MITIGATION MEASURES
OCTOBER 2007
Weetwood
Elm House Farm, Saighton Lane,
Saighton, Chester, CH3 6EN
Tel. 01244 330111
Fax. 01244 332111
www.weetwood.net
CEG
KIRKSTALL FORGE
SIGNATURE SHEET
Report Title
Client
Report Status
Final
Date of Issue
30 October 2007
Prepared by
:
A. Morriss BSc (Hons), MSc
Checked by
:
C. D. Whitlow BSc, PhD
Approved by
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
CONTENTS
Page
i
ii
iv
Signature Sheet
Contents
List of Tables, Figures & Appendices
INTRODUCTION ................................................................ 1
1.1
1.2
1.3
1.4
BACKGROUND ..........................................................................................1
OBJECTIVES AND DELIVERABLES ...............................................................1
APPROACH TAKEN IN THIS STUDY ..............................................................2
PURPOSE OF THIS REPORT ........................................................................2
2.1
2.2
2.3
3.1
3.2
3.3
3.4
3.5
3.5.1
3.5.2
3.5.3
4.1
GEOMORPHOLOGICAL ASSESSMENT REQUIREMENTS.................................. 13
4.2
GEOMORPHOLOGICAL ASSESSMENT METHODS .......................................... 13
4.2.1. Calculating Sediment Transport Rates ....................................................... 14
4.2.2. Sediment Transport Limitations and Assumptions ....................................... 15
4.2.3. Scenario 1: Without FRC.......................................................................... 16
4.2.4. Scenario 2: With FRC .............................................................................. 16
4.3. GEOMORPHOLOGICAL ASSESSMENT RESULTS .............................................. 17
4.3.1. Sediment Transport Rates ....................................................................... 17
4.3.2. Sediment Transport Rates: Results Summary............................................. 23
4.4. GEOMORPHOLOGICAL ASSESSMENT DISCUSSION ........................................ 23
4.4.1. Impacts of the FRC on the Existing Channel Geomorphology ........................ 24
4.4.2. Geomorphological Consequences: Summary .............................................. 27
4.4.3. Additional Impacts of the Proposed FRC on the Existing Channel .................. 27
4.5. FRC DESIGN: GEOMORPHOLOGICAL CONSIDERATIONS ................................. 29
Weetwood
ii
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
BIBLIOGRAPHY ............................................................... 37
Weetwood
iii
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
LIST OF TABLES
Table 2.1 FRC hard engineering design drawings as available for this study...............3
High flow design hydrological estimates were drawn from the existing iSIS model for
the 100-year and 100-year plus allowance for climate change (100-year CC) events.
The QMED estimate was drawn from the HiFlows-UK website whilst the two low flow
design estimates for Q95 and Q50 were read from the flow duration curve held on the
National River Flow Archive (NFRA). Design estimates as used are summarized in
Table 3.1.Table 3.1. Design hydrological estimates and sources as input into the iSIS
model...............................................................................................................6
Table 3.2. Model scenarios as run during this study...............................................7
Table 3.3. Simulated results for the 100-year and 100-year CC events comparing the
pre- (outline design) and post-refinement alterations to the FRC. .......................... 11
Table 3.4. Results of roughness sensitivity tests. Sensitivity results shown against
refined FRC simulation outputs for 100-year CC design event. ............................... 11
Table 4.1. Modelled flows for sediment transport calculations. .............................. 15
Table 4.2. Sediment sizes as used for sediment transport calculations. .................. 15
Table 4.3. Channel cross sections modelled for scenario 1 (without FRC). .............. 16
Table 4.4. Channel cross sections modelled for scenario 2 (with FRC).................... 16
LIST OF FIGURES
Figure 2.1. Proposed plan view of FRC: possible pool-riffle sequence as illustrated is
approximate only. ..............................................................................................5
Figure 2.2. Proposed refinements to the hard engineering cross section as supplied.
Levels and measurements indicative only. Note that TRHB has been drawn to the left
of the cross section. ...........................................................................................5
Figure 3.1. FRC iSIS cross section showing revised Mannings n estimates (0.033 in
low flow channel and 0.045 on margins) to reflect the introduction of marginal
vegetation to screen the hard engineering structures. ............................................7
Figure 3.2. Results of 100-year CC design event in long section showing outline FRC
cross section (pre-refinement) and FRC post-refinement from Rein Road Weir to
Kirkstall Bridge. .................................................................................................9
Figure 3.3. Results of 100-year CC design event in long section showing outline FRC
cross section (pre-refinement) and FRC post-refinement from Rein Road Weir to the
lower railway bridge. ..........................................................................................9
Figure 3.4. Results of 100-year design event in long section showing baseline (no
FRC), outline FRC cross section pre-refinement and FRC post-refinement from Rein
Road Weir to Kirkstall Bridge. ............................................................................ 10
Figure 3.5. Results of 100-year design event in long section showing baseline (no
FRC), outline FRC cross section pre-refinement and FRC post-refinement from Rein
Road Weir to the lower railway bridge. ............................................................... 10
Figure 3.6. Results of 100-year CC design event in long section showing refined FRC
against sensitivity test results. .......................................................................... 12
Figure 4.1. The Meyer-Peter and Muller (1948) sediment transport function ........... 14
Figure 4.2. Sediment transport sand fraction Q95. ........................................... 17
Weetwood
iv
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
1 INTRODUCTION
1.1
BACKGROUND
In the present situation, the existing flood risk to the proposed redevelopment
at Kirkstall Forge is unacceptable to the Environment Agency largely due to the
potential blockage to the passage of the River Aire beneath a pair of railway
bridges. Flood mitigation has been proposed which involves the introduction of
an entirely new, engineered flood relief channel (FRC).
The construction of the FRC is intended to reduce the flood risk associated with
blockage of the two bridges. Previous modelling work has confirmed the
potential of a FRC to lower flood risk to acceptable levels and has allowed basic
cross section area and geometry to be outlined: the new channel will be a
minimum of 25m wide (based on a Mannings n roughness coefficient estimate
of 0.033).
Weetwood Environmental Engineering (Weetwood) has been supplied with a
proposed hard engineering design of gross cross section geometry based on
these design specifications. This cross section requires refinement in order to:
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
1.4
Re-run the iSIS model to ensure that the hydraulic performance of the
FRC is largely unaffected
using
established
river
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Author
Date
DV-SK-011 Rev P2
RD White Young
Green Consulting
20.06.2007
Kirkstall Forge
Bypass
Channel.dwg
No.
675_SK03
Rev.C
10.09.07
Bypass
Channel
Rev. C copy.jpg
675_SK03
Randle
Siddeley
Associates
10.09.2007
Kirkstall
Forge
Bypass-Channel
Section A-A.dwg No.
675_SK04
Rev.D
10.09.07
Randle
Siddeley
Associates
10.09.2007
This information formed the basis of the cross section and planform geometry
refinements as detailed below.
2.2
Weetwood
761R01/AG
30 October 2007
CEG
2.3
KIRKSTALL FORGE
FRC SUGGESTED REFINEMENTS
The gross cross section design as dictated by the hard engineering structures
required refinement mainly to:
1) Provide additional potential fish habitat by the creation of a more varied
flow pattern and potential refugia and lying up areas
2) Provide aesthetic softening of the appearance of the hard engineered
structures as proposed.
In order to address 1) and 2) above, the approach taken was to introduce a
pair of marginal coir net berms to create a sinuous, low flow channel running
along the middle of the FRC. It is proposed to tie this material into the hard
engineering structures and to plant emergent and marginal aquatic vegetation
designed to partially screen the vertical revetment on the TLHB and the base of
the rip-rap on the TRHB.
It is understood that, due to the risk of blockage associated with vegetation and
large woody debris within local reaches, planting trees along these margins
would be unacceptable to the Environment Agency. However, given the vertical
face of the proposed revetment, more effective screening of the TLHB may be
possible using trees and shrubs tolerant of periodic flooding. Costs in terms of
a decrease in conveyance and increase in flood levels are likely to be slight if
only one bank is vegetated in this manner. However, it may be necessary to
set the berm on this bank at a slightly higher level to ensure that any trees
planted here would survive
Without using trees to soften the rip-rap, an alternative method would be to
green this feature by blinding the batters with gravel and soil during
installation and seeding with grass and herbs of local provenance. This may
allow the surface of the rip-rap and the face of the TRHB to appear more
natural and established soon after seeding with an appropriate mixture.
Further structural refinement is proposed by incorporating the engineering of a
sequence of pools and riffles designed to introduce some low flow variability
into the new reach. Running the riffles diagonally across the FRC will, in
conjunction with the marginal mattresses, force flow from side to side of the
channel with passage over each feature. Associated pools and zones of scour
could be added at alternate banks in order to provide a wider, more natural
variety of habitat for fish within the reach. A possible configuration of this
arrangement is presented in Figure 2.1 and Figure 2.2.
Further flow diversity could be ensured by lowering the invert level of one side
of the riffle slightly to force the flow to alternating sides of the FRC during
periods of low discharge if required. Larger material may also be incorporated
within the surface of the riffle i.e. in the boulder fractions in order to
increase small-scale bedform and flow diversity.
Information regarding
appropriate minimum sizing of material can also be found within the
geomorphological assessment section below.
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Figure 2.1. Proposed plan view of FRC: possible pool-riffle sequence as illustrated is
approximate only.
Figure 2.2. Proposed refinements to the hard engineering cross section as supplied.
Levels and measurements indicative only. Note that TRHB has been drawn to the left
of the cross section.
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
3 HYDRAULIC MODELLING
3.1
3.2
HYDROLOGY
High flow design hydrological estimates were drawn from the existing iSIS
model for the 100-year and 100-year plus allowance for climate change (100year CC) events. The QMED estimate was drawn from the HiFlows-UK website
whilst the two low flow design estimates for Q95 and Q50 were read from the flow
duration curve held on the National River Flow Archive (NFRA).
Design
estimates as used are summarized in Table 3.1.
Table 3.1. Design hydrological estimates and sources as input into the iSIS model.
Flow Exceedence
Probability / Return
Period
Q95
3.3
Discharge (m3/s)
Source
Comment
3.367
NFRA
Q50
NFRA
QMED
100yr
100yr CC
138.8
300.63
360.756
HiFlows-UK
Atkins
Atkins
As quoted on website
Approximate (read
from flow duration
curve)
As quoted on website
Scaled to Newlay Weir
Scaled to Newlay Weir
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Figure 3.1. FRC iSIS cross section showing revised Mannings n estimates (0.033 in
low flow channel and 0.045 on margins) to reflect the introduction of marginal
vegetation to screen the hard engineering structures.
3.4
FRC Included
Return Period
Q95
Q50
QMED
100-year
100-year CC
Q95
Q50
QMED
100-year
100-year CC
Comment
-/-/-/-/-/-/-/-/-/-/-
100-year CC
100- year CC
100-year CC
Weetwood
Purpose
Baseline Scenarios for
Geomorphological
Analysis
Geomorphological
Analysis and Flood Risk
Flood Risk Sensitivity
Increased Growth of
Vegetation
Flood Risk Sensitivity:
Addition of Trees to Left
Bank
Flood Risk Sensitivity
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Baseline scenarios were also re-modelled (i.e. without the inclusion of the FRC)
for use in the geomorphological assessment.
Runs as executed during this
study are listed in Table 3.2.
3.5
3.5.1
3.5.2
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
100yr CC Design Event: Long Section
48
46
Elevation/ SG (mAOD)
44
42
40
38
36
34
32
UPSTREAM RAILWAY
BRIDGE
DOWNSTREAM
RAILWAY BRIDGE
30
0
500
1000
1500
2000
2500
Right bank
Bed
Figure 3.2. Results of 100-year CC design event in long section showing outline FRC
cross section (pre-refinement) and FRC post-refinement from Rein Road Weir to
Kirkstall Bridge.
Elevation/ SG (mAOD)
44
42
40
38
36
34
32
DOWNSTREAM
RAILWAY BRIDGE
UPSTREAM RAILWAY
BRIDGE
30
0
100
200
300
400
500
600
700
800
900
1000
Right bank
Bed
Figure 3.3. Results of 100-year CC design event in long section showing outline FRC
cross section (pre-refinement) and FRC post-refinement from Rein Road Weir to the
lower railway bridge.
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
100yr Design Event: Long Section
48
46
Elevation/ SG (mAOD)
44
42
40
38
36
34
32
UPSTREAM RAILWAY
BRIDGE
DOWNSTREAM
RAILWAY BRIDGE
30
0
500
1000
1500
2000
2500
Right bank
Bed
Figure 3.4. Results of 100-year design event in long section showing baseline (no
FRC), outline FRC cross section pre-refinement and FRC post-refinement from Rein
Road Weir to Kirkstall Bridge.
Elevation/ SG (mAOD)
44
42
40
38
36
34
32
UPSTREAM RAILWAY
BRIDGE
DOWNSTREAM
RAILWAY BRIDGE
30
0
100
200
300
400
500
600
700
800
900
1000
Right bank
Bed
Figure 3.5. Results of 100-year design event in long section showing baseline (no
FRC), outline FRC cross section pre-refinement and FRC post-refinement from Rein
Road Weir to the lower railway bridge.
Weetwood
10
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Table 3.3. Simulated results for the 100-year and 100-year CC events comparing the
pre- (outline design) and post-refinement alterations to the FRC.
Node
BY_130
BY_065
BY_000
3.5.3
100yr
Outline
FRC
Design
(mAOD)
38.368
38.256
38.13
100yr
Refined
FRC
(mAOD)
Difference
(m)
38.403
38.262
38.13
0.035
0.006
0
100yr CC
Outline
FRC
Design
(mAOD)
38.7
38.57
38.423
100yr
CC
Refined
FRC
(mAOD)
38.736
38.577
38.423
Difference
(m)
0.036
0.007
0
Sensitivity Tests
A short series of sensitivity tests to varying roughness estimates within the
bypass channel were run using the 100-year CC design estimate in order to
assess impact on flood risk. These included:
S1: Raising the roughness of the FRC margins to 0.055 to represent increased
vegetation
S2: Raising the roughness of the FRC TLHB to 0.07 to represent tree growth
S3: Raising the roughness of the entire FRC to 0.045
These results are presented against the results of runs using the refined FRC
(Mannings n of 0.033 and 0.045) in long section in Figure 3.6. Results
within the FRC are presented in Table 3.4. None of the sensitivity tests
caused a significant increase in flood risk to the development site. This is to
be expected since any decrease in conveyance in the FRC is likely to result in
more flow through the existing meander.
Table 3.4. Results of roughness sensitivity tests. Sensitivity results shown against
refined FRC simulation outputs for 100-year CC design event.
Node
100yr
CC
Refined
FRC
BY_130
BY_065
BY_000
38.736
38.577
38.423
Weetwood
S1:
Channel
0.033
Banks
0.055
38.775
38.599
38.423
Difference
from
100yr CC
Refined
FRC
0.039
0.022
0
S2:
Banks
0.045
0.07
38.738
38.578
38.423
11
Difference
from
100yr CC
Refined
FRC
0.002
0.001
0
S3:
Entire
FRC
0.045
38.818
38.622
38.423
Difference
from
100yr CC
Refined
FRC
0.082
0.045
0
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
100yr CC Design Event Sensitivity: Long Section
48
46
Elevation/ SG (mAOD)
44
42
40
38
36
34
32
UPSTREAM RAILWAY
BRIDGE
DOWNSTREAM
RAILWAY BRIDGE
30
0
Left bank
100yr CC FRC TLHB 0.07
500
1000
1500
2000
2500
Figure 3.6. Results of 100-year CC design event in long section showing refined FRC
against sensitivity test results.
Weetwood
12
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
4 GEOMORPHOLOGICAL ASSESSMENT
4.1
4.2
Assess the potential impact of the proposed Flood Relief Channel (FRC)
on the geomorphological processes operating within the existing channel
primarily via sediment entrainment/ transport modelling
Weetwood
13
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Sediment transport modelling coupled with the existing Fluvio report (Fluvio,
2006) and additional design plans and iSIS model results were used to gain an
understanding of the dynamics of potential morphological change within the
River Aire and to indicate likely patterns of change which may otherwise be
unknown.
4.2.1. Calculating Sediment Transport Rates
Sediment transport rates were calculated for a number of cross sections in the
vicinity of the proposed FRC. Results from the hydraulic modelling undertaken
as part of this study were used to provide the key hydraulic parameters. For
each cross section, the Peter-Meyer and Muller transport function (see Figure
4.1) was used to calculate potential sediment transport rates for a range of
flows and a range of sediment sizes.
The Meyer-Peter and Muller sediment transport equation (Meyer-Peter and
Muller, 1948) and as reviewed in Wilcock (2001).
(1)
qs
( s 1) gD
=8
( s 1) gD
3/ 2
( s 1) gD
= ghS
Figure 4.1. The Meyer-Peter and Muller (1948) sediment transport function
Models were run for two scenarios:
Scenario 1: without the designed FRC (current conditions), and
Scenario 2: with the FRC refined.
The flows used to drive the models are shown in Table 4.1 below. These flows
are chosen as they provide a full range of flows from very low to very high
and can be used to observe likely sediment dynamics over a full range of flow
conditions. In natural channels, QMED is approximate to bankfull discharge
and is indicative of the most geomorphologically effective flows within many
rivers (Knighton, 1998).
Weetwood
14
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Table 4.1. Modelled flows for sediment transport calculations.
Flow Exceedence
Probability / Return
Period
Q95
Q50
Discharge
Comment
3.367 m3/s
9 m3/s
QMED
138.8 m3/s
100yr CC*
360.756 m3/s
* Note: the sediment transport calculations use a 100yr CC flow incorporating an assumption of a
23% blockage at the upper railway bridge.
Sediment sizes used within the models are based on typical size class
thresholds cited in fluvial geomorphology literature (Knighton, 1998), see
Table 4.2 below. The sediment size used in the transport models is the
minimum size within the size classes. Fluvio (2006) indicate that the gravel
size fraction (10-40mm) is dominant (40%-50%) along with sand material,
although a range of sediment size up to the cobble fraction is found within the
channel at Kirkstall Forge.
Table 4.2. Sediment sizes as used for sediment transport calculations.
Sediment Size
Classes
Boulder
Cobble
Gravel (Coarse)
Gravel (Fine)
Sand
Size in Metres
(Lower Size Limit)
0.256
0.064
0.016
0.002
0.00006
The results of the iSIS hydraulic model for the range of flows listed above
were extracted and imported into an Excel spreadsheet.
A rearranged
Manning`s formula was used to derive a water surface slope (based on
velocity and stage outputs from iSIS) which was then used along with flow
depth, flow width and sediment size to derive a sediment transport rate for a
particular sediment size fraction.
In this study, the sediment transport rates are expressed as a volume of
sediment moved over a period of time (m3/s). The volume (m3) can be
converted into a mass (kg) by multiplying the volume by 2650 (dry weight of
sediment in kg per m3).
4.2.2. Sediment Transport Limitations and Assumptions
The fluvial geomorphology literature lists many assumptions and limitations in
the use and interpretation of sediment transport functions.
Some key
assumptions and limitations are:
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
The transport function assumes a steady and uniform flow. It does not
take into account turbulence or velocity fluctuations.
As outlined earlier, sediment transport data have not been collected for this
study and therefore the model results have not been calibrated: the figures
obtained are therefore used for indicative purposes only. The relative values
being more appropriate to this study than the absolute values.
4.2.3. Scenario 1: Without FRC
Sediment transport rates are calculated for cross sections within the vicinity of
the proposed FRC. Cross sections used are shown in Table 4.3 below.
Table 4.3. Channel cross sections modelled for scenario 1 (without FRC).
Channel Cross
Section
1700200
1700176C
1700066
1607120D
Location
Located 24 m upstream of railway bridge
Upstream railway bridge
Located within the existing channel meander (between the
two rail bridges)
Located immediately downstream of the proposed FRC
outlet
Cross
Location
Located 24 m upstream of railway bridge
Upstream railway bridge
Located within the existing channel meander (between the
two rail bridges)
Located immediately downstream of the proposed FRC
outlet
Located within the upstream end of the proposed FRC
Located within the mid-section of the proposed FRC
Located within the downstream end of the proposed FRC
It should be noted that a limited number of cross sections within the Kirkstall Forge reaches
were modelled to provide sediment transport estimates.
Weetwood
16
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
0.00010
0.00008
0.00006
0.00004
0.00002
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
Weetwood
17
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Sediment Transport (Sand Fraction): Q50
0.00160
0.00140
0.00120
0.00100
0.00080
0.00060
0.00040
0.00020
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
0.00070
0.00060
0.00050
0.00040
0.00030
0.00020
0.00010
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
18
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Sediment Transport (Sand Fraction): QMED
0.14000
0.12000
0.10000
0.08000
0.06000
0.04000
0.02000
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
0.14000
0.12000
0.10000
0.08000
0.06000
0.04000
0.02000
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
19
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Sediment Transport (Coarse Gravel Fraction): QMED
0.10000
0.09000
0.08000
0.07000
0.06000
0.05000
0.04000
0.03000
0.02000
0.01000
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
0.01400
0.01200
0.01000
0.00800
0.00600
0.00400
0.00200
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
20
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Sediment Transport (Sand Fraction): 100yr CC
0.50000
0.45000
0.40000
0.35000
0.30000
0.25000
0.20000
0.15000
0.10000
0.05000
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
0.45000
0.40000
0.35000
0.30000
0.25000
0.20000
0.15000
0.10000
0.05000
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
21
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Sediment Transport (Coarse Gravel Fraction): 100yr CC
0.45000
0.40000
0.35000
0.30000
0.25000
0.20000
0.15000
0.10000
0.05000
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
Figure 4.11.
0.20000
0.15000
0.10000
0.05000
0.00000
1700200
1700176C
1700066
1607120D
BY 130
BY 065
BY 000
22
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Boulders are not transported at any of the modelled flows within any of
the modelled cross sections.
At Q50 flows, sand and fine gravel are the only size fractions potentially
transported.
The greatest potential transport rates, for a given sediment size, are
located at cross section 1700200.
Potential sediment transport rates are greater within the existing channel
meander compared to potential rates at the locations of the entrance and
exit to the proposed FRC.
Boulders are not transported at any of the modelled flows within any of
the modelled cross sections.
Potential transport rates are consistently higher within the FRC compared
to those in the existing meander, for a given sediment size and flow.
23
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
In addition, the iSIS model results, the sediment transport modelling and an
understanding of fluvial processes has been used to make some key
recommendations about the geomorphology related design aspects of the FRC.
4.4.1. Impacts of the FRC on the Existing Channel Geomorphology
4.4.1.1. Erosion and Deposition Pre-FRC
The River Aire at Kirkstall forge is a laterally constrained channel, but with a
long profile characterised by pool and riffle sequences: a consequence of
changes in bed elevation to accommodate temporal and spatial fluctuations
in flow velocities and sediment transport. Sediment within the channel is
dominated by gravels (10-40mm) and sands, but also includes cobbles.
Fluvio (2006) suggest that coarse material is only entrained and transported
very infrequently during high flows whereas the sand fraction is highly
mobile. The absence of exposed gravel bars within the reach and protected
channel banks indicates the river is sediment supply limited.
The results of the sediment transport modelling are broadly in line with these
observations. Sand material is shown to be mobile through all flows above
Q95, whilst coarse-gravels and cobbles are mobilised at flows of QMED and
above.
Results suggest that the highest rates of potential sediment transport
(increased flow velocities) occur upstream of the proposed FRC (cross section
1700200) and remain high (albeit at a lower rate) within the existing channel
meander (cross section 1700066). However, flow velocities and therefore
potential sediment transport rates, are significantly lower at cross sections
1700176C and 1607120D and deposition here is more likely, particularly for
sand size material at lower flows where sediment transport rates are zero.
The main reason for the reduction in flow competence here is the widening of
the channel within the meander loop (~50m) near the railway bridges
compared to further upstream (~25m) near the footbridges. This propensity
for deposition is indicated in the field by the raised bed elevations (riffles)
within the meander loop - particularly on the inside of the meander bend.
4.4.1.2. Erosion and Deposition Within the Existing Channel (Post-FRC)
There are two main impacts of the FRC on sediment dynamics within the
existing channel. The first is a significant increase in channel velocity and
therefore potential sediment transport approximately 24m upstream of the
upper railway bridge (cross section 1700200). The second is a marked
reduction in velocity and potential sediment transport rates within the
existing channel meander (1700066), in between the two railway bridges
(see Figure 4.13). The likely impacts of these changes are discussed in more
detail below.
Weetwood
24
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
AREA
POSSIBLE
INCREASED
Area ofOF
possible
increased
EROSION
AROUND
THE HUMP
&
sediment
erosion around
the `hump`
and
POSSIBLY
FURTHER
UPSTREAM
possibly further
upstream
Area
of OF
possible
increased
AREA
POSSIBLE
INCREASED
sediment
deposition
and channel
SEDIMENT
DEPOSITION
AND
bank erosion
Figure 4.13. Areas of potential increased erosion and deposition. Based on Drawing
360 Required Bank Heights, 05/10/2006, Weetwood.
4.4.1.3. Cross Section 1700200
Model results suggest that the FRC will cause a significant increase in flow
velocities and therefore potential sediment transport rates at cross section
1700200: most pronounced at flows of QMED and above. This cross section
is located upstream of the new footbridge and at the location of a riffle or
hump (see Fluvio, 2006). Although not modelled for sediment transport
rates, the cross sections further upstream (upstream to 1700350) show a
similar increase in flow velocity and therefore, by extension, there is
potential for increased sediment transport rates at these locations as well.
The increased potential transport rates are most pronounced at flows of
QMED and above and likely to be a result of the greater flow conveyance
through the FRC at these flows.
The model results suggest there may be significant effects on the stability of
the channel at and immediately upstream of cross section 1700200. The
sediment transport rates calculated can only provide an indication of
potential sediment transport: they are based on the assumption of an
unlimited supply of sediment available for transportation. As the River Aire
at Kirkstall Forge appears to be a sediment supply limited channel, then the
excess stream power is likely to be transferred into bed and or bank scour
within this section of river. The likely consequences of this excess stream
power are threefold:
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
The Fluvio report (Fluvio, 2006) suggests that skimming of the hump (the
raised bed level at cross section 1700200 and upstream) would only result in
a very short-term lowering of the bed elevation. Under current flow and
sediment transport conditions the feature would reform within several years
or a decade. However, erosion of the hump resulting from significant
change to the flow hydraulics (a consequence of the construction of the FRC)
would be likely to cause a permanent change in the bed elevation at this
location and further upstream.
4.4.1.4. Cross Section 1700066
Model results indicate a significant reduction in potential sediment transport
rates within the existing channel meander (in between the two railway
bridges), once the FRC is in operation. This modelled reduction in stream
competence is a direct consequence of the reduction in flow through the
existing channel meander. At Q95, Q50 and QMED discharges approximately
half of the flow within the river is diverted through the FRC. This is increased
to ~63% at 100yr CC flows (with 23% railway bridge blockage).
Material that would normally be transported through this reach at Q95 and
Q50 flows (largely sand), is more likely to be deposited within the channel
meander (as indicated by the cross section 1700066 model results). Even at
QMED flows, gravel material may be deposited whereas previously it would
have been more likely to be transported through the reach. When the
effects of the increased likelihood of bed scour upstream of the FRC are
considered (i.e. increased availability of material for potential deposition as
outlined above) the effects of the reduced stream power within the existing
meander are compounded.
Although sand material may be deposited within the meander section during
low to moderate flows, model results indicate that this material would be
removed at QMED and above. However, more coarse material (gravels) may
only be re-mobilised and transported from this reach during the very highest
discharges. Cobble material (if eroded and transferred to this reach from the
hump as outlined above) may reside within the meander permanently.
Material deposited within the reach may form a more prominent gravel bar
on the inside of the meander loop, adding material to the existing bar
feature. The river here may respond to the formation of a gravel bar feature
in one of two ways.
Weetwood
26
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Firstly, the river channel may become narrower and more incised (forced
towards the outside of the meander bend), with a concomitant increase in
flow velocity in order that continuity of flow is maintained. Secondly, and
potentially less desirable, is a tendency for the river channel to migrate
laterally, causing erosion of the channel banks on the outside of the meander
loop. The likelihood and extent of the latter depends to a large extent on the
composition and strength of the material of the channel banks: soft material
(alluvial material) will be more prone to erosion than more resistance
material (bedrock).
Information about the composition of the channel
material at this location is not available. However, Fluvio (2006) indicate
that the meander loop has undergone a degree of migration over the last
150 years indicating that the banks are prone to erosion. It should be noted
that meander evolution at this location may eventually threaten the stability
of the steep slope at the top of which sits the Leeds and Liverpool Canal.
Weetwood
27
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Weetwood
28
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Impacts on fish habitats downstream of the proposed FRC are likely to be
short-term only. One consequence of the potential bed scour at the hump
will be mobilisation of bed sediments and re-deposition of this material
further downstream. It has already been indicated that fine material from
the bed scour may be deposited within the existing channel meander.
During subsequent floods, this material is likely to mobilised further,
entrained within the flow and then re-deposited in downstream sections.
However, the flow regime downstream will not be affected and any fine
material that is deposited (as a consequence of bed scour) is likely to be
removed during subsequent moderate to high flows. Furthermore, the
volume of fine material potentially entrained from upstream bed scour is
considerable, but finite and, therefore, may not pose a long-term issue.
Although the fish habitats are likely to be affected to varying degrees, the
additional habitat afforded by the FRC may counter any disturbance to
habitats within the existing channel. A key objective of the FRC is to provide
a suitable habitat for fish populations, notwithstanding the main
consideration for flood risk mitigation.
29
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
The current FRC designs provide the scope for hydraulic variability (i.e. the
incorporation of pools and riffles), and these will promote a degree of
turbulence within the channel and help promote localised fluctuations in
velocity leading to more effective sediment entrainment. This engineered bed
topography should provide a broad template for the hydraulic variability to
ensure an effective transfer of sediment through the new channel. However,
there are likely to be additional natural bed forms that form and move within
the channel in response to the fluctuating influx of flow and material.
High flow sediment transfer is greater through pools than riffles and low
flow storage at riffles is greater than at pools. This provides the
conditions for the coarse material on riffles and the maintenance of pool
riffle sequences
Successive sequences of pools and riffles often have their high points
(on riffles) and low points (in pools) alternating from one side of the
bank to the other.
Weetwood
30
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Material used to construct the pool-riffle sequence must also reflect the
characteristics of flow nature of sediment within the channel. As indicated by
the sediment transport models, the cobble size fraction of bed load is
potentially entrained within the FRC however, only at 100yr CC flows. This
suggests that a conservative estimate of material used to `seed` the riffles,
must be somewhat larger than cobbles (i.e. an intermediate axis greater than
64mm). As flows vary in velocity (and therefore entrainment capacity) around
a modelled mean value, an appropriate minimum size for riffle seeding would
be in the order of 100mm. Occasional larger material may also be used, to
provide localised flow variability, to act as zones of deposition and for fish
habitat purposes.
Additional flow variability may also be provided by alternating the location of
successive riffles from one side of the channel to the other (see above). Not
only will this provide valuable flow diversity (undercurrents, secondary
circulation) important as fish habitats, it will provide the channel with a
greater scope for internal adjustments (i.e. hydraulic and bed form
variations). This is important as the new channel attempts to attain a form
and flow that is at equilibrium with the prevalent flow and sediment regimes.
Once the gross riffle and pool sequences are constructed, flows within the
channel will modify the dimensions of these features to a certain extent.
However, as Fluvio (2006) and this study have indicated, local reaches of the
River Aire appear to be sediment supply limited. As such any attainment of
equilibrium within the man-made pool riffle sequence (i.e. material sorting,
armouring, subtle morphological adjustments) make take several years or
flood cycles to mature.
31
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
There are a number of options that may be employed to reduce the impact of
these potential issues and may be viewed as a starting point for further
investigation.
4.6.1. Reducing Bed-Scour
The cause of the possible bed scour upstream of the FRC inlet (upstream of
cross section 1700200) may be a throttle effect through the FRC at moderate
to high flows. Moderation of this impact could be achieved through treating
the cause or halting the effects by:
Reducing the flow competence through the FRC at high flows thereby
slowing flow velocities through the channel (increasing roughness) and
thus causing a backing-up effect further upstream, leading to reduced
flow competence (and channel velocities) at the point of possible bed
scour. Although this is an effective means of reducing or even halting
the bed scour potential, it should be noted that this method is not an
effective means of delivering the required flood protection benefits of
the FRC.
Weetwood
32
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Removal of the upstream bed scour problem (see above) may prevent
coarse material from being entrained and further deposited in the
meander loop. However, even by halting or reducing the bed scour
issue, sediment transferred through the reach at the highest flows, will
still be deposited within the meander loop causing a build-up of sediment
due to the reduced flows with the operation of the FRC.
Increasing the flows through the existing channel meander may increase
the competence of flows to remove sediment deposited within the
meander loop. This option, however, may reduce the effectiveness of the
FRC for reducing flood risk as less flow would pass through in high flows.
Furthermore, the entrance to the new channel would require engineering
in such a way that during high flows, only a pre-determined volume of
water is able to enter.
Weetwood
33
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Modelled sediment transport rates through the FRC indicate that material
will be transferred effectively through the new channel, with no major
morphological changes expected. However, some morphological
readjustment of the designed bed features (pool and riffle sequences) is
to be expected as the channel readjusts to flow and sediment inflows.
The broad-scale bed features and overall design of the FRC are generally
appropriate for the flow characteristics and sediment dynamics within the
River Aire. However, detailed design features, such as the nature of bank
material and cross section dimensions may require further assessment
for a full understanding of its long-term operational effectiveness and
stability.
Weetwood
34
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
marginal berms within the FRC designed to encourage a sinuous flow path
and provide a platform for marginal vegetation
blinding with gravel and soil of the rip-rap battering in order to allow
vegetation to be readily established and provide a more natural
appearance.
The design of these features is broadly in-line with the geomorphological analysis.
Material with an intermediate axis >64mm could be used to provide a relatively
stable platform from which to initiate or seed a semi-natural pool-riffle sequence.
It is currently proposed to use material of 100mm to 300mm to form the basis of
the features introduced to the new FRC. Subsequent development and maturation
of these bedforms should be expected over several flood events in response to
anticipated sediment delivery from the main channel and scour both within the
main channel and the FRC. However, initial use of material of the above size is
expected to resist transport by all but the most extreme discharges thereby
ensuring that the main riffle and habitat features as installed are not destroyed.
The design of the features within the FRC has been deliberately broad-scale.
Over-engineering the in-stream features is to be avoided and natural sorting and
armouring of the large-scale features as proposed should be expected as a natural
response of the river to the significant geomorphological change in local reaches
prompted by the introduction of an entirely new channel.
Section 1 as shown in White Young Green drawing DV-SK-011 Rev P2 shows riprap overlying a 0.17m thick Reno mattress. It is unclear what benefit this
mattress will offer when positioned beneath rip-rap: it is possible that setting a
mattress at this location (i.e. beneath the rip-rap) will actually be counterproductive. It is recommended that further justification for this section of the
hard-engineering design is sought since the mattress may act as a plane of shear
to the overlying material.
iSIS simulations incorporating the changes to the overall FRC design have shown
that there is a negligible increase in flood levels due the introduction of the
marginal berms and vegetation to soften the engineered channels appearance.
However, subsequent broad-scale geomorphological modelling using results from
the hydraulic model suggests that there may be several significant changes to the
local geomorphological regime which may need to be addressed prior to finalising
and implementing any designs. Most notably, these include:
Weetwood
35
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
Possibility of erosion of the outer bend of the meander between the two
railway bridges due to development of the point bar from aggradation of
sediment transported into the reach from upstream scour.
Meander
evolution at this location may eventually threaten the stability of the steep
slope at the top of which sits the Leeds and Liverpool Canal.
Mitigation options for both these scenarios are outlined above including bed check
structures and additional bank and revetment protection. However, further more
detailed investigation is required in order to reduce the current uncertainty
concerning the potential magnitude of these impacts. Hydraulic model runs
examining these mitigation scenarios have not been attempted in this study.
The modelling and geomorphological assessment have also revealed that there is
some potential for an impact on fish habitat within the existing meander.
However, this is expected to be short term only and is mitigated by the
introduction of new habitat features within the FRC. Deposition of fine material
during periods of low flow is possible due to the decrease in velocities within the
meander reach between the two bridges a direct consequence of the
introduction of the FRC. However, this material is expected to move through the
reach during higher flows on an annual basis. It should be noted that this cycle of
deposition and transport is a natural process and, whilst a change from the
existing regime within the meander, is likely to be consistent with patterns of
erosion and aggradation in the River Aire locally.
Finally, it should be reiterated that the approach taken in this study has been
necessarily broad-scale and semi-quantitative. Results as quoted within the body
of this report rest on a number of assumptions which would, ideally, be subject to
field verification and confirmation in order to reduce the levels of uncertainty
surrounding the qualitative judgements as presented.
Weetwood
36
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
6 BIBLIOGRAPHY
Fluvio, 2006. Geomorphological investigation of the River Aire at Kirkstall Forge,
Leeds. Report Prepared for Weetwood Environmental Engineering.
Hydrosurveys, 2004. Baseline fisheries survey of the River Aire, Kirkstall, Leeds.
Unpublished Report, Hydrosurveys, Kenilworth.
Knighton, D., 1998. Fluvial Forms and Processes: a new perspective. Arnold,
London
Meyer-Peter E, Muller R., 1948. Formulation for bed load transport.
Proceedings International Association for Hydraulic Research, 2nd Congress,
Stockholm; 3964.
Randle Siddeley Associates., 2007. Kirkstall Forge Bypass Channel. Drawing
number 675 SK03 REV C.
Wilcock, P. R., 2001. Towards a practical method for estimating sedimenttransport rates in gravel-bed rivers. Earth Surface Processes and Landforms. 26,
1395-1408. J Wiley.
Weetwood
37
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
APPENDICES
APPENDIX A:
ATTENDEES:
Representing CEG - Charles Johnson, Gareth Chambers, Granville Davies, Andrew
Grime
Representing the Environment Agency Gillian Turner & Robert Sanderson
(Development Control), Ian Thynne (Planning), Erica Adamson (Biodiversity), Neil
Trudgill and Pat OBrien (Fisheries), Karen Wooster (Water Resources)
NOTE OF MEETING:
1. PROPOSED FLOOD RELIEF CHANNEL
Drawing numbers 675_SK03 Rev B. 18.07.07, 675_SK04 Rev C. 06.08.07 and DVSK-011 Rev P2 formed the basis of the discussions although it was noted that the
additional rip rap shown on the last drawing was not yet fully included on the
landscape sketches. It was agreed in principle that the proposals tabled would
allow Clause 28 of the planning conditions to be discharged subject to the
following.
1.1
1.2
1.3
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
The rights of other riparian owners will need to be considered before such structures are removed
Weetwood
761R01/AG
30 October 2007
CEG
KIRKSTALL FORGE
APPENDIX B:
Node Label
Outline FRC
Design100yr
CC (mAOD)
FRC
Refined
100yr
CC
(mAOD)
02671700930F
40.487
40.492
S1:
Channel
0.033
Banks
0.055
100-yr
CC
(mAOD)
40.498
10
2671700920
40.473
40.478
40.484
40.478
40.49
39.944
39.949
36
2671700894
40.512
40.517
40.522
40.517
40.527
40.019
40.025
40.76
126
1700804
40.127
40.134
40.141
40.134
40.149
39.642
39.649
40.45
173
02671700757A
40.121
40.127
40.134
40.127
40.142
39.646
39.653
40.44
173
02671700757B
40.121
40.127
40.134
40.127
40.142
39.646
39.653
393
2671700537
39.622
39.632
39.642
39.632
39.654
39.189
39.2
40.07
580
1700350
39.234
39.247
39.262
39.248
39.278
38.832
38.847
39.81
630
1700300
38.98
38.995
39.012
38.996
39.032
38.631
38.648
39.63
680
1700250
38.774
38.797
38.822
38.798
38.849
38.416
38.44
39.58
730
1700200
38.278
38.293
38.31
38.294
38.328
37.939
37.989
39.33
754
02671700176C
38.7
38.736
38.775
38.738
38.818
38.368
38.403
39.83
754
02671700176D
38.449
38.452
38.456
38.452
38.46
38.146
38.148
38.58
864
2671700066
38.428
38.428
38.429
38.428
38.43
38.125
38.125
38.45
930
02671607120C
38.446
38.449
38.452
38.449
38.456
38.141
38.143
38.56
Chainage
From
Rein
Road
Weir (m)
S2:
Banks
0.045
0.07
100-yr
CC
(mAOD)
S3:
Entire
FRC
0.045
100-yr
CC
(mAOD)
Outline FRC
Design100yr
(mAOD)
FRC
Refined
100yr
(mAOD)
Minimum
Required
Bank
Top
Level
40.492
40.504
39.959
39.965
40.75
40.74
930
02671607120D
38.423
38.423
38.423
38.423
38.423
38.13
38.13
38.42
1007
2671607043
38.066
38.066
38.066
38.066
38.066
37.85
37.851
38.07
1124
2671606926
38.079
38.079
38.079
38.079
38.079
37.824
37.824
38.08
1281
2671606769
37.846
37.846
37.846
37.846
37.846
37.598
37.598
1564
2671606486
37.468
37.468
37.468
37.468
37.468
37.267
37.267
1754
2671606296
37.39
37.39
37.39
37.39
37.39
37.187
37.187
1899
2671606151
37.249
37.249
37.249
37.249
37.249
37.007
37.007
2045
2671606005
36.87
36.87
36.87
36.87
36.87
36.728
36.728
2143
2671605907
37.02
37.021
37.021
37.021
37.02
36.84
36.84
2148
02671605902E
37.033
37.033
37.033
37.033
37.033
36.849
36.849
2148
02671605902F
36.848
36.848
36.848
36.848
36.848
36.424
36.424
2169
2671605881
36.845
36.845
36.845
36.845
36.845
36.421
36.421
2284
2671605766
36.713
36.713
36.713
36.713
36.713
36.245
36.245
2438
2671605612
36.379
36.379
36.379
36.379
36.379
35.892
35.892
2542
2671605508
36.22
36.22
36.22
36.22
36.22
35.807
35.807
2588
Chainage
From
FRC
Entrance
(m)
0
02671605462C
36.207
Outline FRC
Design100yr
(mAOD)
FRC
Refined
100yr
(mAOD)
38.7
36.207
S3:
Entire
FRC
0.045
(mAOD)
38.818
BY_130
36.207
S2:
Banks
0.045
0.07
(mAOD)
38.738
35.805
Node Label
36.207
S1:
Channel
0.033
Banks
0.055
38.775
35.805
Outline FRC
Design100yr
CC (mAOD)
36.207
FRC
Refined
100yr
CC
(mAOD)
38.736
38.368
38.403
65
BY_065
38.57
38.577
38.599
38.578
38.622
38.256
38.262
130
BY_000
38.423
38.423
38.423
38.423
38.423
38.13
38.13
Weetwood
761R01/AG
30 October 2007