WASA's requirements

Wastewater Treatment Plant General Design Checklist


No.
1

Requirements for Submission

Item
General Requirements

Four copies of designs submitted


Plan showing set back distances, proposed WWTP, security measures etc. provided
Submitted WWTP designs reflects Outline approval
North arrow shown on map
Point of discharge indicated
2

Flow Requirements
Type of Development
Occupancy Figure
Area of Development (ha)

Pre Treatment Units


Plan and Sectional Drawings of Screening Mechanism and Grit Chamber provided
Calculations for Design of Screening Mechanism and Grit Chamber provided
Calculations shall include the following:
a. Clear spacing for screens (mm)
b. Screen dimensions
c. Detention Time for Grit Chamber
d. Horizontal Velocity for Grit Chamber
e. Settling Velocity for Grit Chamber
f. Volume of Grit Chamber

Primary Treatment
Plan and Sectional Drawing of Pre-treatment tanks and/or Primary Clarifiers
Calculations for Pre-Treatment tanks and/or Primary Clarifiers provided
Calculations shall include the following:
a. Retention Time for Tanks
b. Tank dimensions and volume
c. Water Velocity in Clarifier
d. Skimmer Scraper Power in Clarifier

wssm ltd - 2016

WASA's requirements
Wastewater Treatment Plant General Design Checklist
No.
5

Requirements for Submission

Item
Secondary Treatment

Plan and Sectional Drawings of Aeration tank


Calculations for Aeration tank provided
Calculations shall include the following:
a. Reactor Volume
b. Mean Cell Residence Time
c. Mixed Liquor SS Solids
d. Retention Time
e. Food/Mass Ratio
Note: the same details for calculation for a different type of reactor would apply
Calculations Showing Oxygen Requirement for Aeration Tank provided
Calculations must include the following:
a. Oxygen Requirement (Kg Gzld)
b. Efficiency of Equipment ()
c. Air required for mixing (Specifications for blower/aerator required)
Lifting devices provided for removal of aerators (details required)
6

Secondary Clarifier
Plan and Sectional Drawings of Clarifier
Calculations must include the following:
a. Tank dimensions and volume
b. Recycle Ratio
c. Solids Loading Rate
d. Overflow Rate
e. Weir loading Rate
f. Retention Time

wssm ltd - 2016

WASA's requirements
Wastewater Treatment Plant General Design Checklist
No.
7

Item

Requirements for Submission

Sludge Handling
Plan and Sectional Drawings of Sludge Handling Mechanism
Calculations for Sludge Handling Mechanism
E.g. Aerobic Digester, calculations must include:
a. Volume of Sludge
b. Volume of Digester
c. Air Requirements and associated specs.
d. Retention Time
E.g. Sludge Drying Bed, calculations must include
a. Volume of Wet Sludge
b. Mass of Secondary Solids
c. Dimensions and number of Sludge Beds
d. Drainage and media provided (details required)

Disinfection
Disinfection methodology/Type of disinfection proposed
No. of units to be used and order of use - must state the following
a. Minimum/Maximum Flow rate to be treated by each UVlChlorination System
b. Effluent levels that are expected with the system proposed

wssm ltd - 2016

WASA's requirements
Wastewater Treatment Plant General Design Checklist
No.
9

Requirements for Submission

Item
Other

The following must be included in the WWTP submission


a. Flow Monitoring Mechanism for Large WWTP (weirs, meters) and their specs
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.

Generator (for Large WWTP) provided. Auxillary storage fuel, noise control, measures, plinth, housing, vent,
unit specifications provided
Operations and Maintenance Plan (for Large WWTP) provided
Sampling points on the influent and effluent of the WWTP provided
Setback distances should be a minimum of 25 m and l.5m from property and habitable buildings for Large
WWTPs and Small WWTPs respectively.
Independent bypass along system provided
Certification for pre fabricated WWTP form a Reputable Organisation, specs. provided
Pipe sizes, length, type and classes to be used in the WWTP provided
Piping properly secured. Aboveground PVC pipework to be laid below ground, encased or be replaced by steel
type
Valves used within WWTP suitable for use in wastewater environments, specs req'd
WWTP located downwind of habitats & downstream of water treatment plant
Adequte security lighting, fencing, signage and accessway provided
Potable water (hose bib), water storage (90 lpm at 30 m pressure) and pump provided

n. Grounds must be properly paved and have proper surface drainage, vehicular and service access to WWTP
o. Operators building with storage for equipment, water closet, face basin and shower peovided
p. Aritectural & structural plans and sections of Operatior's building provided
q. Apron provided aroundOperator's Building
r.

For packaged plants influent & effuent empirical data on parameters (BODS, TSS, pH, etc)., based on prior use
of the system is required'

s. For package plants, the treatment capacities ofthe process units in terms of BOD, COD, etc. is required