Operation Procedure
Page 1 of 7
Work Instruction
G1-7027 A/B
Revision no.
Prepared by
Effective date
Issue no.
DCC
Signature
Name Surname
Date
Guruh Iriyanto
12/05/2015
Reviewed by
Approved by
REVISION HISTORY
Revision : 00
Date :
Condensate Pump
Operation Procedure
Page 2 of 7
Rev.
Effective date
00
Revision : 00
Date :
Description of Revision
Initial Issue
Prepared
Reviewed
Approved
Condensate Pump
Operation Procedure
Page 3 of 7
ENGLISH
BAHASA INDONESIA
1.
UNIT
Utility
1.
UNIT
Utility
2.
SYSTEM
Turbine
2.
SISTIM
Turbin
3.
SAFETY
Ensure all permits are signed off
3.
KESELAMATAN
Pastikan semua
ijin
kerja
sudah
ditandatangani
Ensure
Operator
recommended PPE
is
wearing
4.
ENGLISH
Revision : 00
Date :
peralatan
instrument
dalam
kondisi baik
Pastikan Kondisi di sekitar equipment ter
bebas dari gangguan
Pastikan sealing valve sudah terbuka
Condensate Pump
Operation Procedure
Page 4 of 7
BAHASA INDONESIA
Ensure inlet and outlet valve of pump
opened
Ensure hot well level normal F1-7026
START CONDENSATE PUMP
indikasi
pada
display
bahwa
Revision : 00
Date :
Condensate Pump
Operation Procedure
Page 5 of 7
ENGLISH
BAHASA INDONESIA
Pastikan
pompa
running
dan
On
menyala
or temperature
BAHASA INDONESIA
ENGLISH
Revision : 00
Date :
lihat
Condensate Pump
Operation Procedure
Page 6 of 7
indikasi
pada
display
bahwa
Revision : 00
Date :
Condensate Pump
Operation Procedure
Page 7 of 7
Revision : 00
Date :