Seat No.-23
Section H
15BSPHH010540
LEAN Methodology in
Textile Industry
ABSTRACT
Lean Manufacturing is a technique originally developed in the automotive
industry that concentrates on shortening the time between the customers
order and shipment. Lean manufacturing has been applied very
successfully in manufacturing operations, resulting in shorter production
lead times, greatly reduced inventories, and significantly enhanced
profitability. These techniques also promote improved flexibility, enhanced
reliability and substantial cost reductions [1-4]. This work addresses the
implementation of lean philosophy in a textile machinery manufacturer,
with a focus on elimination of process bottle necks and optimizing the
process layout. Value stream mapping was the main tool used to identify
the opportunities for various lean techniques. The primary motive is to
evolve and test several strategies in the elimination of bottle necks on the
shop floor by the incorporation of a layout modification and a versatile
automation strategy. Simulation models are built for the inherent
processes and the denouements of such changes modeled and analyzed.
The effects of lean and the value addition by automation are clearly
demonstrated by the simulation. A noticeable reduction in lead time and
work-in-process inventory level is achieved.
Problem environment
3.1 Profile of the company
The company, ABC Limited is a leading textile machinery
manufacturer in India which produces a range of spinning
machinery. In 1962, the company was founded to provide the Indian
Sl. No.
Time
1.
30 min
2.
2.6 min
3.
25 min
4.
2 min
5.
1.6 min
6.
1.8 min
7.
3.1 min
Description
Paddle polishing batch processing
Paddle welding
Annealing batch processing Grinding
Perpendicular bending
Radius bending
Regrinding and radius checking
After several brain storming and a thorough study of the shop floor,
it was observed that manufacturing operations sequence consists
various forms of non-value-adding activities as follows:
Back-tracking of parts from grinding station to bending
station - increased transportation distance and time
value-added time are noted on the current state map. It provides the
snapshot in time. Inventory storage points in between the stages are
shown in triangles. The timeline at the bottom of the current state
map has two components. The first component is the production
lead time and second component is value-added time or processing
time.
Value-added time is calculated by adding the processing time for
each process in the value stream. The cycle time for each is the
average cycle time, which is determined by using actual data from
the company.
This current state map provides a picture of existing positions
and guide about the gap areas. It helps to visualise how things
would work when some improvements are incorporated. The gap
area in the existing state results in a road map for improvement. Fig.
4 shows the current state map.
Existing layout
New layout
Work-space utilisation
Work-space is an imaginary area occupied by a machine wherein the
distance between successive machines is always greater than four
feet . The term work-space includes the space occupied by every
machine plus some of the free space on either side of a machine
(Table 2). The redesigned layout requires annealing to be included in
cell 1 in place of perpendicular bending and the latter should be
shifted to cell 2. Further, from Table 2, it is observed that both the
cells occupy the same area and that; cell 2 has lesser free space
than cell 1. Hence, there is some scope for improvement which leads
to a
corresponding increase in free space in cell 2.
Table 2 Summary of work-space utilisation
MACHINE
WORK SPACE
Cell 1
Cell 2
Annealing
11x7feet
Grinding machine
6x4 feet
Bending (bending to required shape) machine
8x6 feet
Regrinding and radius checking
12x6
Total area of cell 2
40x20
Free space in cell 2
less than
10 feet( measured from radius checking machine till the
end of cell 2)
Observations led to a conclusion that both annealing and
perpendicular bending occupied approximately the same space and
it is viable that the former can be replaced by the latter considering
the fact that there is 15 feet of free space after accommodating the
perpendicular bending machine. But in the re-designed Layout, this
free space would decrease to 12 feet which is still within the
acceptable limits. Fig. 7 shows the work space of machines in the redesigned layout and a conspicuous increase in free space in cell 2
with a corresponding decrease in free space in cell 1. Also, with
annealing now being shifted to cell 1, it provides considerable
leeway which is a pre-requisite, given the nature of the process.
Conclusions