) 1300 then 1450 MWe (and, later, EPR 1500 MWe) (fig. 2 and 3)
In the 1300 MWe and 1450 MWe (and 1500 MWe project), the containment is
similar.
The Reactor building of a 1450 MWe nuclear power plant (the latest step in terms
of technology built by EDF that is called N4 in the jargon) consists of 2
concentric containment walls (fig. 2). The inner containment wall, biaxially
prestressed and 120 cm thick, is designed to withstand an internal pressure of
0.53 MPa, which leads for the units to a mean initial prestress of 9.3 MPa along
the vertical axis (zz) and 13.3 MPa tangentially (). The outer one, 55 cm thick,
designed to withstand external aggressions, is made of reinforced concrete.
Finally, the space left between the two containment walls is kept in depression
(0.0015 MPa) in order to suck in and filter the possible leaks from the inner
containment. The construction of the containments lasts 5 years; the prestressing
begins at the end of the 2nd year and takes 1 year, in a complex site staging. The
Reactor is commissioned approximately 7 years after the start of construction.
To simplify, EDF must justify in front of the French Safety Authority (equivalent
to US-NRC) the capability of the inner containment wall to ensure, in case of an
accident, a leak rate less than 1.5 % per day of the total mass of fluids in the
containment at the LOCA temperature and pressure scenario (Loss Of primary
Coolant Accident that leads to a mean temperature of 160 C and an absolute
pressure of 0.53 MPa). To evaluate experimentally this leak rate, each
containment undergoes a leakage test at 0.53 MPa in dry air at atmospheric
temperature at the end of the civil engineering construction (containment preoperational pressure test), at the first refueling shutdown and then periodically
every 10 years. Only the 1.5 % leak rate is mandatory but in the case of the
leakage test, the leak rate should not exceed the value of 1 % that is considered as
a construction criterion.
The move from 900 MWe to 1300 MWe and now 1450 MWe is accompanied by
improvements of the projects and construction methods:
the elimination of the steel liner from the internal wall and the creation of an
external wall, reducing the level of stresses of thermal origin,
the construction of this external wall at the beginning of civil works facilitates
the carrying out of the projects by permitting the execution of prestressing
operations with great flexibility of phasing and without interferences to the
construction of neighbouring structures : previously, in the case of single-wall
containment, parts of the structures were left waiting until the prestressing was
completed.
Fig. 1
Fig. 2
Fig. 3
2.2. CONCRETE
In a NPP where the main goal is to maximize the leaktightness of the containment and
thus to minimize the risks of cracking, the qualities or technical specifications that are
asked to the concrete are mainly the following:
1. A good stability of fresh concrete to ensure a minimum segregation in the
formworks,
2. A low viscosity of fresh concrete allowing it to be pumped over a distance greater
that 100 m;
3. A low autogenous shrinkage (hydration shrinkage) in order to minimize the stresses
that develop at construction joints;
4. A low exothermia of the hydration reaction to minimize the thermal shrinkage
responsible for periodic (2 m) vertical cracks on the structure. The temperature
increase due to hydration is very important for this kind of structure because of the
size effect;
5. A low permeability in air and water and a low porosity of the concrete;
6. A good durability (low carbonation, low chloride penetration, etc.) since the
Reactor containment is designed to have a lifespan greater than 50 years;
7. Low delayed strains (creep and shrinkage) to ensure a minimum prestress loss at 50
years;
8. A high tensile strength to reduce cracking.
As it can be seen above, the compressive strength will be a logical consequence of some
of the above properties.
From this technical specification list, the final choice by EDF has been based mainly on
the work of three researchers in LCPC, Dr. F de Larrard [2, 5] in the formulation,
optimisation of mix design and mechanical properties of HPC, Dr. P. Acker [1] in the
physico chemical properties of concrete and Dr. J. -M. Torrenti [8] in the modelling of
temperature increase and stress development in early age concrete.
It is now known that it is possible to improve the intrinsic properties of concrete with an
optimisation of its granular skeleton and addition of new products like superplasticisers,
fillers and silica fume in order to significantly increase the compressive strength of
concrete. However, the above technical specifications can be obtained for a High
Performance Concrete (as opposed to High Strength Concrete where the main focus is
the strength). Indeed, properties (1), (5), (6) and (7) are highly correlated to the
compactness of the concrete. In order to reduce the exothermia of the concrete (4), it
has been decided to reduce the amount of cement and replace it by addition of fillers
(for compactness) and silica fume (to ensure an even better compactness without
diminishing the compressive strength too much). In order to ensure low delayed strains,
(3) and (7), a good possibility is to reduce the volume of cement paste (cement + water
+ silica fume). In parallel, in order to obtain a low autogeneous shrinkage (often very
high for HSC compared to normal concretes) a good solution is to have a high
water/cement ratio close to 0.6 where the autogeneous shrinkage is greatly reduced.
Finally, the basic creep will be quite low due to the low volume of cement paste, the
drying shrinkage will also be low due to the low total amount of free water and the
drying creep was experimentally measured very low (6) as is rather usual for a
HSC/HPC with silica fume.
All this analysis has been performed and presented internationally in [3, 4].
Furthermore, as far as the long run is concerned, an experimentally based simulation
performed in [6] shows that the delayed strains and the prestress losses expected on the
120 cm containment wall should be almost twice lower that for the regular concrete.
2.3. Prestressing
While maintaining the basic concepts and technology that permitted the development
of the 900 MWe (fig. 4), the standard project, and particularly:
the technique of placing prestressing cables by pushing a strand at a time into the
ducts,
the verification of moderate and regular values of coefficients of friction,
the final protection of these same cables after stressing by grouting with a special
cement grout,
resulted in the adoption of the following arrangements for P'4 1300 MWe / N4 1450
MWe units (fig. 5) (and EPR 1500 MWe project):
Fig. 4
PWR 900 MWe
Fig. 5
PRESTRESSING LAYOUT
The figure 5 arrangements shows the difference with the 900 Mwe:
use of higher strength 37T15S (even 55T15S for EPR) tendons,
use of complete revolution horizontal tendons instead of 3/4 revolution,
use of "inverted J" vertical tendons continuing across the dome instead of pure
dome tendons
STRAND
MODEL
SITE
TENDON
Number Initial tenof strand sioning Kn
Anchorage
JACK
2450
12T15
Freyssinet SF
19
3928
19T15
monogroup
system
Freyssinet K500
252,1
19
3928
19T15
monogroup
37T15
monogroup
Freyssinet K500
MM
Smm2
RkN
15,2
139
240
12
15,2
139
252,1
15,2
139
FESSENHEIM
BUGEY
TIHANGE
CRUAS
15,2
139
252,1
37
7649
1300 MWe - P4
EDF - 1st Generation
Double wall Containment
without steel liner
1300 MWe - P'4
EDF - 2nd Generation
Double wall Containment
without steel liner
PALUEL
ST ALBAN
FLAMANVILLE
15,2
139
252,1
37
7649
CATTENOM 1-3-4
CATTENOM 2 (Val
(Hal
15,2
15,2
15,7
139
139
150
252,1
252,1
265
37
37
37
7649
7649
7844
15,7
150
265
36
7632
15,7
15,7
15,7
15,7
15,7
150
150
150
150
150
265
265
265
265
279
36
37
37
37 and 55
54
7632
7844
8258
8258
12023
DAMPIERRE
GRAVELINES
TRICASTIN
BLAYAIS
ST LAURENT
CHINON
BELLEVILLE
PENLY
NOGENT
GOLFECH
1450 MWe - N4
EDF
Double wall Containment
without steel liner
1500 MWe - EPR
NPI
Double wall Containment
without steel liner
CHOOZ l
CHOOZ 2
CIVAUX 1
CIVAUX 2
Freyssinet K1000
37T15
monogroup
GPN ZPE1000
37T15
monogroup
GPN ZPE1000
37T15
monogroup
"
55 C 15 locally
55C15
Systme C
GPN ZPE1000
C 1500 FE
C1500 FE
3. SAFETY / INTEGRITY
In 1990, the Engineering and Construction Division of Electricit de France (EDF) was
choosing a High Strength / High Performance Concrete (HSC/HPC) as defined in II.2. for
the internal containment of CIVAUX 2 Nuclear Power Plant (NPP) Unit near Poitiers, the
third and last barrier in case of an accident.
From January 17th to 24th, 1996, the Reactor containment of the Civaux 2 unit, has
successfully undergone its containment building pressure test up to 0.53 MPa (absolute
pressure) which corresponds roughly to 5.3 times the atmospheric pressure. The leak rate
obtained, 0.19 % per day of the total mass of gas (dry air for the leakage test) present in
the containment, can be regarded as a world record for this kind of double prestressed
concrete containment design without a metallic or composite liner. This leak rate is firstly
to be compared with the construction criterion of 1 % (in the case of a double
containment) and secondly with the leak rate of the Civaux 1 unit (same design but normal
concrete instead of a HPC), equal to 0.38 %, that is, exactly twice as much as for the HPC.
The announced leak rate of 0.19 % per day of the total mass of gas present in the
containment corresponds to a leak volume of 28.7 m per hour measured in normal
conditions at 0 C and atmospheric pressure (1.013 105 Pa). A large part of this volume
goes through concrete micro-cracks, porosity but mainly through the cracks formed at
early age which are due to thermal shrinkage combined with autogenous shrinkage. These
cracks have been for sure re-closed by the prestressing forces. However, they may partly
re-open when the compression of the concrete diminishes as long as the pressure in the
containment increases.
So, the leak rate of the containment is closed to 0.162 % per day, which corresponds to the
leak rate safety criterion of a single containment with a metallic liner (as was previously
taken into account on the EDF 900 MWe NPP containment).
The results of EDF N4 technology double walls containment leak tests - Comparison with
the mean of all the EDF NPP double containment. - is as follows:
0,9
0,8
0,7
0,6
0,75 %
EDF N4 technology
0,5
0,4
0,3
0,34 %
0,39 %
0,38 %
0,2
0,19%
0,1
0
Mean
Chooz 1
Chooz 2
Civaux 1
Civaux 2
6. ACKNOWLEDGEMENTS
It would be too long to thank every person that has participated in this success.
However, the author would like to mention EDF SEPTEN-GC (Services Etudes et Projets
Thermiques et Nuclaires - Division GC), EDF-CNEN (Centre National d'Equipement
Nuclaire), GPN ("Groupement pour la Prcontrainte Nuclaire" of French prestressing
companies) with FREYSSINET Cy, that have been in charge of the prestressing works,
French Civil Works Companies in charge of the French NPP containments construction
and COYNE & BELLIER, the Design offices responsible for the calculations and the
constructions drawings of the containments.
CONCLUSION:
Our civil engineering answer to increase the safety level whilst lowering the costs:
IMPROVE EVER MORE CIVIL WORKS TECHNICS, NOTABLY IN
PRESTRESSING AND CONCRETE PERFORMANCES
REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
Torrenti J.M., Paties C, Piau J.M., Ackder P, de Larrard F. (1992) "La simulation
numrique des effets de l'hydratation du bton", Colloque Stru Co Me, Paris.
[9]