CONSTRUCTION PART 2
PREPARED BY AHMAD HAKIMI BIN MAT NOR
CONSTRUCTION OF PAD
FOOTING
Construction Plan
Using the authorized construction plan, contractor will locate
the location of the footing and begin the construction works.
Excavation Work, Concreting and Curing
It is usual for the excavated surface of soil to be blinded with a
thin layer of lean concrete before the overlying structure work
takes place.
If the ground is soft and the reinforcement is heavy, blinding
layer may need to be 150 mm thick, reinforced with mesh
reinforcement.
Normal conditions blinding is 50-75mm thick grade 15 or 20
concrete, not reinforced, figure 2.1 illustrate this procedure.
Figure 2.6: Location of spacing block and the whole pad footing
Figure 2.7 show the finished pad footing with base steel
column.
Placing of Concrete
Some keys to successful placing concrete for foundation are as
follow:
a)
Compaction of concrete
Any incompletely compacted or porous zones, in which the
individual pieces of concrete aggregate are visibly separate
and the void between not filled, that enable any corrosive
chemicals in ground water solution to attack the concrete and
the reinforcement.
Concrete placed by tremie pipe has to have a relatively high
slump of 100-150 mm and therefore flows easily and selfcompacting. Concrete for normal structure use (including pad
footing) has low slump of 25 75 mm, and need to be
compacted into position to achieve a homogeneous deposit
with little trapped air.
In foundation work compaction is normally done by poker
vibrators, and sometimes by shutter mounted vibrators.
PREPARATION OF
REINFORCEMENT BAR
Preparation for steel reinforcement
Concrete reinforcement may take in the form of cage forming
at the bottom of the pad footing.
All reinforcement are to be arranged and hold up by spacer bar
at the correct distance. The bending of bar reinforcement is
specified by many codes such as BS 4466.
All forms of reinforcement should be supported on spacer
bocks, figure 2.6.
BACKFILLING
Concrete normally achieve its adequate strength after some
period and depends on the type of cement used namely,
ordinary Portland cement or the quick hardened.
Removal of formwork is accomplished as soon as the concrete
reach the strength that enough to sustain its own weight with
other loadings attached on them.
However, concrete shall be given a minimum hardening period
to prevent it from broken during the removal of formwork.
Table 2.1 shows minimum period of formwork removal from a
particular part of a structure.
Backfilling of the excavations is done as the concrete attains
strength.
10
21
END