CHAPTER
A I R P O RT D EV E L O P M E N T
PROGRAM
Airport Development
Program
4.1
4 . 1 O V E RV IE W
At the end of 1996, the Greater
Toronto Airports Authority
(GTAA) assumed responsibility
for Toronto Pearson International
Airport. At that time the Airport
had an estimated airside, terminal
and groundside capacity of
28 million passengers annually.
Passenger volumes at that point
had reached 24 million passengers
per year and were growing at
approximately one million passengers annually, making the need
for system expansion urgent, particularly given the long lead times
involved in planning, constructing,
and activating new facilities. At
the same time, much of the
existing terminal capacity was
obsolete and in need of replacement or refurbishment.
In 1995, the GTAA Board of
Directors was faced with two
distinct options to address the
Airports future facility needs
required to meet projected
demand. They could continue
with the incremental approach to
airport expansion by infilling
available real estate and maximizing the residual capacity of
existing facilities, or they could
undertake a total redevelopment of
the Airport, thereby optimizing
the facilitys full development
Chapter 4 > A I R P O RT D E V E L O P M E N T P R O G R A M
4.2
New Terminal 1
Chapter 4 > A I R P O RT D E V E L O P M E N T P R O G R A M
4.3
practical annual capacity of
approximately 50 million
passengers per year).
The first new east/west parallel
runway was located on the south
side of the airport lands. Construction began in 1998 and Runway 06R-24L was operational by
the fall of 2002.
The final phase of airside development includes the construction of
a closely-spaced east/west runway
on the north side of the airport
lands, which will be the sixth and
final runway in the ultimate airside system. The demand requirements for this final runway are
expected to occur within the
2013-2019 time period.
4 . 3 TE RMINAL
D EV E LOP ME NT P ROJE C T
At the time the GTAA assumed
responsibility for the Airport, a
number of concepts had been
proposed for expanding terminal
capacity. Careful review of these
plans by the GTAA revealed that
none could be relied upon to provide adequate capacity to match
the full potential of the airside
system. What is more, all of these
plans left in place certain serious
weaknesses of the then terminal
layout, namely a convoluted and
counterintuitive access roadway
system and one of the smallest
aircraft aprons for an airport of
comparable activity in North
America.
In order to ensure that the full
potential of Toronto Pearson
Chapter 4 > A I R P O RT D E V E L O P M E N T P R O G R A M
Pier F Construction
4.4
accommodate primarily domestic
and transborder traffic, they were
initially dedicated to domestic and
international traffic when opened
in April 2004. This capacity, supplemented by another 11 gates
made available from a passenger
hold room facility located in the
Infield area, permitted old
Terminal 1 to be vacated
and demolished.
Once old Terminal 1 was removed,
it was possible to complete more
gate positions on Pier E and the
central processor such that in
October 2005 an additional 10
bridged gates were opened in the
new terminal and reliance on the
Infield Terminal was thereby
significantly reduced. Removal of
old Terminal 1 also freed up space
for construction of Pier F.
Pier F Hammerhead
Pier F Interior
Chapter 4 > A I R P O RT D E V E L O P M E N T P R O G R A M
4.5
adequate new terminal capacity
available for the first time to
accommodate expected future
demand over the next five years.
Demolition of Terminal 2 will
now free up space for the continued expansion of the new
terminal complex in future years
as demand warrants. The final
elements of terminal expansion
will include construction of up to
three additional piers bringing the
total gate count to 86, in addition
to parking positions for commuter
aircraft and off-gate groundloaded aircraft. These last stages of
airport development are expected
to be complete before the
planning horizon of 2030.
Ineld Development
4 . 4 I N F IE L D DE V E LO P ME NT
P R OJE C T
The Infield site lies between the
parallel north-south runways and
encompasses 143 ha (352 acres).
The need for the Infield Development Project arose as a result of
growth in cargo demand and displacement of the former air cargo
area by the new terminal, as well
as an expansion of Pier C on
Terminal 3. The Infield
Development Project was designed
to meet the current and future
requirements of the tenants
displaced by the Terminal and
Airside Development Projects.
These tenants were relocated to a
multi-tenant air cargo complex in
the Infield area located between
the runways. Two airline maintenance hangars, a ground equipment
maintenance building and a flight
Ineld Hangar, Business Aviation, Air Trafc Control and Ancillary Facilities
Chapter 4 > A I R P O RT D E V E L O P M E N T P R O G R A M
4 . 5 S U M M A RY
The primary objective of Toronto
Pearsons Airport Development
Program has been to completely
reinvent the Airport so as to create
a facility that will better serve
passengers, shippers and the
airlines in the coming decades, and
thereby support the continued
growth of the economy in the
Greater Toronto Area. Figure 4-1
presents the work completed
under the ADP.
While the results of this program
have met the immediate needs of
the Airport, new requirements
have emerged. Figure 4-2 presents
a summary of post-ADP projects
4.6
Chapter 4 > A I R P O RT D E V E L O P M E N T P R O G R A M
4.7
Chapter 4 > A I R P O RT D E V E L O P M E N T P R O G R A M
4.8
Chapter 4 > A I R P O RT D E V E L O P M E N T P R O G R A M