Anda di halaman 1dari 10

Package-1 Correspondance (Initial Pile Load test P

DATE

EVENT

11-Dec-15 LOA
15-Dec-15 Shahwadi Casting Yard Handedover
Alignment UTM co-ordinate handed over to contractor
1-Jan-16
with joint survey
9-Jan-16 Test Pile drawings issued
13-Jan-16 Submission of Concrete Mix Design
13-Jan-16 Submission of BBS for test pile
16-Jan-16 Submission of Vendor/Supplier of ATPL
18-Jan-16 Submission of MS-for 1200mm Cast-in-situ Bored Pile
19-Jan-16 Approval of Agency for testing and peroidical examinations
of lifting appliances and gears

22-Jan-16 Submission of Project HSE Plan


28-Jan-16 Submission of Polymer
29-Jan-16 Submission of Traffic Diversion Plan
30-Jan-16 Submission of Revised PQP
30-Jan-16 Approval of Concrete Mix Design
1-Feb-16 Submission of Vendor - Cover Blocks
2-Feb-16 Barrication Shifting on Site
3-Feb-16 Approval of Cover Block
3-Feb-16 Approval of Polymer
9-Feb-16 Approval of MS-for 1200mm Cast-in-situ Bored Pile
9-Feb-16 Approval of QAP
11-Feb-16 Intimation to AMC for removal of median (Test pile Location)
15-Feb-16
15-Feb-16
16-Feb-16
17-Feb-16

3rd Party Audit report of Hydraulic Rig


Approval of Reinforcement Steel
Approval of BBS
Approval of Inhibitor Solution and Cover Block

18-Feb-16 Casting of Pile For Vertical Load Test


19-Feb-16 Disposal of Excavated Earth-Vertical Load Test Pile
19-Feb-16 Approval of Binding Wire
20-Feb-16 Casting of Pile For Horizontal Load Test
21-Feb-16 Disposal of Excavated Earth-Horizontal Load Test Pile

21-Feb-16 First reaction Pile


22-Feb-16 Disposal of Excavated Earth-First Reaction Pile
23-Feb-16 Approval of Inhibitor Solution
27-Feb-16 Second Reaction Pile
28-Feb-16 Disposal of Excavated Earth-Second Reaction Pile

nitial Pile Load test P60)


DETAILS
Awarded to IL&FS
M-35 Ultratech
Admixture, Polymer and Curing Compound
(Eco Drilling Fluid) Bulck Density 50-55
lb/ft3
M35 Grade (Subected to Permeability Test
Report)
Easy Brand Cover Block 75mm
Total 96 nos.
Third Party Approval-Easy Brand Cover
Block 75mm (M35 Grade)
(Eco Drilling Fluid) Bulck Density 50-55
lb/ft3
M & M Engineers
SAIL-Fe500D
Site Approval by GEC
Site Approval by GEC
Pile Dia-1.2m, Pile Depth-29m, Concrete
Qty-34m3, & Steel-1.59T.
GI Binding Wire
Pile Dia-1.2m, Pile Depth-29m, Concrete
Qty-35m3, & Steel-3.25T.
-

Pile Dia-1.5m, Pile Depth-33m, Concrete


Qty-58m3, & Steel-7.74T.
Third Party Approval-ATPL
Pile Dia-1.5m, Pile Depth-33m, Concrete
Qty-58m3, & Steel-7.74T.
-

Package-1 Correspondance (Initial Pile Load test P43)


DATE

EVENT
Test Pile drawings issued
Submission of BBS for test pile
Submission of HSE Plan
Submission of Traffic Diversion Plan
Barrication Shifting on Site
Removal of Kerb Stone
Removal of Street Light Pole
3rd Party Audit report of Hydraulic Rig
Approval of BBS
Trail Trench
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of Pile For Vertical Load Test
Disposal of Excavated Earth-Vertical Load Test Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of Pile For Horizontal Load Test
Disposal of Excavated Earth-Vertical Load Test Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of 1st Reaction Pile
Disposal of Excavated Earth-Vertical Load Test Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of 2nd Reaction Pile

Disposal of Excavated Earth-Vertical Load Test Pile

al Pile Load test P43)


DETAILS

Dumping SiteNos.Stacking SiteM & M Engineers

Pile Dia-1.2m, Pile Depth-29m,


Concrete Qty-34m3, & Steel1.59T.
-

Pile Dia-1.2m, Pile Depth-29m,


Concrete Qty-34m3, & Steel1.59T.
-

Pile Dia-1.2m, Pile Depth-29m,


Concrete Qty-34m3, & Steel1.59T.
-

Pile Dia-1.2m, Pile Depth-29m,


Concrete Qty-34m3, & Steel1.59T.

Package-1 Correspondance (Initial Pile Load test P13)


DATE

EVENT
Test Pile drawings issued
Submission of BBS for test pile
Submission of HSE Plan
Submission of Traffic Diversion Plan
Barrication Shifting on Site
Removal of Kerb Stone
Removal of Street Light Pole
3rd Party Audit report of Hydraulic Rig
Approval of BBS
Trail Trench
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of Pile For Vertical Load Test
Disposal of Excavated Earth-Vertical Load Test
Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of Pile For Horizontal Load Test
Disposal of Excavated Earth-Vertical Load Test
Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of 1st Reaction Pile
Disposal of Excavated Earth-Vertical Load Test
Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of 2nd Reaction Pile
Disposal of Excavated Earth-Vertical Load Test
Pile

nitial Pile Load test P13)


DETAILS

Dumping SiteNos.Stacking SiteM & M Engineers

Pile Dia-1.2m, Pile Depth-29m,


Concrete Qty-34m3, & Steel1.59T.
-

Pile Dia-1.2m, Pile Depth-29m,


Concrete Qty-34m3, & Steel1.59T.
-

Pile Dia-1.2m, Pile Depth-29m,


Concrete Qty-34m3, & Steel1.59T.
-

Pile Dia-1.2m, Pile Depth-29m,


Concrete Qty-34m3, & Steel1.59T.
-