DATE
EVENT
11-Dec-15 LOA
15-Dec-15 Shahwadi Casting Yard Handedover
Alignment UTM co-ordinate handed over to contractor
1-Jan-16
with joint survey
9-Jan-16 Test Pile drawings issued
13-Jan-16 Submission of Concrete Mix Design
13-Jan-16 Submission of BBS for test pile
16-Jan-16 Submission of Vendor/Supplier of ATPL
18-Jan-16 Submission of MS-for 1200mm Cast-in-situ Bored Pile
19-Jan-16 Approval of Agency for testing and peroidical examinations
of lifting appliances and gears
EVENT
Test Pile drawings issued
Submission of BBS for test pile
Submission of HSE Plan
Submission of Traffic Diversion Plan
Barrication Shifting on Site
Removal of Kerb Stone
Removal of Street Light Pole
3rd Party Audit report of Hydraulic Rig
Approval of BBS
Trail Trench
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of Pile For Vertical Load Test
Disposal of Excavated Earth-Vertical Load Test Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of Pile For Horizontal Load Test
Disposal of Excavated Earth-Vertical Load Test Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of 1st Reaction Pile
Disposal of Excavated Earth-Vertical Load Test Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of 2nd Reaction Pile
EVENT
Test Pile drawings issued
Submission of BBS for test pile
Submission of HSE Plan
Submission of Traffic Diversion Plan
Barrication Shifting on Site
Removal of Kerb Stone
Removal of Street Light Pole
3rd Party Audit report of Hydraulic Rig
Approval of BBS
Trail Trench
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of Pile For Vertical Load Test
Disposal of Excavated Earth-Vertical Load Test
Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of Pile For Horizontal Load Test
Disposal of Excavated Earth-Vertical Load Test
Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of 1st Reaction Pile
Disposal of Excavated Earth-Vertical Load Test
Pile
Lowering of temporary lining
Boring of Pile
Lowering of Reinforcement Cage
Casting of 2nd Reaction Pile
Disposal of Excavated Earth-Vertical Load Test
Pile