
.00
378.00
378.00
378.00
.00
1.7.2.1
756.00
.0
.00
.00
756.00
756.00
.00
Instalacin de equipamiento
RD 20 ES 28MAR17 EF 24APR17 LS 28MAR17 LF 24APR17 TF 0
TOTAL :
.00
.0
.00
.00
.00
.00
.00
103
------------------------------------------------------------------------------------------------ ----------------------------------C.S.Soluciones
Represa
18:44
Resource Control - Detail by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.7.3.1
Pruebas de servicio
RD 10 ES 25APR17 EF 8MAY17 LS 25APR17 LF 8MAY17 TF 0
TOTAL :
1.8.1.1
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.8.2.1
.00
.0
.00
.00
.00
TOTAL :
1.8.3.1
.00
.0
.00
.00
.00
104
TOTAL :
.00
.0
.00
.00
.00
.00
.00
532124.00
.0
.00
.00
532124.00
532124.00
.00
==================================================================================================
=================================
105
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:44
Resource Control - Summary by Resource
----------------------------------------------------------------------------------------------------------------------------------UNIT
RESOURCE
VARIANCE
PCT
MEAS
ACTUAL
BUDGET
ACTUAL ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
AYU
- Ayudante
TOTAL AYU
HH
254466.00
.0
.00
.00
254466.00
254466.00
.00
MAS1
HM
.0
.00
.00
16191.00
16191.00
.00
.00
- Maestro de primera
TOTAL MAS1
MAS2
HH
190242.00
.0
.00
.00
190242.00
190242.00
HH
45036.00
.0
.00
.00
45036.00
45036.00
Cam
1799.00
- Maestro de segunda
TOTAL MAS2
MIX
16191.00
.00
- Mixers
TOTAL MIX
.0
.00
.00
1799.00
1799.00
.00
MOTNI - Motoniveladora
TOTAL MOTNI
HM
4563.00
.0
.00
.00
4563.00
4563.00
.00
106
PLUM
- Grua pluma
TOTAL PLUM
RETRO
HM
1225.00
.0
.00
.00
1225.00
1225.00
.00
- Retroexcavadora
TOTAL RETRO
HM
16758.00
HM
1844.00
.0
.00
.00
16758.00
16758.00
.00
.0
.00
.00
1844.00
1844.00
.00
532124.00
.0
.00
.00
532124.00
532124.00
.00
==================================================================================================
=================================
107
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:45
Resource Control - Detail by Resource
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
AYU
- Ayudante
1.1.1.1 AYU
HH
9720.00
.0
.00
.00
9720.00
9720.00
.00
1.1.1.3 AYU
HH
270.00
.0
.00
.00
270.00
270.00
.00
1.1.1.4 AYU
HH
270.00
.0
.00
.00
270.00
270.00
.00
1.1.2.1 AYU
HH
2520.00
.0
.00
.00
2520.00
2520.00
.00
1.1.2.2 AYU
HH
1701.00
.0
.00
.00
1701.00
1701.00
.00
1.1.2.3 AYU
HH
2160.00
.0
.00
.00
2160.00
2160.00
.00
1.1.2.4 AYU
HH
2970.00
.0
.00
.00
2970.00
2970.00
.00
1.1.3.1 AYU
HH
3240.00
.0
.00
.00
3240.00
3240.00
.00
1.2.2.1 AYU
HH
4860.00
.0
.00
.00
4860.00
4860.00
.00
1.2.2.2 AYU
HH
360.00
.0
.00
.00
360.00
360.00
1.2.2.3 AYU
HH
1008.00
.0
.00
.00
1008.00
1008.00
1.3.2.1 AYU
HH
90.00
.0
.00
.00
90.00
90.00
1.3.2.3 AYU
HH
180.00
.0
.00
.00
180.00
180.00
.00
1.3.2.4 AYU
HH
360.00
.0
.00
.00
360.00
360.00
.00
.00
.00
.00
108
1.3.3.2 AYU
HH
126.00
.0
.00
.00
126.00
126.00
.00
1.4.1.1 AYU
HH
810.00
.0
.00
.00
810.00
810.00
.00
1.4.1.2 AYU
HH
1800.00
.0
.00
.00
1800.00
1800.00
.00
1.4.1.3 AYU
HH
3780.00
.0
.00
.00
3780.00
3780.00
.00
1.4.2.1 AYU
HH
3240.00
.0
.00
.00
3240.00
3240.00
.00
1.4.2.2 AYU
HH
4050.00
.0
.00
.00
4050.00
4050.00
.00
1.4.2.3 AYU
HH
22680.00
.0
.00
.00
22680.00
22680.00
1.5.2.1 AYU
HH
90.00
.0
.00
.00
90.00
90.00
1.5.2.2 AYU
HH
162.00
.0
.00
.00
162.00
162.00
.00
1.5.2.3 AYU
HH
189.00
.0
.00
.00
189.00
189.00
.00
1.5.3.1 AYU
HH
1440.00
.0
.00
.00
1440.00
1440.00
1.5.3.2 AYU
HH
810.00
.0
.00
.00
810.00
810.00
1.5.3.3 AYU
HH
24534.00
.0
.00
.00
24534.00
24534.00
.00
1.5.4.1 AYU
HH
15840.00
.0
.00
.00
15840.00
15840.00
.00
1.5.4.2 AYU
HH
20097.00
.0
.00
.00
20097.00
20097.00
.00
1.5.4.3 AYU
HH
111456.00
.0
.00
.00
111456.00
111456.00
1.6.1.2 AYU
HH
7560.00
.0
.00
.00
7560.00
7560.00
.00
1.6.1.3 AYU
HH
2880.00
.0
.00
.00
2880.00
2880.00
.00
1.6.1.4 AYU
HH
2835.00
.0
.00
.00
2835.00
2835.00
.00
1.7.1.1 AYU
HH
378.00
.0
.00
.00
378.00
378.00
.00
.00
.00
.00
.00
.00
HH
254466.00
.0
.00
.00
254466.00
254466.00
.00
==================================================================================================
=================================
1.1.3.1
BOMBA
HM
1080.00
.0
.00
.00
1080.00
1080.00
.00
1.4.3.1
BOMBA
HM
432.00
.0
.00
.00
432.00
432.00
1.4.3.2
BOMBA
HM
1080.00
.0
.00
.00
1080.00
1080.00
.00
1.4.3.3
BOMBA
HM
2052.00
.0
.00
.00
2052.00
2052.00
.00
.00
109
1.5.5.1
BOMBA
HM
1044.00
.0
.00
.00
1044.00
1044.00
1.5.5.2
BOMBA
HM
324.00
.0
.00
.00
324.00
324.00
1.5.5.3
BOMBA
HM
10179.00
.0
.00
.00
10179.00
.00
.00
10179.00
.00
HM
16191.00
.0
.00
.00
16191.00
16191.00
.00
==================================================================================================
=================================
MAS1
- Maestro de primera
1.1.1.1
MAS1
HH
3240.00
.0
.00
.00
3240.00
3240.00
.00
1.1.1.3
MAS1
HH
90.00
.0
.00
.00
90.00
90.00
.00
1.1.1.4
MAS1
HH
90.00
.0
.00
.00
90.00
90.00
.00
1.1.2.1
MAS1
HH
360.00
.0
.00
.00
360.00
360.00
.00
1.1.2.2
MAS1
HH
243.00
.0
.00
.00
243.00
243.00
.00
1.1.3.1
MAS1
HH
1080.00
.0
.00
.00
1080.00
1080.00
.00
1.2.2.1
MAS1
HH
1215.00
.0
.00
.00
1215.00
1215.00
.00
1.2.2.2
MAS1
HH
90.00
.0
.00
.00
90.00
90.00
1.2.2.3
MAS1
HH
252.00
.0
.00
.00
252.00
252.00
1.3.2.1
MAS1
HH
45.00
.0
.00
.00
45.00
45.00
.00
1.3.2.3
MAS1
HH
90.00
.0
.00
.00
90.00
90.00
.00
1.3.2.4
MAS1
HH
180.00
.0
.00
.00
180.00
180.00
.00
1.3.3.2
MAS1
HH
126.00
.0
.00
.00
126.00
126.00
.00
1.4.2.1
MAS1
HH
3240.00
.0
.00
.00
3240.00
3240.00
.00
.00
.00
110
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:45
Resource Control - Detail by Resource
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.4.2.2
MAS1
HH
4050.00
.0
.00
.00
4050.00
4050.00
.00
1.4.2.3
MAS1
HH
22680.00
.0
.00
.00
22680.00
22680.00
.00
1.5.4.1
MAS1
HH
15840.00
.0
.00
.00
15840.00
15840.00
.00
1.5.4.2
MAS1
HH
20097.00
.0
.00
.00
20097.00
20097.00
.00
1.5.4.3
MAS1
HH
111456.00
.0
.00
.00
111456.00
111456.00
1.6.1.1
MAS1
HH
5400.00
.0
.00
.00
5400.00
5400.00
1.7.1.1
MAS1
HH
378.00
.0
.00
.00
378.00
378.00
.00
.00
.00
HH
190242.00
.0
.00
.00
190242.00
190242.00
.00
==================================================================================================
=================================
MAS2
- Maestro de segunda
1.1.1.1
MAS2
HH
3240.00
.0
.00
.00
3240.00
3240.00
.00
1.1.1.3
MAS2
HH
90.00
.0
.00
.00
90.00
90.00
.00
1.1.1.4
MAS2
HH
90.00
.0
.00
.00
90.00
90.00
.00
1.1.2.4
MAS2
HH
990.00
.0
.00
.00
990.00
990.00
.00
111
1.1.3.1
MAS2
HH
1080.00
.0
.00
.00
1080.00
1080.00
.00
1.3.2.3
MAS2
HH
90.00
.0
.00
.00
90.00
90.00
1.3.3.2
MAS2
HH
126.00
.0
.00
.00
126.00
126.00
.00
1.4.1.1
MAS2
HH
810.00
.0
.00
.00
810.00
810.00
.00
1.4.1.2
MAS2
HH
1800.00
.0
.00
.00
1800.00
1800.00
.00
1.4.1.3
MAS2
HH
3780.00
.0
.00
.00
3780.00
3780.00
.00
1.5.2.1
MAS2
HH
90.00
.0
.00
.00
90.00
90.00
1.5.2.2
MAS2
HH
162.00
.0
.00
.00
162.00
162.00
.00
1.5.2.3
MAS2
HH
189.00
.0
.00
.00
189.00
189.00
.00
1.5.3.1
MAS2
HH
1440.00
.0
.00
.00
1440.00
1440.00
1.5.3.2
MAS2
HH
810.00
.0
.00
.00
810.00
810.00
1.5.3.3
MAS2
HH
24534.00
.0
.00
.00
24534.00
24534.00
1.6.1.3
MAS2
HH
2880.00
.0
.00
.00
2880.00
2880.00
.00
1.6.1.4
MAS2
HH
2835.00
.0
.00
.00
2835.00
2835.00
.00
.00
.00
.00
.00
.00
HH
45036.00
.0
.00
.00
45036.00
45036.00
.00
==================================================================================================
=================================
MIX
- Mixers
1.1.3.1
MIX
Cam
120.00
.0
.00
.00
120.00
120.00
1.4.3.1
MIX
Cam
48.00
.0
.00
.00
48.00
48.00
1.4.3.2
MIX
Cam
120.00
.0
.00
.00
120.00
120.00
.00
1.4.3.3
MIX
Cam
228.00
.0
.00
.00
228.00
228.00
.00
1.5.5.1
MIX
Cam
116.00
.0
.00
.00
116.00
116.00
.00
1.5.5.2
MIX
Cam
36.00
.0
.00
.00
36.00
36.00
1.5.5.3
MIX
Cam
1131.00
.0
.00
.00
1131.00
1131.00
.00
.00
.00
.00
Cam
1799.00
.0
.00
.00
1799.00
1799.00
.00
112
==================================================================================================
=================================
MOTNI - Motoniveladora
1.1.3.1
MOTNI
HM
1080.00
.0
.00
.00
1080.00
1080.00
.00
1.2.1.1
MOTNI
HM
2268.00
.0
.00
.00
2268.00
2268.00
.00
1.2.1.2
MOTNI
HM
297.00
.0
.00
.00
297.00
297.00
.00
1.2.1.3
MOTNI
HM
432.00
.0
.00
.00
432.00
432.00
.00
1.2.1.4
MOTNI
HM
270.00
.0
.00
.00
270.00
270.00
.00
1.2.3.1
MOTNI
HM
108.00
.0
.00
.00
108.00
108.00
.00
1.2.3.2
MOTNI
HM
108.00
.0
.00
.00
108.00
108.00
.00
HM
4563.00
.0
.00
.00
4563.00
4563.00
.00
==================================================================================================
=================================
PLUM
- Grua pluma
1.1.1.1
PLUM
HM
1080.00
.0
.00
.00
1080.00
1080.00
.00
1.1.1.3
PLUM
HM
50.00
.0
.00
.00
50.00
50.00
.00
1.1.1.4
PLUM
HM
50.00
.0
.00
.00
50.00
50.00
.00
1.3.2.1
PLUM
HM
45.00
.0
.00
.00
45.00
45.00
.00
HM
1225.00
.0
.00
.00
1225.00
1225.00
.00
==================================================================================================
=================================
113
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:45
Resource Control - Detail by Resource
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL ESTIMATE TO
BUDGET
COMPLETE
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
RETRO
- Retroexcavadora
1.1.2.3
RETRO
HM
540.00
.0
.00
.00
540.00
540.00
1.1.3.1
RETRO
HM
1800.00
.0
.00
.00
1800.00
1800.00
.00
1.2.1.1
RETRO
HM
9072.00
.0
.00
.00
9072.00
9072.00
.00
1.2.1.2
RETRO
HM
1188.00
.0
.00
.00
1188.00
1188.00
.00
1.2.1.3
RETRO
HM
1728.00
.0
.00
.00
1728.00
1728.00
.00
1.2.1.4
RETRO
HM
1080.00
.0
.00
.00
1080.00
1080.00
.00
1.3.1.1
RETRO
HM
9.00
1.5.1.1
RETRO
HM
270.00
.0
.00
.00
270.00
270.00
.00
1.5.1.2
RETRO
HM
504.00
.0
.00
.00
504.00
504.00
.00
1.5.1.3
RETRO
HM
567.00
.0
.00
.00
567.00
567.00
.00
.0
.00
.00
9.00
9.00
.00
.00
HM
16758.00
.0
.00
.00
16758.00
16758.00
.00
==================================================================================================
=================================
114
1.1.2.3 TOLVA
HM
180.00
.0
.00
.00
180.00
180.00
.00
1.1.2.4 TOLVA
HM
180.00
.0
.00
.00
180.00
180.00
.00
1.1.3.1 TOLVA
HM
720.00
.0
.00
.00
720.00
720.00
.00
1.2.3.1 TOLVA
HM
36.00
.0
.00
.00
36.00
36.00
.00
1.2.3.2 TOLVA
HM
36.00
.0
.00
.00
36.00
36.00
.00
1.3.1.1 TOLVA
HM
18.00
.0
.00
.00
18.00
18.00
.00
1.5.1.1 TOLVA
HM
135.00
.0
.00
.00
135.00
135.00
.00
1.5.1.2 TOLVA
HM
252.00
.0
.00
.00
252.00
252.00
.00
1.5.1.3 TOLVA
HM
287.00
.0
.00
.00
287.00
287.00
.00
HM
1844.00
.0
.00
.00
1844.00
1844.00
.00
==================================================================================================
=================================
532124.00
.0
.00
.00
532124.00
532124.00
.00
==================================================================================================
=================================
115
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:45
Resource Control - Summary by Activity
1
-----------------------------------------------------------------------------------------------------------------------------------
ACTIVITY ID
VARIANCE
PCT
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.1.1.1
Instalacin de campamentos
RD 60 ES 22SEP15 EF 14DEC15 LS 22SEP15 LF 14DEC15 TF
TOTAL :
1.1.1.2
17280.00
.0
.00
.00
17280.00
.00
TOTAL :
1.1.1.3
17280.00
.00
.0
.00
.00
.00
.00
.00
TOTAL :
1.1.1.4
500.00
.0
.00
.00
500.00
500.00
.00
116
TOTAL :
1.1.2.1
500.00
.0
.00
.00
500.00
TOTAL :
.0
.00
.00
TOTAL :
1.1.2.4
2880.00
.00
1944.00
.0
.00
.00
1944.00
1944.00
.00
2880.00
.00
4140.00
.00
Excavacin de escarpe
RD 10 ES 2FEB16 EF 15FEB16 LS 2FEB16 LF 15FEB16 TF
TOTAL :
2880.00
2880.00
.0
.00
.00
TOTAL :
4140.00
.0
.00
.00
4140.00
Construccin de atagua
RD 40 ES 1MAR16 EF 25APR16 LS 1MAR16 LF 25APR16 TF
TOTAL :
1.1.3.2
2880.00
1.1.3.1
2880.00
Roce
RD
1.1.2.3
.00
1.1.2.2
500.00
10200.00
.0
.00
.00
10200.00
10200.00
.00
117
TOTAL :
1.1.3.4
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.1.3.5
.0
.00
.00
.00
TOTAL :
1.3.1.1
.00
.00
.0
.00
.00
.00
Excavaciones subterrneas
RD
TOTAL :
27.00
.0
.00
.00
27.00
27.00
.00
118
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:45
Resource Control - Summary by Activity
2
-----------------------------------------------------------------------------------------------------------------------------------
ACTIVITY ID
VARIANCE
PCT
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.3.2.4
Hormign proyectado
RD 10 ES 11MAY16 EF 24MAY16 LS 5JUL16 LF 18JUL16 TF 39
TOTAL :
1.3.2.1
.00
.00
540.00
540.00
.00
180.00
.00
TOTAL :
180.00
.0
.00
.00
180.00
TOTAL :
1.3.2.3
.0
1.3.2.2
540.00
.00
.0
.00
.00
.00
.00
.00
119
TOTAL :
1.1.3.3
.0
.00
.00
360.00
TOTAL :
.00
.0
.00
.00
.00
.00
.00
TOTAL :
11340.00
.0
.00
.00
11340.00
11340.00
.00
TOTAL :
1.2.1.2
.00
1.2.1.3
360.00
1.2.1.1
360.00
2160.00
.0
.00
.00
2160.00
2160.00
.00
1485.00
.00
1350.00
.00
TOTAL :
1.2.1.4
1485.00
.0
.00
.00
1485.00
TOTAL :
1.3.2.5
1350.00
.0
.00
.00
1350.00
TOTAL :
.00
.0
.00
.00
.00
.00
.00
120
1.4.1.1
TOTAL :
1.4.2.1
1620.00
.0
.00
.00
1620.00
1620.00
.00
6480.00
.00
3600.00
.00
TOTAL :
1.4.1.2
6480.00
.0
.00
.00
6480.00
TOTAL :
3600.00
.0
.00
.00
3600.00
121
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:45
Resource Control - Summary by Activity
3
-----------------------------------------------------------------------------------------------------------------------------------
ACTIVITY ID
VARIANCE
PCT
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.4.2.2
TOTAL :
1.4.3.2
8100.00
.0
.00
.00
8100.00
8100.00
.00
1200.00
.00
TOTAL :
1.4.3.1
.0
.00
.00
1200.00
TOTAL :
1.3.1.2
1200.00
480.00
.0
.00
.00
480.00
480.00
.00
122
TOTAL :
1.3.3.1
.00
.0
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.3.3.2
.00
378.00
.0
.00
.00
378.00
378.00
.00
TOTAL :
.00
.0
.00
.00
.00
.00
.00
TOTAL :
450.00
.0
.00
.00
450.00
450.00
.00
TOTAL :
1.5.1.1
.00
1.2.2.3
.00
TOTAL :
1.2.2.2
.0
1.3.3.3
.00
1260.00
.0
.00
.00
1260.00
1260.00
.00
TOTAL :
405.00
.0
.00
.00
405.00
405.00
.00
123
1.5.1.2
TOTAL :
1.2.3.2
.0
.00
.00
756.00
756.00
.00
144.00
144.00
.00
TOTAL :
1.4.1.3
756.00
144.00
.0
.00
.00
TOTAL :
7560.00
.0
.00
.00
7560.00
7560.00
.00
124
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:45
Resource Control - Summary by Activity
4
-----------------------------------------------------------------------------------------------------------------------------------
ACTIVITY ID
VARIANCE
PCT
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.4.2.3
1.5.2.1
TOTAL :
45360.00
.00
.00
45360.00
.00
TOTAL :
180.00
.0
.00
.00
180.00
180.00
.00
324.00
.00
TOTAL :
1.5.3.1
.0
1.5.2.2
45360.00
324.00
.0
.00
.00
324.00
125
TOTAL :
1.5.4.1
2880.00
.0
.00
.00
2880.00
2880.00
.00
TOTAL :
1.4.3.3
31680.00
.0
.00
.00
31680.00
TOTAL :
2280.00
.0
.00
.00
2280.00
2280.00
.00
1620.00
.00
Moldaje plinto
RD
TOTAL :
1.5.4.2
.00
1.5.3.2
31680.00
1620.00
.0
.00
.00
1620.00
Enfierradura plinto
RD 77 ES 21JUL16 EF 4NOV16 LS 8SEP16 LF 23DEC16 TF 35
TOTAL :
1.5.1.3
.0
.00
.00
40194.00
40194.00
.00
TOTAL :
1.5.2.3
40194.00
854.00
.0
.00
.00
854.00
854.00
.00
378.00
.00
TOTAL :
378.00
.0
.00
.00
378.00
126
1.5.3.3
1.5.4.3
TOTAL :
49068.00
49068.00
.0
.00
.00
.00
TOTAL :
1.5.5.3
49068.00
222912.00
.0
.00
.00
222912.00
222912.00
.00
TOTAL :
11310.00
11310.00
.0
.00
.00
11310.00
.00
127
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:45
Resource Control - Summary by Activity
5
-----------------------------------------------------------------------------------------------------------------------------------
ACTIVITY ID
VARIANCE
PCT
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.5.5.1
TOTAL :
1.5.5.2
1160.00
.0
.00
.00
1160.00
1160.00
.00
Hormigonado plinto
RD 12 ES 20OCT16 EF 4NOV16 LS 8DEC16 LF 23DEC16 TF 35
TOTAL :
1.2.2.1
360.00
.0
.00
.00
360.00
360.00
.00
Relleno plinto
RD 15 ES 7NOV16 EF 25NOV16 LS 26DEC16 LF 13JAN17 TF 35
TOTAL :
1.2.3.1
6075.00
.0
.00
.00
6075.00
6075.00
.00
128
TOTAL :
1.6.1.1
1.6.1.2
144.00
.0
.00
.00
144.00
TOTAL :
5400.00
5400.00
.0
.00
.00
7560.00
.0
.00
.00
7560.00
7560.00
.00
5760.00
.00
5670.00
.00
Aplicacin de antixidos
TOTAL :
5760.00
.0
.00
.00
5760.00
Pinturas
RD
TOTAL :
5670.00
.0
.00
.00
5670.00
Instalacin de tuberas
RD
TOTAL :
1.7.2.1
.00
1.7.1.1
5400.00
Limpieza de superficies
TOTAL :
1.6.1.4
.00
Terminaciones de estructuras
1.6.1.3
144.00
756.00
.0
.00
.00
756.00
756.00
.00
Instalacin de equipamiento
RD 20 ES 28MAR17 EF 24APR17 LS 28MAR17 LF 24APR17 TF
TOTAL :
.00
.0
.00
.00
.00
.00
.00
129
1.7.3.1
Pruebas de servicio
RD 10 ES 25APR17 EF 8MAY17 LS 25APR17 LF 8MAY17 TF
TOTAL :
1.8.1.1
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.8.2.1
.00
.0
.00
.00
TOTAL :
.00
.0
.00
.00
130
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:45
Resource Control - Summary by Activity
6
-----------------------------------------------------------------------------------------------------------------------------------
ACTIVITY ID
VARIANCE
PCT
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.8.3.1
TOTAL :
.00
.00
.0
.00
.00
.00
.00
532124.00
.0
.00
.00
532124.00
532124.00
00
=================================================================
=================================================================
=
131
Represa
18:47
Tabular Resource Use - Monthly
----------------------------------------------------------------------------------------------------------------------------------PERIOD ----AVAILABLE---SCHEDULE---
-----EARLY SCHEDULE----
1JUL96
1AUG96
USAGE
----------- ------------
- Ayudante
CUMULATIVE
----------- ------------
USAGE
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1OCT96
.00
.00
.00
.00
.00
.00
1NOV96
.00
.00
.00
.00
.00
.00
1DEC96
.00
.00
.00
.00
.00
.00
1JAN97
.00
.00
.00
.00
.00
.00
1FEB97
.00
.00
.00
.00
.00
.00
1APR97
1MAY97
0
0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1JUN97
.00
.00
.00
.00
.00
.00
1JUL97
.00
.00
.00
.00
.00
.00
1AUG97
.00
.00
.00
.00
USAGE
.00
CUMULATIVE
TARGET = EARLY
1SEP96
1MAR97
---TARGET 1
----------- ------------
UNIT OF MEASURE = HH
.00
-----LATE SCHEDULE-----
.00
.00
1SEP97
.00
.00
.00
.00
.00
.00
1OCT97
.00
.00
.00
.00
.00
.00
132
1NOV97
.00
.00
.00
.00
.00
.00
1DEC97
.00
.00
.00
.00
.00
.00
1JAN98
.00
.00
.00
.00
.00
.00
1FEB98
.00
.00
.00
.00
.00
.00
133
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:47
Tabular Resource Use - Monthly
----------------------------------------------------------------------------------------------------------------------------------PERIOD ----AVAILABLE---SCHEDULE---
-----EARLY SCHEDULE----
USAGE
----------- ------------
1AUG96
.00
.00
CUMULATIVE
----------- ------------
1JUL96
-----LATE SCHEDULE-----
USAGE
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1OCT96
.00
.00
.00
.00
.00
.00
1NOV96
.00
.00
.00
.00
.00
.00
1DEC96
.00
.00
.00
.00
.00
.00
1JAN97
.00
.00
.00
.00
.00
.00
1FEB97
.00
.00
.00
.00
.00
.00
1APR97
1MAY97
0
0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1JUN97
.00
.00
.00
.00
.00
.00
1JUL97
.00
.00
.00
.00
.00
.00
1AUG97
.00
.00
.00
.00
.00
TARGET = EARLY
.00
USAGE
.00
1SEP96
1MAR97
CUMULATIVE
----------- ------------
UNIT OF MEASURE = HM
.00
---TARGET 1
.00
1SEP97
.00
.00
.00
.00
.00
.00
1OCT97
.00
.00
.00
.00
.00
.00
1NOV97
.00
.00
.00
.00
.00
.00
134
1DEC97
.00
.00
.00
.00
.00
.00
1JAN98
.00
.00
.00
.00
.00
.00
1FEB98
.00
.00
.00
.00
.00
.00
135
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:47
Tabular Resource Use - Monthly
----------------------------------------------------------------------------------------------------------------------------------PERIOD ----AVAILABLE---SCHEDULE---
-----EARLY SCHEDULE----
1JUL96
1AUG96
USAGE
----------- ------------
- Maestro de primera
.00
.00
-----LATE SCHEDULE-----
CUMULATIVE
----------- ------------
USAGE
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1OCT96
.00
.00
.00
.00
.00
.00
1NOV96
.00
.00
.00
.00
.00
.00
1DEC96
.00
.00
.00
.00
.00
.00
1JAN97
.00
.00
.00
.00
.00
.00
1FEB97
.00
.00
.00
.00
.00
.00
1APR97
0
0
1MAY97
0
0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1JUN97
.00
.00
.00
.00
.00
.00
1JUL97
.00
.00
.00
.00
.00
.00
1AUG97
.00
.00
.00
.00
USAGE
TARGET = EARLY
1SEP96
1MAR97
CUMULATIVE
----------- ------------
UNIT OF MEASURE = HH
.00
---TARGET 1
.00
.00
1SEP97
.00
.00
.00
.00
.00
.00
1OCT97
.00
.00
.00
.00
.00
.00
1NOV97
.00
.00
.00
.00
.00
.00
136
1DEC97
.00
.00
.00
.00
.00
.00
1JAN98
.00
.00
.00
.00
.00
.00
1FEB98
.00
.00
.00
.00
.00
.00
137
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:47
Tabular Resource Use - Monthly
----------------------------------------------------------------------------------------------------------------------------------PERIOD ----AVAILABLE---SCHEDULE---
-----EARLY SCHEDULE----
1JUL96
1AUG96
USAGE
----------- ------------
- Maestro de segunda
.00
.00
-----LATE SCHEDULE-----
CUMULATIVE
----------- ------------
USAGE
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1OCT96
.00
.00
.00
.00
.00
.00
1NOV96
.00
.00
.00
.00
.00
.00
1DEC96
.00
.00
.00
.00
.00
.00
1JAN97
.00
.00
.00
.00
.00
.00
1FEB97
.00
.00
.00
.00
.00
.00
1APR97
0
0
1MAY97
0
0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1JUN97
.00
.00
.00
.00
.00
.00
1JUL97
.00
.00
.00
.00
.00
.00
1AUG97
.00
.00
.00
.00
USAGE
TARGET = EARLY
1SEP96
1MAR97
CUMULATIVE
----------- ------------
UNIT OF MEASURE = HH
.00
---TARGET 1
.00
.00
1SEP97
.00
.00
.00
.00
.00
.00
1OCT97
.00
.00
.00
.00
.00
.00
1NOV97
.00
.00
.00
.00
.00
.00
138
1DEC97
.00
.00
.00
.00
.00
.00
1JAN98
.00
.00
.00
.00
.00
.00
1FEB98
.00
.00
.00
.00
.00
.00
139
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:47
Tabular Resource Use - Monthly
----------------------------------------------------------------------------------------------------------------------------------PERIOD ----AVAILABLE---SCHEDULE---
-----EARLY SCHEDULE----
1JUL96
1AUG96
USAGE
----------- ------------
- Mixers
CUMULATIVE
----------- ------------
USAGE
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1OCT96
.00
.00
.00
.00
.00
.00
1NOV96
.00
.00
.00
.00
.00
.00
1DEC96
.00
.00
.00
.00
.00
.00
1JAN97
.00
.00
.00
.00
.00
.00
1FEB97
.00
.00
.00
.00
.00
.00
1APR97
1MAY97
0
0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1JUN97
.00
.00
.00
.00
.00
.00
1JUL97
.00
.00
.00
.00
.00
.00
1AUG97
.00
.00
.00
.00
USAGE
.00
CUMULATIVE
TARGET = EARLY
1SEP96
1MAR97
---TARGET 1
----------- ------------
.00
-----LATE SCHEDULE-----
.00
.00
1SEP97
.00
.00
.00
.00
.00
.00
1OCT97
.00
.00
.00
.00
.00
.00
1NOV97
.00
.00
.00
.00
.00
.00
140
1DEC97
.00
.00
.00
.00
.00
.00
1JAN98
.00
.00
.00
.00
.00
.00
1FEB98
.00
.00
.00
.00
.00
.00
141
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:47
Tabular Resource Use - Monthly
----------------------------------------------------------------------------------------------------------------------------------PERIOD ----AVAILABLE---SCHEDULE---
-----EARLY SCHEDULE----
USAGE
----------- ------------
MOTNI - Motoniveladora
1JUL96
1AUG96
.00
.00
-----LATE SCHEDULE-----
CUMULATIVE
----------- ------------
USAGE
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1OCT96
.00
.00
.00
.00
.00
.00
1NOV96
.00
.00
.00
.00
.00
.00
1DEC96
.00
.00
.00
.00
.00
.00
1JAN97
.00
.00
.00
.00
.00
.00
1FEB97
.00
.00
.00
.00
.00
.00
1APR97
0
0
1MAY97
0
0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1JUN97
.00
.00
.00
.00
.00
.00
1JUL97
.00
.00
.00
.00
.00
.00
1AUG97
.00
.00
.00
.00
USAGE
TARGET = EARLY
1SEP96
1MAR97
CUMULATIVE
----------- ------------
UNIT OF MEASURE = HM
.00
---TARGET 1
.00
.00
1SEP97
.00
.00
.00
.00
.00
.00
1OCT97
.00
.00
.00
.00
.00
.00
1NOV97
.00
.00
.00
.00
.00
.00
142
1DEC97
.00
.00
.00
.00
.00
.00
1JAN98
.00
.00
.00
.00
.00
.00
1FEB98
.00
.00
.00
.00
.00
.00
143
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:47
Tabular Resource Use - Monthly
----------------------------------------------------------------------------------------------------------------------------------PERIOD ----AVAILABLE---SCHEDULE---
-----EARLY SCHEDULE----
1JUL96
1AUG96
USAGE
----------- ------------
- Grua pluma
CUMULATIVE
----------- ------------
USAGE
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1OCT96
.00
.00
.00
.00
.00
.00
1NOV96
.00
.00
.00
.00
.00
.00
1DEC96
.00
.00
.00
.00
.00
.00
1JAN97
.00
.00
.00
.00
.00
.00
1FEB97
.00
.00
.00
.00
.00
.00
1APR97
1MAY97
0
0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1JUN97
.00
.00
.00
.00
.00
.00
1JUL97
.00
.00
.00
.00
.00
.00
1AUG97
.00
.00
.00
.00
USAGE
.00
CUMULATIVE
TARGET = EARLY
1SEP96
1MAR97
---TARGET 1
----------- ------------
UNIT OF MEASURE = HM
.00
-----LATE SCHEDULE-----
.00
.00
1SEP97
.00
.00
.00
.00
.00
.00
1OCT97
.00
.00
.00
.00
.00
.00
1NOV97
.00
.00
.00
.00
.00
.00
144
1DEC97
.00
.00
.00
.00
.00
.00
1JAN98
.00
.00
.00
.00
.00
.00
1FEB98
.00
.00
.00
.00
.00
.00
145
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:47
Tabular Resource Use - Monthly
----------------------------------------------------------------------------------------------------------------------------------PERIOD ----AVAILABLE---SCHEDULE---
-----EARLY SCHEDULE----
1JUL96
1AUG96
USAGE
----------- ------------
- Retroexcavadora
.00
.00
-----LATE SCHEDULE-----
CUMULATIVE
----------- ------------
USAGE
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1OCT96
.00
.00
.00
.00
.00
.00
1NOV96
.00
.00
.00
.00
.00
.00
1DEC96
.00
.00
.00
.00
.00
.00
1JAN97
.00
.00
.00
.00
.00
.00
1FEB97
.00
.00
.00
.00
.00
.00
1APR97
0
0
1MAY97
0
0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1JUN97
.00
.00
.00
.00
.00
.00
1JUL97
.00
.00
.00
.00
.00
.00
1AUG97
.00
.00
.00
.00
USAGE
TARGET = EARLY
1SEP96
1MAR97
CUMULATIVE
----------- ------------
UNIT OF MEASURE = HM
.00
---TARGET 1
.00
.00
1SEP97
.00
.00
.00
.00
.00
.00
1OCT97
.00
.00
.00
.00
.00
.00
1NOV97
.00
.00
.00
.00
.00
.00
146
1DEC97
.00
.00
.00
.00
.00
.00
1JAN98
.00
.00
.00
.00
.00
.00
1FEB98
.00
.00
.00
.00
.00
.00
147
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:47
Tabular Resource Use - Monthly
----------------------------------------------------------------------------------------------------------------------------------PERIOD ----AVAILABLE---SCHEDULE---
-----EARLY SCHEDULE----
USAGE
----------- ------------
1JUL96
1AUG96
CUMULATIVE
----------- ------------
USAGE
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1OCT96
.00
.00
.00
.00
.00
.00
1NOV96
.00
.00
.00
.00
.00
.00
1DEC96
.00
.00
.00
.00
.00
.00
1JAN97
.00
.00
.00
.00
.00
.00
1FEB97
.00
.00
.00
.00
.00
.00
1APR97
1MAY97
0
0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1JUN97
.00
.00
.00
.00
.00
.00
1JUL97
.00
.00
.00
.00
.00
.00
1AUG97
.00
.00
.00
.00
USAGE
.00
CUMULATIVE
TARGET = EARLY
1SEP96
1MAR97
---TARGET 1
----------- ------------
UNIT OF MEASURE = HM
.00
-----LATE SCHEDULE-----
.00
.00
1SEP97
.00
.00
.00
.00
.00
.00
1OCT97
.00
.00
.00
.00
.00
.00
1NOV97
.00
.00
.00
.00
.00
.00
148
1DEC97
.00
.00
.00
.00
.00
.00
1JAN98
.00
.00
.00
.00
.00
.00
1FEB98
.00
.00
.00
.00
.00
.00
149
19.
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:48
Cost Control - Summary by Activity
----------------------------------------------------------------------------------------------------------------------------------PCT
ACTIVITY ID
VARIANCE
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.1.1.1
Instalacin de campamentos
RD 60 ES 22SEP15 EF 14DEC15 LS 22SEP15 LF 14DEC15 TF
TOTAL :
1.1.1.2
48420000.00
.0
.00
.00
TOTAL :
1.1.1.3
.00
.0
.00
.00
.00
.00
.00
TOTAL :
6395000.00
.0
.00
.00
150
1.1.1.4
TOTAL :
1.1.2.1
6395000.00
.0
.00
TOTAL :
1.1.2.2
7920000.00
.0
.00
TOTAL :
5346000.00
.0
.00
32400000.00
.0
.00
.00
TOTAL :
18990000.00
.0
.00
.00
Construccin de atagua
RD 40 ES 1MAR16 EF 25APR16 LS 1MAR16 LF 25APR16 TF
TOTAL :
1.1.3.2
.00
Excavacin de escarpe
TOTAL :
1.1.3.1
.00
1.1.2.4
Roce
RD
1.1.2.3
.00
16740000.00
.0
.00
.00
151
TOTAL :
1.1.3.3
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.1.3.4
.00
.00
.0
.00
.00
.00
TOTAL :
1.1.3.5
.00
.0
.00
.00
.00
TOTAL :
.00
.0
.00
.00
.00
152
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:48
Cost Control - Summary by Activity
----------------------------------------------------------------------------------------------------------------------------------PCT
ACTIVITY ID
VARIANCE
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.2.1.1
TOTAL :
1.2.1.2
.00
.0
.00
.00
.00
.00
.00
TOTAL :
1.2.1.3
10395000.00
.0
.00
TOTAL :
1.2.1.4
.00
15120000.00
.0
.00
.00
153
TOTAL :
1.2.2.1
9450000.00
.0
.00
.00
Relleno plinto
RD 15 ES 7NOV16 EF 25NOV16 LS 26DEC16 LF 13JAN17 TF 35
TOTAL :
1.2.2.2
.00
1305000.00
.0
.00
.00
TOTAL :
3654000.00
.0
.00
.00
TOTAL :
5400000.00
.0
.00
.00
TOTAL :
1.3.1.1
1.2.3.2
.00
TOTAL :
1.2.3.1
.0
1.2.2.3
17617500.00
5400000.00
.0
.00
.00
Excavaciones subterrneas
RD
TOTAL :
1125000.00
.0
.00
.00
154
1.3.1.2
TOTAL :
1.3.2.1
.0
.00
.00
.00
.00
.00
TOTAL :
1.3.2.2
.00
4927500.00
.0
.00
.00
TOTAL :
.00
.0
.00
.00
.00
.00
.00
155
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:48
Cost Control - Summary by Activity
----------------------------------------------------------------------------------------------------------------------------------PCT
ACTIVITY ID
VARIANCE
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.3.2.3
TOTAL :
1.3.2.4
1170000.00
.0
.00
.00
Hormign proyectado
RD 10 ES 11MAY16 EF 24MAY16 LS 5JUL16 LF 18JUL16 TF 39
TOTAL :
1.3.2.5
1710000.00
.0
.00
.00
TOTAL :
1.3.3.1
.00
.0
.00
.00
.00
.00
.00
156
TOTAL :
1.3.3.2
.00
.00
.00
.00
.00
TOTAL :
882000.00
.0
.00
.00
882000.00
882000.00
.00
TOTAL :
1.4.1.1
.0
1.3.3.3
.00
.00
.0
.00
.00
.00
.00
.00
TOTAL :
1.4.1.2
4860000.00
.0
.00
.00
TOTAL :
1.4.1.3
10800000.00
.0
.00
TOTAL :
1.4.2.1
.00
22680000.00
.0
.00
.00
TOTAL :
22680000.00
.0
.00
.00
157
1.4.2.2
TOTAL :
1.4.2.3
28350000.00
.0
.00
TOTAL :
1.4.3.1
.00
.00
.0
.00
.00
.00
.00
.00
TOTAL :
12960000.00
.0
.00
.00
158
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:48
Cost Control - Summary by Activity
----------------------------------------------------------------------------------------------------------------------------------PCT
ACTIVITY ID
VARIANCE
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.4.3.2
TOTAL :
1.4.3.3
.00
.0
.00
.00
.00
TOTAL :
.00
.0
.00
.00
.00
.00
.00
TOTAL :
1.5.1.2
.00
1.5.1.1
.00
15525000.00
.0
.00
.00
159
TOTAL :
1.5.1.3
32760000.00
.00
.0
.00
.00
TOTAL :
540000.00
.0
.00
.00
540000.00
540000.00
.00
972000.00
.00
TOTAL :
972000.00
.0
.00
.00
972000.00
TOTAL :
1.5.3.1
1.5.2.3
.00
TOTAL :
1.5.2.2
.0
1.5.2.1
28980000.00
1134000.00
.0
.00
.00
TOTAL :
1.5.3.2
8640000.00
.0
.00
.00
Moldaje plinto
RD
TOTAL :
4860000.00
.0
.00
.00
160
1.5.3.3
TOTAL :
1.5.4.1
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.5.4.2
.00
.0
.00
.00
.00
Enfierradura plinto
RD 77 ES 21JUL16 EF 4NOV16 LS 8SEP16 LF 23DEC16 TF 35
TOTAL :
.00
.0
.00
.00
.00
161
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:48
Cost Control - Summary by Activity
----------------------------------------------------------------------------------------------------------------------------------PCT
ACTIVITY ID
VARIANCE
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.5.4.3
TOTAL :
1.5.5.1
.00
.0
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.5.5.2
.00
.0
.00
.00
.00
Hormigonado plinto
RD 12 ES 20OCT16 EF 4NOV16 LS 8DEC16 LF 23DEC16 TF 35
TOTAL :
1.5.5.3
9720000.00
.0
.00
.00
162
TOTAL :
1.6.1.1
.00
.0
.00
.00
.00
TOTAL :
.00
.0
.00
.00
18900000.00
.0
.00
TOTAL :
17280000.00
.0
.00
.00
Pinturas
RD
TOTAL :
17010000.00
.0
.00
.00
Instalacin de tuberas
RD
TOTAL :
1.7.2.1
.00
Aplicacin de antixidos
RD 10 ES 1MAR17 EF 14MAR17 LS 1MAR17 LF 14MAR17 TF
1.7.1.1
.00
Limpieza de superficies
TOTAL :
1.6.1.4
.00
.00
1.6.1.3
.00
Terminaciones de estructuras
RD 20 ES 18JAN17 EF 14FEB17 LS 18JAN17 LF 14FEB17 TF
1.6.1.2
.00
2646000.00
.0
.00
.00
Instalacin de equipamiento
RD 20 ES 28MAR17 EF 24APR17 LS 28MAR17 LF 24APR17 TF
TOTAL :
.00
.0
.00
.00
.00
.00
.00
163
1.7.3.1
Pruebas de servicio
RD 10 ES 25APR17 EF 8MAY17 LS 25APR17 LF 8MAY17 TF
TOTAL :
1.8.1.1
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.8.2.1
.00
.0
.00
.00
.00
TOTAL :
.00
.0
.00
.00
.00
164
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:48
Cost Control - Summary by Activity
----------------------------------------------------------------------------------------------------------------------------------PCT
ACTIVITY ID
VARIANCE
ACTUAL
BUDGET
CMP
ACTUAL
ESTIMATE TO
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.8.3.1
TOTAL :
.00
.0
.00
.00
.00
.00
.00
482059000.00
.0
.00
.00
==============================================================================================
=====================================
165
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:48
Cost Control - Detailed by Resource
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL
BUDGET
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
AYU
- Ayudante
1.1.1.1
AYU
HH
18000000.00
.0
.00
1.1.1.3
AYU
HH
675000.00
.0
.00
.00
675000.00
675000.00
.00
1.1.1.4
AYU
HH
675000.00
.0
.00
.00
675000.00
675000.00
.00
1.1.2.1
AYU
HH
6300000.00
.0
.00
.00
1.1.2.2
AYU
HH
4252500.00
.0
.00
.00
1.1.2.3
AYU
HH
5400000.00
.0
.00
.00
1.1.2.4
AYU
HH
7425000.00
.0
.00
.00
1.1.3.1
AYU
HH
8100000.00
.0
.00
.00
1.2.2.1
AYU
HH
12150000.00
.0
.00
1.2.2.2
AYU
HH
900000.00
.0
.00
.00
1.2.2.3
AYU
HH
2520000.00
.0
.00
1.3.2.1
AYU
HH
225000.00
.0
.00
.00
225000.00
225000.00
.00
1.3.2.3
AYU
HH
450000.00
.0
.00
.00
450000.00
450000.00
.00
1.3.2.4
AYU
HH
900000.00
.0
.00
.00
900000.00
900000.00
.00
1.3.3.2
AYU
HH
315000.00
.0
.00
.00
315000.00
315000.00
.00
900000.00
900000.00
.00
.00
.00
.00
166
1.4.1.1
AYU
HH
2025000.00
.0
.00
.00
1.4.1.2
AYU
HH
4500000.00
.0
.00
.00
1.4.1.3
AYU
HH
9450000.00
.0
.00
.00
1.4.2.1
AYU
HH
8100000.00
.0
.00
.00
1.4.2.2
AYU
HH
10125000.00
.0
.00
1.4.2.3
AYU
HH
.00
1.5.2.1
AYU
HH
225000.00
.0
.00
.00
225000.00
225000.00
.00
1.5.2.2
AYU
HH
405000.00
.0
.00
.00
405000.00
405000.00
.00
1.5.2.3
AYU
HH
472500.00
.0
.00
.00
472500.00
472500.00
.00
1.5.3.1
AYU
HH
3600000.00
.0
.00
.00
1.5.3.2
AYU
HH
2025000.00
.0
.00
.00
1.5.3.3
AYU
HH
.00
.0
.00
.00
.00
.00
.00
1.5.4.1
AYU
HH
.00
.0
.00
.00
.00
.00
.00
1.5.4.2
AYU
HH
.00
.0
.00
.00
.00
.00
.00
1.5.4.3
AYU
HH
.00
.0
.00
.00
.00
.00
.00
1.6.1.2
AYU
HH
18900000.00
.0
.00
1.6.1.3
AYU
HH
7200000.00
.0
.00
.00
1.6.1.4
AYU
HH
7087500.00
.0
.00
.00
1.7.1.1
AYU
HH
945000.00
.0
.00
.00
.0
.00
.00
.00
.00
945000.00
.00
.00
945000.00
.00
.00
HH 143347500.00
.0
.00
.00
==============================================================================================
=====================================
BOMBA
1.1.3.1
BOMBA
HM
.00
.0
.00
1.4.3.1
BOMBA
HM
12960000.00
1.4.3.2
BOMBA
HM
.00
.0
.00
.00
.00
.00
.00
1.4.3.3
BOMBA
HM
.00
.0
.00
.00
.00
.00
.00
1.5.5.1
BOMBA
HM
.00
.0
.00
.00
.00
.00
.00
.0
.00
.00
.00
.00
.00
.00
167
1.5.5.2
BOMBA
HM
9720000.00
1.5.5.3
BOMBA
HM
.00
.0
.0
.00
.00
.00
.00
.00
.00
HM
22680000.00
.0
.00
.00
==============================================================================================
=====================================
MAS1
- Maestro de primera
1.1.1.1
MAS1
HH
14580000.00
.0
1.1.1.3
MAS1
HH
405000.00
.0
.00
.00
405000.00
405000.00
.00
1.1.1.4
MAS1
HH
405000.00
.0
.00
.00
405000.00
405000.00
.00
1.1.2.1
MAS1
HH
1620000.00
.0
.00
.00
1.1.2.2
MAS1
HH
1093500.00
.0
.00
.00
1.1.3.1
MAS1
HH
4860000.00
.0
.00
.00
1.2.2.1
MAS1
HH
5467500.00
.0
.00
.00
1.2.2.2
MAS1
HH
405000.00
.0
.00
.00
1.2.2.3
MAS1
HH
1134000.00
.0
.00
1.3.2.1
MAS1
HH
202500.00
.0
.00
.00
202500.00
202500.00
.00
1.3.2.3
MAS1
HH
405000.00
.0
.00
.00
405000.00
405000.00
.00
1.3.2.4
MAS1
HH
810000.00
.0
.00
.00
810000.00
810000.00
.00
1.3.3.2
MAS1
HH
567000.00
.0
.00
.00
567000.00
567000.00
.00
1.4.2.1
MAS1
HH
14580000.00
.0
.00
.00
405000.00
405000.00
.00
.00
.00
.00
168
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:48
Cost Control - Detailed by Resource
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL
BUDGET
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.4.2.2
MAS1
HH
18225000.00
.0
.00
1.4.2.3
MAS1
HH
.00
.0
.00
.00
.00
.00
.00
1.5.4.1
MAS1
HH
.00
.0
.00
.00
.00
.00
.00
1.5.4.2
MAS1
HH
.00
.0
.00
.00
.00
.00
.00
1.5.4.3
MAS1
HH
.00
.0
.00
.00
.00
.00
.00
1.6.1.1
MAS1
HH
.00
.0
.00
.00
.00
.00
.00
1.7.1.1
MAS1
HH
1701000.00
.0
.00
.00
.00
HH
66460500.00
.0
.00
.00
==============================================================================================
=====================================
MAS2
- Maestro de segunda
1.1.1.1
MAS2
HH
11340000.00
.0
.00
.00
1.1.1.3
MAS2
HH
315000.00
.0
.00
.00
315000.00
315000.00
.00
1.1.1.4
MAS2
HH
315000.00
.0
.00
.00
315000.00
315000.00
.00
1.1.2.4
MAS2
HH
3465000.00
.0
.00
.00
169
1.1.3.1
MAS2
HH
3780000.00
.0
.00
1.3.2.3
MAS2
HH
315000.00
.0
.00
.00
1.3.3.2
MAS2
HH
.00
1.4.1.1
MAS2
HH
2835000.00
.0
.00
.00
1.4.1.2
MAS2
HH
6300000.00
.0
.00
.00
1.4.1.3
MAS2
HH
13230000.00
.0
.00
1.5.2.1
MAS2
HH
315000.00
.0
.00
.00
315000.00
315000.00
.00
1.5.2.2
MAS2
HH
567000.00
.0
.00
.00
567000.00
567000.00
.00
1.5.2.3
MAS2
HH
661500.00
.0
.00
.00
661500.00
661500.00
.00
1.5.3.1
MAS2
HH
5040000.00
.0
.00
.00
1.5.3.2
MAS2
HH
2835000.00
.0
.00
.00
1.5.3.3
MAS2
HH
.00
1.6.1.3
MAS2
HH
10080000.00
.0
.00
1.6.1.4
MAS2
HH
9922500.00
.0
.00
.0
.00
.0
.00
.00
315000.00
.00
.00
.00
315000.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
HH
71316000.00
.0
.00
.00
==============================================================================================
=====================================
MIX
- Mixers
1.1.3.1
MIX
Cam
.00
.0
.00
.00
.00
.00
.00
1.4.3.1
MIX
Cam
.00
.0
.00
.00
.00
.00
.00
1.4.3.2
MIX
Cam
.00
.0
.00
.00
.00
.00
.00
1.4.3.3
MIX
Cam
.00
.0
.00
.00
.00
.00
.00
1.5.5.1
MIX
Cam
.00
.0
.00
.00
.00
.00
.00
1.5.5.2
MIX
Cam
.00
.0
.00
.00
.00
.00
.00
1.5.5.3
MIX
Cam
.00
.0
.00
.00
.00
.00
.00
Cam
.00
.0
.00
.00
.00
.00
.00
170
==============================================================================================
=====================================
MOTNI
- Motoniveladora
1.1.3.1
MOTNI
HM
.00
.0
.00
.00
.00
.00
.00
1.2.1.1
MOTNI
HM
.00
.0
.00
.00
.00
.00
.00
1.2.1.2
MOTNI
HM
10395000.00
.0
.00
.00
1.2.1.3
MOTNI
HM
15120000.00
.0
.00
.00
1.2.1.4
MOTNI
HM
9450000.00
.0
.00
.00
1.2.3.1
MOTNI
HM
3780000.00
.0
.00
.00
1.2.3.2
MOTNI
HM
3780000.00
.0
.00
.00
HM
42525000.00
.0
.00
.00
==============================================================================================
=====================================
PLUM
- Grua pluma
1.1.1.1
PLUM
HM
4500000.00
.0
.00
.00
1.1.1.3
PLUM
HM
5000000.00
.0
.00
.00
1.1.1.4
PLUM
HM
5000000.00
.0
.00
.00
1.3.2.1
PLUM
HM
4500000.00
.0
.00
.00
HM
19000000.00
.0
.00
.00
==============================================================================================
=====================================
171
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:48
Cost Control - Detailed by Resource
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL
BUDGET
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
RETRO
- Retroexcavadora
1.1.2.3
RETRO
HM
18900000.00
.0
.00
1.1.3.1
RETRO
HM
.00
.0
.00
.00
.00
.00
.00
1.2.1.1
RETRO
HM
.00
.0
.00
.00
.00
.00
.00
1.2.1.2
RETRO
HM
.00
.0
.00
.00
.00
.00
.00
1.2.1.3
RETRO
HM
.00
.0
.00
.00
.00
.00
.00
1.2.1.4
RETRO
HM
.00
.0
.00
.00
.00
.00
.00
1.3.1.1
RETRO
HM
315000.00
.0
.00
.00
1.5.1.1
RETRO
HM
9450000.00
.0
.00
1.5.1.2
RETRO
HM
17640000.00
.0
.00
.00
1.5.1.3
RETRO
HM
19845000.00
.0
.00
.00
315000.00
315000.00
.00
.00
.00
HM
66150000.00
.0
.00
.00
==============================================================================================
=====================================
TOLVA
- Camin Tolva
172
1.1.2.3
TOLVA
HM
8100000.00
.0
.00
.00
1.1.2.4
TOLVA
HM
8100000.00
.0
.00
.00
1.1.3.1
TOLVA
HM
.00
1.2.3.1
TOLVA
HM
1620000.00
.0
.00
.00
1.2.3.2
TOLVA
HM
1620000.00
.0
.00
.00
1.3.1.1
TOLVA
HM
810000.00
.0
.00
.00
1.5.1.1
TOLVA
HM
6075000.00
.0
.00
1.5.1.2
TOLVA
HM
11340000.00
.0
.00
.00
1.5.1.3
TOLVA
HM
12915000.00
.0
.00
.00
.0
.00
.00
.00
.00
810000.00
.00
810000.00
.00
.00
HM
50580000.00
.0
.00
.00
==============================================================================================
=====================================
482059000.00
.0
.00
.00
==============================================================================================
=====================================
173
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
18:49
Cost Control - Summary by Resource
----------------------------------------------------------------------------------------------------------------------------------UNIT
PCT
RESOURCE
VARIANCE
MEAS
ACTUAL
BUDGET
ACTUAL
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
COMPLETE
FORECAST
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
AYU
- Ayudante
TOTAL AYU
HH 143347500.00
BOMBA
HM
MAS2
HH
.00
22680000.00
.0
.00
.00
66460500.00
.0
.00
.00
71316000.00
.0
.00
.00
- Maestro de segunda
TOTAL MAS2
HH
- Mixers
TOTAL MIX
MOTNI
- Maestro de primera
TOTAL MAS1
MIX
.00
TOTAL BOMBA
MAS1
.0
Cam
.00
.0
.00
.00
.00
.00
.00
- Motoniveladora
TOTAL MOTNI
HM
42525000.00
.0
.00
.00
174
PLUM
- Grua pluma
TOTAL PLUM
RETRO
HM
.0
.00
.00
- Retroexcavadora
TOTAL RETRO
TOLVA
19000000.00
HM
66150000.00
.0
.00
.00
- Camin Tolva
TOTAL TOLVA
HM
50580000.00
.0
.00
.00
482059000.00
.0
.00
.00
==============================================================================================
=====================================
175
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:50
Cost Control - Detailed by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
BUDGET
ACTUAL
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.1.1.1
Instalacin de campamentos
RD 60 ES 22SEP15 EF 14DEC15 LS 22SEP15 LF 14DEC15 TF
AYU
HH
18000000.00
.0
.00
00
MAS1
HH
14580000.00
.0
.00
MAS2
HH
11340000.00
.0
.00
PLUM
HM
4500000.00
00
00
.0
.00
.00
48420000.00
.0
.00
00
1.1.1.2
TOTAL :
.00
.0
.00
.00
.00
.00
.00
176
1.1.1.3
AYU
HH
675000.00
MAS1
HH
405000.00
PLUM
HM
5000000.00
MAS2
HH
315000.00
.0
.0
.0
.0
.00
.00
.00
.00
.00
.00
675000.00
405000.00
675000.00
405000.00
315000.00
315000.00
.00
.00
.00
.00
1.1.1.4
6395000.00
.0
.00
.00
AYU
HH
675000.00
MAS1
HH
405000.00
PLUM
HM
5000000.00
MAS2
HH
315000.00
.0
.0
.0
.0
.00
.00
.00
.00
.00
.00
675000.00
405000.00
675000.00
405000.00
315000.00
315000.00
.00
.00
.00
.00
1.1.2.1
6395000.00
.0
.00
.00
AYU
HH
MAS1
HH
6300000.00
1620000.00
.0
.0
.00
.00
.00
.00
1.1.2.2
7920000.00
.0
.00
.00
Roce
RD
177
AYU
HH
MAS1
HH
4252500.00
.0
1093500.00
.00
.0
.00
.00
.00
1.1.2.3
5346000.00
.0
.00
.00
Excavacin de escarpe
RD 10 ES 2FEB16 EF 15FEB16 LS 2FEB16 LF 15FEB16 TF
AYU
RETRO
18900000.00
TOLVA
HH
5400000.00
HM
18900000.00
HM
8100000.00
.0
.00
.0
.00
.00
.00 18900000.00
.00
.0
.00
00
------------ ----- ------------ ------------ ------------ ------------ -----------TOTAL :
32400000.00
.0
.00
00
1.1.2.4
MAS2
AYU
TOLVA
HH
HH
HM
3465000.00
7425000.00
8100000.00
.0
.0
.0
.00
.00
.00
.00
.00
.
00
------------ ----- ------------ ------------ ------------ ------------ -----------TOTAL :
18990000.00
.0
.00
00
178
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:50
Cost Control - Detailed by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL
BUDGET
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.1.3.1
Construccin de atagua
RD 40 ES 1MAR16 EF 25APR16 LS 1MAR16 LF 25APR16 TF
MAS1
HH
4860000.00
.0
.00
.00
MAS2
HH
3780000.00
.0
.00
.00
AYU
HH
8100000.00
.0
.00
TOLVA
HM
.00
.0
.00
.00
.00
.00
.00
RETRO
HM
.00
.0
.00
.00
.00
.00
.00
MOTNI
HM
.00
.0
.00
.00
.00
.00
.00
MIX
BOMBA
Cam
.00
HM
.0
.00
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
16740000.00
.0
.00
00
1.1.3.2
TOTAL :
.00
.0
.00
.00
.00
.00
.00
179
1.1.3.3
TOTAL :
1.1.3.4
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.1.3.5
.00
.00
.00
.00
TOTAL :
1.2.1.1
.0
.00
.0
.00
.00
.00
RETRO
HM
.00
.0
.00
.00
.00
.00
.00
MOTNI
HM
.00
.0
.00
.00
.00
.00
.00
1.2.1.2
.00
.0
.00
.00
.00
.00
.00
RETRO
HM
.00
.0
MOTNI
HM
10395000.00
.00
.0
.00
.00
.00
.00
.00
00
------------ ----- ------------ ------------ ------------ ------------ ------------
180
TOTAL :
10395000.00
.0
.00
00
1.2.1.3
MOTNI
HM
15120000.00
RETRO
HM
.00
.0
.00
00
.0
.00
.00
.00
.00
.00
15120000.00
.0
.00
00
1.2.1.4
RETRO
HM
.00
.0
MOTNI
HM
9450000.00
.00
.0
.00
.00
.00
.00
.00
00
------------ ----- ------------ ------------ ------------ ------------ -----------TOTAL :
9450000.00
.0
.00
.00
181
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:50
Cost Control - Detailed by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
BUDGET
ACTUAL
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.2.2.1
Relleno plinto
RD 15 ES 7NOV16 EF 25NOV16 LS 26DEC16 LF 13JAN17 TF 35
MAS1
AYU
HH
HH
5467500.00
.0
.00
.00
12150000.00
.0
.00
00
------------ ----- ------------ ------------ ------------ ------------ -----------TOTAL :
17617500.00
.0
.00
00
1.2.2.2
MAS1
AYU
HH
HH
405000.00
900000.00
.0
.0
.00
.00
.00
.00
405000.00
900000.00
405000.00
900000.00
.00
.00
1.2.2.3
1305000.00
.0
.00
.00
182
RD
MAS1
AYU
HH
HH
1134000.00
2520000.00
.0
.0
.00
.00
.00
.00
1.2.3.1
3654000.00
.0
.00
.00
TOLVA
HM
1620000.00
.0
.00
MOTNI
HM
3780000.00
.0
.00
00
00
------------ ----- ------------ ------------ ------------ ------------ -----------TOTAL :
1.2.3.2
5400000.00
.0
.00
.00
TOLVA
HM
1620000.00
.0
.00
MOTNI
HM
3780000.00
.0
.00
00
00
------------ ----- ------------ ------------ ------------ ------------ -----------TOTAL :
1.3.1.1
5400000.00
.0
.00
.00
Excavaciones subterrneas
RD
RETRO
HM
315000.00
.0
.00
.00
315000.00
315000.00
.00
TOLVA
HM
810000.00
.0
.00
.00
810000.00
810000.00
.00
183
TOTAL :
1.3.1.2
1125000.00
.00
.00
TOTAL :
1.3.2.1
.0
.00
.0
.00
.00
.00
.00
.00
MAS1
AYU
HH
HH
PLUM
HM
202500.00
225000.00
4500000.00
.0
.00
.0
.00
.00
.0
.00
.00
202500.00
225000.00
202500.00
225000.00
.00
.00
.00
1.3.2.2
4927500.00
.0
.00
.00
TOTAL :
.00
.0
.00
.00
.00
.00
.00
184
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:50
Cost Control - Detailed by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
BUDGET
ACTUAL
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.3.2.3
MAS1
HH
405000.00
.0
.00
.00
405000.00
405000.00
.00
MAS2
HH
315000.00
.0
.00
.00
315000.00
315000.00
.00
AYU
HH
450000.00
.0
.00
.00
450000.00
450000.00
.00
1.3.2.4
1170000.00
.0
.00
.00
Hormign proyectado
RD 10 ES 11MAY16 EF 24MAY16 LS 5JUL16 LF 18JUL16 TF 39
MAS1
AYU
HH
HH
810000.00
900000.00
.0
.0
.00
.00
.00
.00
810000.00
900000.00
810000.00
900000.00
.00
.00
1.3.2.5
1710000.00
.0
.00
.00
185
TOTAL :
1.3.3.1
.00
.0
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.3.3.2
.00
.0
.00
.00
.00
MAS1
HH
567000.00
MAS2
HH
.00
AYU
HH
.0
.0
315000.00
.00
.00
.0
.00
567000.00
.00
.00
.00
.00
567000.00
.00
315000.00
.00
.00
315000.00
.00
1.3.3.3
882000.00
.00
.00
882000.00
882000.00
.00
TOTAL :
1.4.1.1
.0
.00
.0
.00
.00
.00
.00
.00
MAS2
AYU
HH
HH
2835000.00
2025000.00
.0
.0
.00
.00
.00
.00
4860000.00
.0
.00
.00
186
1.4.1.2
MAS2
AYU
HH
HH
6300000.00
4500000.00
.0
.0
.00
.00
.00
.00
10800000.00
.0
.00
00
1.4.1.3
MAS2
HH
13230000.00
.0
.00
00
AYU
HH
9450000.00
.0
.00
.00
22680000.00
.0
.00
00
187
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:50
Cost Control - Detailed by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
BUDGET
ACTUAL
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.4.2.1
MAS1
HH
14580000.00
.0
.00
00
AYU
HH
8100000.00
.0
.00
.00
22680000.00
.0
.00
00
1.4.2.2
MAS1
HH
18225000.00
.0
.00
00
AYU
HH
10125000.00
.0
.00
00
------------ ----- ------------ ------------ ------------ ------------ -----------TOTAL :
28350000.00
.0
.00
00
188
1.4.2.3
MAS1
HH
AYU
.00
HH
.0
.00
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
1.4.3.1
.00
.0
.00
.00
.00
.00
.00
MIX
BOMBA
12960000.00
Cam
.00
HM
.0
.00
12960000.00
.00
.0
.00
.00
.00
.00
.00 12960000.00
.00
------------ ----- ------------ ------------ ------------ ------------ ------------
TOTAL :
12960000.00
.0
.00
00
1.4.3.2
MIX
BOMBA
Cam
HM
.00
.0
.00
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
1.4.3.3
.00
.0
.00
.00
.00
.00
.00
MIX
.00
BOMBA
Cam
HM
.00
.00
.0
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
189
TOTAL :
1.5.1.1
.00
.0
.00
.00
.00
.00
.00
TOLVA
HM
6075000.00
.0
.00
RETRO
HM
9450000.00
.0
.00
00
00
------------ ----- ------------ ------------ ------------ ------------ -----------TOTAL :
15525000.00
.0
.00
00
1.5.1.2
TOLVA
HM
11340000.00
.0
.00
HM
17640000.00
.0
.00
.00 17640000.00
00
RETRO
17640000.00
.00
------------ ----- ------------ ------------ ------------ ------------ ------------
TOTAL :
28980000.00
.0
.00
00
1.5.1.3
TOLVA
HM
12915000.00
.0
.00
HM
19845000.00
.0
.00
.00 19845000.00
00
RETRO
19845000.00
.00
------------ ----- ------------ ------------ ------------ ------------ ------------
TOTAL :
32760000.00
.0
.00
00
190
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:50
Cost Control - Detailed by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
BUDGET
ACTUAL
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.5.2.1
MAS2
AYU
HH
HH
315000.00
225000.00
.0
.0
.00
.00
.00
.00
315000.00
225000.00
315000.00
225000.00
.00
.00
1.5.2.2
540000.00
.0
.00
.00
540000.00
540000.00
.00
MAS2
AYU
HH
HH
567000.00
405000.00
.0
.0
.00
.00
.00
.00
567000.00
405000.00
567000.00
405000.00
.00
.00
1.5.2.3
972000.00
.0
.00
.00
972000.00
972000.00
.00
191
MAS2
AYU
HH
HH
661500.00
472500.00
.0
.00
.0
.00
.00
.00
661500.00
472500.00
661500.00
472500.00
.00
.00
1.5.3.1
1134000.00
.0
.00
.00
MAS2
AYU
HH
HH
5040000.00
3600000.00
.0
.00
.0
.00
.00
.00
1.5.3.2
8640000.00
.0
.00
.00
Moldaje plinto
RD
MAS2
AYU
HH
HH
2835000.00
2025000.00
.0
.00
.0
.00
.00
.00
1.5.3.3
4860000.00
.0
.00
.00
MAS2
AYU
HH
HH
.00
.00
.0
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1.5.4.1
.00
.0
.00
.00
.00
.00
.00
192
MAS1
AYU
HH
HH
.00
.00
.0
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1.5.4.2
.00
.0
.00
.00
.00
.00
.00
Enfierradura plinto
RD 77 ES 21JUL16 EF 4NOV16 LS 8SEP16 LF 23DEC16 TF 35
MAS1
AYU
HH
HH
.00
.00
.0
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
1.5.4.3
.00
.0
.00
.00
.00
.00
.00
MAS1
AYU
HH
HH
.00
.00
.0
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.0
.00
.00
.00
.00
.00
193
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:50
Cost Control - Detailed by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
ACTUAL
BUDGET
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.5.5.1
MIX
Cam
BOMBA
HM
.00
.0
.00
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
1.5.5.2
.00
.0
.00
.00
.00
.00
.00
Hormigonado plinto
RD 12 ES 20OCT16 EF 4NOV16 LS 8DEC16 LF 23DEC16 TF 35
MIX
BOMBA
Cam
HM
.00
.0
.00
9720000.00
.0
.00
.00
.00
.00
.00
00
------------ ----- ------------ ------------ ------------ ------------ -----------TOTAL :
1.5.5.3
9720000.00
.0
.00
.00
194
MIX
BOMBA
Cam
.00
HM
.0
.00
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
1.6.1.1
.00
.0
.00
.00
.00
.00
.00
Terminaciones de estructuras
RD 20 ES 18JAN17 EF 14FEB17 LS 18JAN17 LF 14FEB17 TF
MAS1
HH
.00
.0
.00
.00
.00
.00
.00
1.6.1.2
.00
.0
.00
.00
.00
.00
.00
Limpieza de superficies
RD 10 ES 15FEB17 EF 28FEB17 LS 15FEB17 LF 28FEB17 TF
AYU
HH
18900000.00
.0
.00
00
------------ ----- ------------ ------------ ------------ ------------ -----------TOTAL :
18900000.00
.0
.00
00
1.6.1.3
Aplicacin de antixidos
RD 10 ES 1MAR17 EF 14MAR17 LS 1MAR17 LF 14MAR17 TF
MAS2
HH
10080000.00
.0
.00
00
AYU
HH
7200000.00
.0
.00
.00
17280000.00
.0
.00
00
1.6.1.4
Pinturas
195
RD
MAS2
AYU
HH
HH
9922500.00
7087500.00
.0
.00
.0
.00
.00
.00
17010000.00
.0
.00
00
1.7.1.1
Instalacin de tuberas
RD
MAS1
AYU
HH
HH
1701000.00
945000.00
.0
.00
.0
.00
.00
945000.00
945000.00
.00
.00
1.7.2.1
2646000.00
.0
.00
.00
Instalacin de equipamiento
RD 20 ES 28MAR17 EF 24APR17 LS 28MAR17 LF 24APR17 TF
TOTAL :
.00
.0
.00
.00
.00
.00
.00
196
----------------------------------------------------------------------------------------------------------------------------------C.S.Soluciones
Represa
START DATE
18:50
Cost Control - Detailed by Activity
----------------------------------------------------------------------------------------------------------------------------------COST
ACCOUNT UNIT
PCT
ACTUAL
BUDGET
ACTUAL
CMP
ESTIMATE TO
TO DATE
THIS PERIOD
----------- -------- ------------ -------- ---- ------------ ----- ------------ ------------ ------------ ------------ ------------
1.7.3.1
Pruebas de servicio
RD 10 ES 25APR17 EF 8MAY17 LS 25APR17 LF 8MAY17 TF
TOTAL :
1.8.1.1
.00
.0
.00
.00
TOTAL :
.00
.0
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
TOTAL :
1.8.3.1
.00
1.8.2.1
.00
.0
.00
.00
197
TOTAL :
.00
.0
.00
.00
.00
.00
.00
482059000.00
.0
.00
.00
=================================================================
=================================================================
=
198
Histogramas de recurso
199