Abstract
Novel well completion techniques and exceptional field
execution allowed the six well completions on the Anadarko
operated Marco Polo Deepwater TLP project in Green Canyon
608 to be accomplished in world-class fashion. All six wells
(seventeen frac packs) were placed on production in only 168
days, including 14 days lost due to storms, after riser tie-back
operations were complete. An operational efficiency of 85%,
with weather downtime accounting for 9% and other lost time
accounting for 6%, was obtained during the completion
campaign.
This paper will focus on how the implementation
challenges of completing seventeen zones in six deepwater
dry-tree wells with a 1000 hp rig were met, and will highlight
a number of concepts and technical firsts that can be applied to
other deepwater development projects.
Background
Anadarkos Marco Polo deepwater development project is
located in Green Canyon Block 608 in the Gulf of Mexico,
approximately 175 miles south of New Orleans, in a 4300
water depth environment.
Field Development
The Marco Polo Field was discovered in 2000, and the project
was sanctioned for development in 2001. Six development
wells were drilled in 2002 and 2003, and were temporarily
abandoned to await completion after installation of the TLP in
2004 (Refer to Figure 1, Marco Polo TLP). The TLP hull and
deck were installed in January 2004, and were designed to
accommodate a 1000-hp completion rig to run riser tiebacks
and perform completions. Only 88 persons are allowed on the
platform at a time (maximum POB) due to USCG rules, a
significant issue for rig operations.
Geological
The Green Canyon Block 608 (Marco Polo) field is located in
the southern portion of the Marco Polo salt withdrawal minibasin. The depositional model for the field is a restricted
basin floor amalgamated sheet fan sand. Moderate to strong
aquifer support was expected, although the potential presence
of internal baffles and barriers introduce uncertainty to the
extent of the aquifer support.
The trap geometry was created by salt withdrawal and
extensional faulting due to sediment loading on the eastern
side of the salt ridge. The primary trap consists of a fault
bounded graben dipping away from the salt ridge. The main
faults are west-southwest to east-northeast trending faults that
form the graben. The updip trap component to the west is salt
and/or sand punch-out. The graben is further subdivided into
separate compartments by additional faulting. Refer to Figure
2, Marco Polo M10 Sand Structure Map.
Two main fault compartments make up the Marco Polo
field. Another graben fault, downthrown to the north west and
trending in the same direction as the bounding faults,
subdivides the graben into these two main compartments,
designated as Fault Block I and Fault Block II. The two main
compartments are further subdivided into two additional
compartments by faults that are trending northwest to
southeast and downthrown to the west (towards salt). The
four main producing compartments for the Marco Polo field
are designated FB IA, FB IB, FB IIA and FB IIB (Updip
compartments are denoted A).
The productive horizons at the Marco Polo Field consist
of seven stacked Lower Pliocene sandstone reservoirs; the
M10, M20, M30, M40, M50, M60, and M70; 75% of the
reserves are concentrated in the M40 and M50 Sands.
Reservoir depths range from 11000 to 13500 tvd-ss. Refer to
Figure 3, Marco Polo Type Log.
A complete open hole logging suite was obtained on all
discovery and development wells. Continuous whole core was
obtained through both the M-40 and M-50 intervals in the GC
608 #1 ST#1 wellbore.
Reservoir
Initial reservoir pressures range from 6700 to 7600 psi.
Reservoir temperatures range from 115 to 122 oF. Ambient
mudline temperature is 38 oF at 4300 water depth. Reservoir
fluids are undersaturated black oils, with API gravities ranging
from 30-34 and GORs ranging from 700 to 1000 scf/stb.
During the exploratory and development drilling phases,
reservoir pressures were measured on nearly all productive
intervals in all wells, and reservoir fluid samples were
SPE 95331
SPE 95331
SPE 95331
Wellbore Displacement
All wells were successfully cleaned out and indirectly
displaced to calcium chloride/bromide completion fluid in one
trip. All had been temporarily abandoned after drilling with
water based mud to TD and a surface cement plug.
Non-rotating brushes and scrapers were used with various
downhole combinations of bits, mills and drill collars to drill
the surface plug and wash settled barite. The optimal
toolstring was a standard rock bit and 6-1/2 drill collars.
Bentonite gel sweeps were used while pumping at 10-12 bpm
and rotating the drill string with the kelly at +70 rpm to
achieve efficient mud and cement cleanout from the wellbore.
Once the wellbore was washed out to PBTD and displaced to
treated salt water (TSW; treated with oxygen scavenger),
chemical sweeps were pumped, a short trip made to the upper
scraper/brush (generally four were spaced out in the string),
and the well displaced again with TSW followed by calcium
chloride/bromide completion fluid.
The brush scraper system employed was of a robust
design, which allowed continuous rotation and not cause
casing damage or component failure. The internal diameter of
the tools would allow the passage of electric line severing or
cutting tools to the end of the workstring, should an
unforeseen event occur.
All wells used calcium bromide-calcium chloride (CaBr2CaCl2) blend with a density of between 11.7 and 12.6 ppg, and
contained 0.5% of a non-ionic surfactant to reduce emulsion
potential. Target true crystallization temperature (TCT) was
below 20 oF, and pressure crystallization temperature (PCT)
was below 32 oF at 10,000 psi. All completion fluids and
reservoir fluids were tested for compatibility in the laboratory
prior to completion operations, and confirmed after first
production.
Perforating Strategy
The Marco Polo perforating strategy achieved a balance
between operational efficiency and perforation performance
by perforating all individual zones overbalanced. A 6-1/2
gun (with integral tandem centralizers; collapse rating of
12,000 psi) with 14 shot per foot, big hole charges using
sintered zinc casing and liners was used. The firing system
employed redundant pressure delay firing heads to eliminate
drop bar retrieval issues. The firing heads were both placed at
the top of the gun to keep the distance from the bottom shot to
the sump packer to a minimum. This reduced the probability
of the packer plug-running tool damaging the packer plug
when the guns fired, or having a void in the bottom of the frac
pack due to a longer interval from the bottom shot to the sump
packer.
Intervals to be perforated ranged from 21 to 170
measured depth in length, and from 19 to 35 degree deviation.
In all cases the top 5 foot of reservoir quality sand was not
perforated to assist in frac pack containment. A packer plug
was used to isolate and prevent debris from falling into the
prior completed interval when perforating the upper zone(s)
in a well.
Overbalanced perforating minimizes the risk of gun
sanding, minimizes risks with packer plug retrieval, has lower
operational cost, reduces the probability of hydrate formation,
and has been documented to not reduce frac pack
SPE 95331
SPE 95331
SPE 95331
the tubing string and land the tubing hanger without damaging
any components.
All wells utilized 4-1/2 13Cr85 12.75# production tubing
with a proven two-step, low makeup torque thread. Range
two length joints were used between the production seal
assembly and the packoff tubing hanger (POTH) set below the
mudline.
The 4-1/2 tubing above the POTH was controlled length
(all joints of the same length, +/-0.025), and were internally
coated with a phenolic compound which can reduce tubing
friction and potentially reduce paraffin deposition
The gas lift string tubing used above the pack off tubing
hanger (POTH) is 1.9 L-80 2.9# with the same two-step
thread, and is also virtually the same controlled length as the
4-1/2 tubing. The dual tubing strings were installed using
only a single 4-1/2 elevator. The 1.9 tubing was clamped to
the 4-1/2 tubing mid-joint using a non-metallic bolt fastened
centralizer which kept the production tubing from contacting
the riser casing wall. Short one and two foot pups were
installed in the 1.9 string to keep the two strings at a
convenient height while running in hole.
All tubing and tubing accessories arrived at the rig in as
run condition with respect to thread compound (no cleaning
required). Accessories were preassembled with handling
pups.
Following the final frac pack and pressure testing of
sliding sleeves in a given well, the well was displaced with
corrosion inhibitor treated packer fluid. On the trip out of the
hole, all drill pipe from 200 below the mud line was laid
down in order to provide room on the limited drill floor and to
allow setting of the storm packer on drill pipe should a rig
evacuation during tubing installation be required.
Rig Preparations
The rig preparations to run tubing included modifications to
the bell nipple (upper section removed and replaced with
funnel to obtain spider deck access), installation of the control
line manipulator, changing one set of pipe rams to dual rams
(and testing), and placement of material and equipment on the
pipe rack.
Only two control line spooling units were required, and
were located on the piperack. A novel split drum held the
upper (three component) and lower (two component) sections
of Flatpack A (containing the encapsulated Fiber Optic cable,
lower CIM control line and POTH control line), reducing
equipment and personnel requirements. The other unit held
the three component Flatpack B, which consists of SCSSV
and upper CIM control lines. Refer to Figure 10, Flatpack
Layout.
Control lines were installed on the spider deck of the rig,
which is 138 below the drill floor. Cameras, radio and
intercom were used to prevent miscommunication between the
driller and the installation crew. A hydraulically operated
traveling sheave assembly placed the control lines on the
tubing wall. This arrangement proved to be effective on this
installation due to the limited space on the rig floor by
separating the tubing make up and clamp installation
operations.
SPE 95331
SPE 95331
10
the tubing hanger and tubing hanger running tool had not
entered the bell nipple and could be monitored.
The entire tubing assembly was then rotated to align for
tubing hanger landing. This was consistently accomplished
for all 6 wells by hand from the drill floor with right hand
rotation. Four different orientations were required for the
landing of the tubing hanger due to TLP design.
At this point the BOP stack tensioners was adjusted to
center the tubing hanger as much as possible. The spider was
also removed to give more freedom of movement as the
hanger traveled past the BOP stack, minimizing potential seal
damage.
The SCSSV line was then re-attached and the SCSSV
opened, the stack drained, and the tubing hanger landed with
visual confirmation via the casing valve. After testing the
hanger void and backside, the running tool was retrieved and a
backpressure valve installed in the 4-1/2 tubing.
Well Commissioning
After the tubing was installed and hanger landed, adjacent
wells were shut-in (if producing) and the rig was skidded at
least two slots. This allowed crane access to the well slot just
completed. The control lines were then terminated in the
tubing head outlet valves and the fiber optic fusion splice
performed while BOP nipple up operations were underway on
the next well to be completed.
All remaining completion operations were not on the
critical path, saving four to six rig days per well completion.
The tree was installed by the platform crane. Methods
were employed to assist in alignment and to mitigate
TLP/crane motion. After the tree was tested, the back
pressure valves were removed. The pre-installed flowlines
and umbilical were then connected and tested.
The SCSSV was then function tested and opened from
the tree outlet. The downhole fiber optic gauges were also
connected, tested and monitored. A three way manifold was
then rigged up to the tubing, gas lift wing, and casing valve.
The tree instrumentation lines, which had been pre-fitted to
the individual tree and platforms, were then installed and
tested with a separate crew.
At this point the completion fluid in the inner riser by
tubing annulus above the POTH was displaced to treated
seawater down the casing valve, taking returns up the gas lift
line. The circulation path was then changed and the riser
annulus circulated with additional treated seawater to insure
all traces of calcium bromide were removed from the well.
This pumping was performed by a third pumping unit while
the next completion was being displaced with treated sea
water using the two main rig pumps.
The 9.0 ppg gelled insulating fluid12, which was brought
on board out of the critical path and stored in the reserve
completion fluid tanks, was circulated in place in the same
direction. The POTH was then control line set while
monitoring the volume of fluid pumped and pressure tested
(first from above and then from below). The pressure was
then increased to shear a dump-kill valve installed in the GLM
directly above the SCSSV. The completion fluid below the
POTH and above the SCSSV was then displaced with a
hydrate-proof 8.7 ppg fluid. This was a new composition13
designed to underbalance the well for flowback
SPE 95331
2.
3.
SPE 95331
4.
5.
6 .
7.
8.
9.
10.
11.
12.
13.
Figure 1
Marco Polo TLP
11
Figure 2
Marco Polo M-10 Sand Structure Map
Figure 3
Marco Polo Type Log
12
Figure 4
Marco Polo Generalized Wellbore Schematic
SPE 95331
SPE 95331
13
Figure 5
Marco Polo Completion Operations Timeline
Figure 6
Marco Polo Completions Operational Effiency
Weather
Planned
Unplanned
139 days
(85%)
24 days
(15%)
14 days
(9%)
Unavoidable
6 days (4%)
Avoidable
4 days (2%)
14
SPE 95331
Figure 7
Marco Polo Mudline and Surface Wellhead Locations
Figure 9
Flatpack Layout
Slot/Keel Location
Mudline (Sub Surface) Wellhead Location
Figure 8
POTH Schematic
Table 1
Marco Polo Reservoir Fluid Properties
Property
GOR (SCF/STB)
API
Reservoir Temperature
(deg. F)
Initial Reservoir Pressure
(psia)
Bubble-Point Pressure
(psia)
CO2 Reservoir Fluid
Mole %
M10
1209
29.7
M40
1156
33.5
M50
742
31.7
M60
745
31.4
115
119
121
122
7087
7368
7433
7477
5596
4188
2771
3154
0.06
0.21
0.20
0.24
Table 2
Marco Polo Initial Well Productivity
Well
A-3
A-4
A-5
A-6
A-7
A-8
Initial Rate
7,000 BOPD
3,500 BOPD
9,000 BOPD
11,500 BOPD
11,000 BOPD
12,000 BOPD
Drawdown
281 psi
100 psi
201 psi
251 psi
277 psi
249 psi
PI (bbl/d/psi)
24.9
35.0
44.8
45.8
39.7
48.1
Skin
-2.1
-2.3
-2.7
0.1
-2.8
1.1
SPE 95331
15
Table 3
Marco Polo Perforating Data Summary
Well
#
A-5
A-6
A-4
A-3
A-8
A-7
Sand
M-50
M-40
M-60
M-50
M-40
M-60
M-50
M-40
M-70
M-50
M-40
M-60
M-50
M-40
M-40
M-20
M-10
Mid
Perf
(MD)
12,354
12,215
12,993
12,765
12,530
12,470
12,357
12,230
12,192
11,738
11,630
11,935
11,788
11,641
12,540
12,234
11,960
Hole
Angle
@
Perfs
23
22
31
30
30
19
19
19
35
34
34
32
32
31
27
26
27
Gross
Perfs
92
50
35
170
60
21
83
40
28
64
40
30
105
49
80
60
64
BHP
(psi)
7,397
7,335
7,501
7,459
7,368
7,358
7,326
7,368
7,381
6,943
6,877
7,235
7,224
7,190
6,900
7,336
6,872
Temp
(deg F)
117
115
121
117
115
121
116
113
118
113
112
120
116
111
123
112
113
OB*
(psi)
578
523
508
364
368
430
483
450
280
425
465
347
267
237
1,064
477
700
Operation
On Bottom
Pickle
Mini Frac
SRT
Frac
Boat
74
79
79
79
79
@ Mudline
(4,344 ft)
Begin End
43
43
45
51
51
73
67
71
63
79
@ XO tool
(12, 146 ft)
Begin End
118
119
117
111
111
103
97
99
100
89
Table 5
Marco Polo Total Sand Control Installation Days
A-5
A-8
A-7
Total
9.9
12.6
75.1
17
4.9
6.0
4.1
3.6
3.8
4.2
4.4
16
SPE 95331
Table 6
Marco Polo Frac Pack Summary
Well
#
A-5
A-6
A-4
A-3
A-8
A-7
Sand
M-50
M-40
M-60
M-50
M-40
M-60
M-50
M-40
M-70
M-50
M-40
M-60
M-50
M-40
M-40
M-20
Closure
psi
8,545
8,441
9,069
9,100
8,752
8,400
8,518
8,384
8,161
7,886
8,091
NA
8,377
8,067
8,433
8,348
Fluid
Efficiency
21%
15%
17%
14%
10%
46%
30%
20%
51%
14%
27%
NA
15%
19%
35%
14%
%Pad
13%
31%
30%
37%
56%
14%
17%
27%
19%
38%
25%
34%
40%
27%
13%
24%
bpm
15
18
15
25
18
15
15
15
15
15
15
15
15
12
12
15
Net
psi
428
996
552
221
302
461
328
134
294
465
602
286
214
938
146
0
lbs/ft(md)
Behind
Pipe
465
1,057
895
362
464
3,022
1,228
2,636
2,141
504
1,927
1,017
563
820
828
1,233