This work breakdown structure outlines the key elements of constructing a proposed building. It includes 5 main work breakdown structure elements: 1) Enabling work such as site preparation, 2) Foundation work including excavation and footings, 3) External works like constructing the building structure, 4) Internal works including electrical, plumbing and finishes, and 5) Final site clearance activities. Each main element is broken down into detailed sub-elements to fully define the scope of work.
This work breakdown structure outlines the key elements of constructing a proposed building. It includes 5 main work breakdown structure elements: 1) Enabling work such as site preparation, 2) Foundation work including excavation and footings, 3) External works like constructing the building structure, 4) Internal works including electrical, plumbing and finishes, and 5) Final site clearance activities. Each main element is broken down into detailed sub-elements to fully define the scope of work.
This work breakdown structure outlines the key elements of constructing a proposed building. It includes 5 main work breakdown structure elements: 1) Enabling work such as site preparation, 2) Foundation work including excavation and footings, 3) External works like constructing the building structure, 4) Internal works including electrical, plumbing and finishes, and 5) Final site clearance activities. Each main element is broken down into detailed sub-elements to fully define the scope of work.
WORK BREAK DOWN STRUCTURE FOR CONSTRUCTION OF PROPOSED BUILDING
WBS Element Definitions
WBS Code WBS Element 1 Enabling work WBS Element Description Preparing the site for construction activities includes clearing and cutting to remove unwanted vegetation and the removal of topsoil from construction site for general level surface. This element covers the cost of providing facilities to create site suitable for individuals and to overall control over site. Installation of fencing to control access or to provide security for selected areas is also part of this WBS element. WBS Code WBS Element 1.1 Site set up WBS Element Description Element includes temporary errection of site office, appointing the office staff and coordinating with head office regarding day to day work WBS Code WBS Element 1.2 Site access WBS Element Description Developing access road to site for transport of vehicles and men at site. It should be free from any obstruction WBS Code WBS Element 1.3 Line out work WBS Element Description Element includes studying the drawings and plotting them actually on ground with scale as per the drawings WBS Code WBS Element 2 Foundation WBS Element Description Foundation is part of substructure which includes excavation as per specifications in drawings and concreting the footings for superstructure. WBS Code WBS Element 2.1 Excavation WBS Element Description Excavate pits or trench for concrete framework. WBS Code WBS Element 2.2 Footing WBS Element Description Element includes all structures below and up to grade i.e. all concrete formwork and reinforcing steel their placement, curing and weather protection of structural concrete and slab on grade WBS Code WBS Element 2.3 Plinth construction
WBS Element Description
The element includes providing construction of ground & plinth beams and filling within them WBS Code WBS Element 3 External works WBS Element Description Work involving major activities to bring shape to structure WBS Code WBS Element 3.1 RCC work WBS Element Description Involves construction of RCC frame and slab with top slab behaving as roof of building WBS Code WBS Element 3.2 Masonry works WBS Element Description This element includes erection of the exterior and interior brick masonry wall, door and window frames. WBS Code WBS Element 3.3 Building finishes WBS Element Description Provide plaster to external and internal walls. WBS Code WBS Element 3.4 Landscaping WBS Element Description Element include designing and creating the landscape around the building. WBS Code WBS Element 3.5 Parking WBS Element Description Provide reserved car park spaces with proper markings and exit location points WBS Code WBS Element 3.6 Paving WBS Element Description This element includes the costs of on-site paving for roads and sidewalks WBS Code WBS Element 4 Internal works WBS Element Description Work elements to be provided within four walls of building WBS Code WBS Element 4.1 Electrical installation WBS Element Description Provide and install complete power distribution system including, lighting, outlets, branch wiring, fire alarm system, communication systems, fiber optic data transmission system, grounding, lightning protection system, UPS systems and access to the site monitoring and control system. WBS Code WBS Element 4.1.1 Lighting
WBS Element Description
Install lighting internally and externally in accordance with the latest Building regulations and codes. Separate inverter lighting will also be provided with an 8 hour battery backup. Adequate external lighting will be provided at entrances to and from the building as well as in parking. WBS Code WBS Element 4.1.2 Power supply (individual MCBs) WBS Element Description This element includes the on-site primary and secondary electrical distribution system down to the connection points for individual units WBS Code WBS Element 4.1.3 Security WBS Element Description Install security system to the building comprising fire alarms, CCTV and video surveillance. WBS Code WBS Element 4.1.4 Passage Lighting WBS Element Description Provide Passage lights in the building and in all selected places outside the building. WBS Code WBS Element 4.1.5 Telecommunications WBS Element Description Installation of all telecommunication systems required like, telephone, Broadband, LAN line network within the building WBS Code WBS Element 4.2 Mechanical Services WBS Element Description Element includes installation of gadgets and piping system WBS Code WBS Element 4.2.1 Water Services WBS Element Description Install water supply pipelines, its insulation and fittings. WBS Code WBS Element 4.2.2 Waste collection system WBS Element Description Provide all sanitary ware, soil and waste pipe work form WCs and toilets and connect to existing external manhole. WBS Code WBS Element 4.2.3 Rainwater pipes WBS Element Description Gutters and downpipes to be installed to keep rainwater away from the foundation of the building WBS Code WBS Element 4.2.4 Air Conditioning WBS Element Description Provide cooling and dehumidification during the summer by installation of split AC units WBS Code WBS Element 4.2.5 Ventilation
WBS Element Description
Natural stack effect with mechanical extract in urinals and WCs WBS Code WBS Element 4.3 Partition Wall WBS Element Description Installation of all internal partition walls made of plywood or Aluminum for dividing room space. WBS Code WBS Element 4.4 Flooring WBS Element Description Installation of floor system and floor finish like laminate flooring or tiles. WBS Code WBS Element 4.5 Ceiling WBS Element Description False ceiling system made in POP finish WBS Code WBS Element 4.6 Building finishes or painting WBS Element Description Interior finish applied to the inside walls and ceiling. Provide ceiling and wall coverings, doorframes and window frames, stairs and floor covering. WBS Code WBS Element 5 Site clearance WBS Element Description Cleaning and washing entire flooring area, parking space and cleaning glass panes of windows.