The OWNER, as represented by a duly authorized officer/manager, may order at any time,
in writing, additional work or alterations. All such work shall be evidenced by a Change
Order duly signed by the OWNER and shall be executed under the same conditions hereof
and of the Contract Documents. All Change Orders shall indicate the completion date of
the works covered thereby. No Change Order shall be valid and binding to the OWNER
without the signature of its duly authorized representative.
4.2
All extra or additional works done by order of the OWNER shall be valued at the rates and
prices set out by both parties for such works.
4.3
Any value of change orders agreed upon shall be considered as part of the Contract but
shall be invoiced separately as change orders.
2
The CONTRACTOR shall, upon OWNERs final acceptance of the works and prior to
issuance of final payment, obtain at its own expense a Guarantee Bond equivalent to Ten Percent
(10%) of the total contract price including all awarded additional amount to answer for faulty
and/or defective materials or workmanship for a period of one (1) year starting from the date of
final acceptance of the work.
The OWNER shall release the Performance Bond upon the submission by the
CONTRACTOR of the Guarantee Bond.
ARTICLE VIII WARRANTIES & RESPONSIBILITIES OF THE CONTRACTOR
0
In case of any defect in workmanship or materials which may become apparent in the
course of the construction, the CONTRACTOR, upon the request of the OWNER, shall at its
own expense, tear down and replace such portion of the work done and/or materials installed
that, as in the OWNERs reasonable opinion, are unsound or defective, or not in accordance with
plans and specifications, without prejudice to the provisions of sub-paragraph 11.4 of article
XI. However, the CONTRACTOR shall not be responsible for inherent defects of materials
supplied by the OWNER.
1
The CONTRACTOR hereby warrants that all the materials which it shall furnish and
supply under this Agreement are new, free from defects and shall fully comply in every respect
with the specifications, approved samples and other requirements of the contract plans and other
related contract documents. The CONTRACTOR shall make no substitution for materials
required to be furnished by it under this Agreement unless written approval is first obtained from
the OWNER.
2
3
The CONTRACTOR shall guarantee and maintain the stability of the CONTRACTORs
works, equipment and materials furnished under this Agreement, keep the same in good repair
and condition for a period of twelve (12) months after issuance of final acceptance of the work
by the OWNER. Defects appearing during this period or any damages resulting from such
defects shall be corrected without expense to the OWNER. If the CONTRACTOR fails to correct
or repair the defects within fifteen (15) days from receipt of written notice thereof from the
OWNER, the OWNER may have the work or repair done by another CONTRACTOR at the
expense of the CONTRACTOR, or alternatively confiscate the Guarantee Bond to answer for the
cost of the correction or repair.
4
The CONTRACTOR shall at all times furnish and maintain sufficient supply of tools,
materials, equipment and skilled and/or unskilled workmen at the jobsite. The CONTRACTOR
shall diligently supervise the construction until completion and it shall have on full-time, a
competent and licensed construction engineer who shall act as Project Supervisor. In addition,
the CONTRACTOR shall also employ competent foremen on full-time duty to supervise the
workmen under this Agreement. The OWNER reserve all the right to reject on reasonable
grounds any person employed by the CONTRACTOR in the construction work and the omission
of the OWNER to exercise such right shall not, in any way, relieve the CONTRACTOR from its
responsibility to fulfill its undertakings.
5
The CONTRACTOR shall coordinate with contractors of other trades who are also
working for the OWNER.
6
The CONTRACTOR shall be responsible for the storage and safekeeping of materials
supplied and duly turned-over to it by the OWNER. Any damages, losses, and pilferages of
these materials shall be for the account of the CONTRACTOR.
7
The CONTRACTOR shall hold the OWNER free and harmless against any claim for
losses, damages or injuries of whatever kind and nature that may be filed or claimed against the
OWNER, by any third person, firm or entity arising out of or in connection with the construction
undertaken by the CONTRACTOR under this Agreement.
4
8
The CONTRACTOR shall be responsible for maintaining the general cleanliness and
sanitation of the site including clearing and removal of debris during the entire contract period.
9
The CONTRACTOR shall at all times provide and maintain an air-conditioned temporary
office with water, light, telephone lines, toilet facilities and good conditioned office furniture
(such as tables, chairs, desks, plan rack, whiteboards) for the use of the staff/representatives of
both OWNER and CONTRACTOR.
10
All provisions with respect to warranties contained in Article X are cumulative and not
alternative, and are in addition to such warranties as may be provided by law or contained in the
other provisions of this Agreement.
11
The CONTRACTOR shall provide qualified personnel to ensure the quality of materials,
workmanship & equipment of a particular item of work.
12
The CONTRACTOR shall submit for approval by the OWNER a Safety, Security &
Sanitation plan to be implemented at the jobsite through its Safety Officer. The plan shall be
implemented during the entire duration of the Construction period.
13
The CONTRACTOR shall provide temporary power supply, to be used for the entire
duration of contracted works. Deposits and cost of metering including monthly electric billings
shall be paid by the CONTRACTOR.
14
Temporary water supply and facilities shall be provided by the CONTRACTOR and cost
of water consumption for the entire period of construction shall be shouldered by the
CONTRACTOR.
ARTICLE IX INSPECTION
The CONTRACTOR shall provide promptly all needed inspection and test which are
necessary in the course of the work and shall be carried out safely and immediately. All
inspections and tests shall be performed in such a manner so as not to delay the prosecution of
the work.
If the work done by the CONTRACTOR is fully completed and in accordance with this
Agreement, the OWNER shall within Thirty (30) days issue a written certificate of
acceptance thereof and the balance found to be due the CONTRACTOR shall become
payable, subject only to the claims under Article VII,and IX,.
10.2
10.3
IN WITNESS WHEREOF, the parties hereto have hereunto affixed their signatures to
this Agreement on this
______ day of _____________________, 2011, at
__________________________ Metro Manila, Philippines.
Owner
By:
By:
KENNETH T. GATCHALIAN
President & C.E.O.
___________________________
__________________________
AC KN OWLED GMENT
REPUBLIC OF THE PHILIPPINES )
) S. S.
BEFORE ME, a Notary Public for and in the _________________ on this ______ day of
__________________, 2008, personally appeared the following:
Name
Kenneth T. Gatchalian
Arch. Charina B. Javier
16752346
01-04-08/ Valenzuela
___________
_______________________
Known to me and to me known to be the same persons who executed the foregoing
instrument and they acknowledged to me that the same is their free and voluntary act and deed of
the companies they represent.
I FURTHER CERTIFY that this instrument consists of seven (7) pages duly signed by the
parties and their instrument witnesses on the left hand margin of every page and sealed with my
notarial seal.
WITNESS MY HAND AND SEAL on the date and place first above written.
NOTARY PUBLIC