PROGRESS REPORTS MONTH OF MARCH

HUSSAN FADHIL & PARTNERS


Activity Name
Start
Finish
Mobilization

Material Submittal Approvals


Electrical Material Submittal Approvals
Mechanical Material Submittal Approvals
Diversion of services
Excavation Soil/ Shoring/Rocks

Levelling & Compaction


Anti Termite treatment
PCC/Curing
Water Proofing PCC
Screed/Curing
Shuttering for Raft foundation
Reinforcement for Raft foundation
Raft Concreting/Curing
Col. & Retaining wall Reinf. Steel (Staircase & Lift)
Col. & Retaining wall Shuttering (Staircase & Lift)
Col. & Retaining wall Concreting (20m Pour)
Water Proofing for raft & Retaining Wall
Back Filling above raft/ Ret Wall
Anti Termite treatment (LB Floor)
Grades Slab
Sleeve works
RCC Holding Tank , Store Room
Beam & Slab Shuttering
Beam & Slab Reinforcement
PT works
Beam & Slab Concreting / Curing
PT Stressing
Col. & Retaining wall Reinf.

Original
Duration
600
0
0
30
30
100
90
90
90
90
90
15
15
60
60
333
182
10
2
2
7
8
15
15
2
20
30
28
37
37
10
15
34
34
25
25
63
20
13
4
5
2
20

BL Start

BL Finish

11-Oct-15
11-Oct-15

1-Jun-17

11-Oct-15
11-Oct-15
25-Oct-15
25-Oct-15
25-Oct-15
4-Nov-15
4-Nov-15
4-Nov-15
10-Nov-15
10-Nov-15
10-Nov-15
10-Nov-15
4-Nov-15
9-Jan-16
9-Jan-16
19-Jan-16
20-Jan-16
25-Jan-16
1-Feb-16
9-Feb-16
9-Feb-16
24-Feb-16
27-Feb-16
3-Mar-16
14-Mar-16
6-Apr-16
13-May-16
19-Jun-16
24-Jun-16
9-Mar-16
9-Mar-16
17-Mar-16
17-Mar-16
11-Apr-16
11-Apr-16
26-Apr-16
5-May-16
9-May-16
14-May-16
16-May-16

1-Jun-17
9-Nov-15
9-Nov-15
1-Feb-16
22-Jan-16
22-Jan-16
1-Feb-16
1-Feb-16
1-Feb-16
24-Nov-15
24-Nov-15
8-Jan-16
8-Jan-16
1-Oct-16
8-Jul-16
18-Jan-16
20-Jan-16
21-Jan-16
31-Jan-16
8-Feb-16
23-Feb-16
23-Feb-16
25-Feb-16
17-Mar-16
1-Apr-16
10-Apr-16
12-May-16
18-Jun-16
28-Jun-16
8-Jul-16
11-Apr-16
11-Apr-16
10-Apr-16
10-Apr-16
12-Jun-16
30-Apr-16
8-May-16
8-May-16
13-May-16
15-May-16
4-Jun-16

Actual
Start

Actual
Finish

Activity %
Complete

100%
87.00%

67%
78%
10-Nov-15
11-Nov-15

17-Dec-15

20-Dec-15

24-Dec-15

100%

27-Dec-15
3-Jan-16
10-Jan-16
20-Jan-16
20-Jan-16
8-Feb-16
11-Feb-16
13-Feb-16
20-Feb-16
27-Feb-16

27-Dec-15
22-Jan-16
23-Jan-16
3-Feb-16
7-Feb-16
9-Feb-16

100%
100%
100%
100%
100%
100%
90%
85%
85%
25%

13-Mar-16

75%

20-Mar-16

3%

Activity Name
Col. & Retaining wall Shuttering
Col. & Retaining wall Concreting
For Lift Installation works - Award of Contract
Delivery of material for lift installation works
For HVAC works - Award of Contract
Staircase & Ramp to Upper Basement floor
Staircase & Ramp (Upper Basement to Grround floor)

Beam & Slab Shuttering


Beam & Slab Reinforcement
PT works
Beam & Slab Concreting
PT Stressing

Column Reinforcement & Shuttering


Column Concreting
Beam & Slab Shuttering & Slab Reinforcement
PT works
Beam & Slab Concreting
PT Stressing
Column Reinforcement & Shuttering
Column Concreting
Beam & Slab Shuttering & Slab Reinforcement
PT works
Beam & Slab Concreting
PT Stressing
Column Reinforcement & Shuttering
Column Concreting
Beam & Slab Shuttering & Slab Reinforcement
PT works
Beam & Slab Concreting
PT Stressing
Column Reinforcement & Shuttering
Column Concreting
Beam & Slab Shuttering & Slab Reinforcement
PT works
Beam & Slab Concreting
PT Stressing

Original
Duration
25
18
244
0
180
0
80
40
40
478
24
15
13
4
1
2
478
218
26
8
1
14
5
1
2
26
8
1
14
5
1
2
26
8
1
14
5
1
2
26
8
1
14
5
1
2

BL Start

BL Finish

18-May-16
26-May-16
4-Nov-15

11-Jun-16
12-Jun-16
4-Jul-16
4-Nov-15
1-May-16
4-Jul-16
1-Oct-16
22-Aug-16
1-Oct-16
31-May-17
6-Jul-16
27-Jun-16
3-Jul-16
3-Jul-16
4-Jul-16
6-Jul-16
31-May-17
7-Feb-17
30-Jul-16
12-Jul-16
13-Jul-16
27-Jul-16
27-Jul-16
28-Jul-16
30-Jul-16
23-Aug-16
5-Aug-16
6-Aug-16
20-Aug-16
20-Aug-16
21-Aug-16
23-Aug-16
16-Sep-16
29-Aug-16
30-Aug-16
13-Sep-16
13-Sep-16
14-Sep-16
16-Sep-16
10-Oct-16
22-Sep-16
23-Sep-16
7-Oct-16
7-Oct-16
8-Oct-16
10-Oct-16

4-Nov-15
14-Jul-16
14-Jul-16
23-Aug-16
9-Feb-16
13-Jun-16
13-Jun-16
21-Jun-16
30-Jun-16
4-Jul-16
5-Jul-16
9-Feb-16
5-Jul-16
5-Jul-16
5-Jul-16
13-Jul-16
14-Jul-16
23-Jul-16
28-Jul-16
29-Jul-16
29-Jul-16
29-Jul-16
6-Aug-16
7-Aug-16
16-Aug-16
21-Aug-16
22-Aug-16
22-Aug-16
22-Aug-16
30-Aug-16
31-Aug-16
9-Sep-16
14-Sep-16
15-Sep-16
15-Sep-16
15-Sep-16
23-Sep-16
24-Sep-16
3-Oct-16
8-Oct-16
9-Oct-16

Actual
Start

Actual
Finish

Activity %
Complete

Activity Name
Column Reinforcement & Shuttering
Column Concreting
Beam & Slab Shuttering & Slab Reinforcement
PT works
Beam & Slab Concreting
PT Stressing
Column Reinforcement & Shuttering
Column Concreting
Beam & Slab Shuttering & Slab Reinforcement
PT works
Beam & Slab Concreting
PT Stressing
Column Reinforcement & Shuttering
Column Concreting
Beam & Slab Shuttering & Slab Reinforcement
PT works
Beam & Slab Concreting
PT Stressing
Column Reinforcement & Shuttering
Column Concreting
Beam & Slab Shuttering & Slab Reinforcement
PT works
Beam & Slab Concreting
PT Stressing
Column Reinforcement & Shuttering
Column Concreting
Beam & Slab Shuttering & Slab Reinforcement
PT works
Beam & Slab Concreting
PT Stressing
Lower Basement
Upper Basement
Ground Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor

Original
Duration
26
8
1
14
5
1
2
26
8
1
14
5
1
2
26
8
1
14
5
1
2
26
8
1
14
5
1
2
26
8
1
14
5
1
2
263
7
7
12
12
25
25
25
25
25
25

BL Start

BL Finish

9-Oct-16
9-Oct-16
17-Oct-16
18-Oct-16
27-Oct-16
1-Nov-16
2-Nov-16
2-Nov-16
2-Nov-16
10-Nov-16
11-Nov-16
20-Nov-16
25-Nov-16
26-Nov-16
26-Nov-16
26-Nov-16
4-Dec-16
5-Dec-16
14-Dec-16
19-Dec-16
20-Dec-16
20-Dec-16
20-Dec-16
28-Dec-16
29-Dec-16
7-Jan-17
12-Jan-17
13-Jan-17
13-Jan-17
13-Jan-17
21-Jan-17
22-Jan-17
31-Jan-17
5-Feb-17
6-Feb-17
3-Jun-16
3-Jun-16
25-Jul-16
13-Aug-16
6-Sep-16
30-Sep-16
24-Oct-16
17-Nov-16
11-Dec-16
4-Jan-17
13-Jan-17

3-Nov-16
16-Oct-16
17-Oct-16
31-Oct-16
31-Oct-16
1-Nov-16
3-Nov-16
27-Nov-16
9-Nov-16
10-Nov-16
24-Nov-16
24-Nov-16
25-Nov-16
27-Nov-16
21-Dec-16
3-Dec-16
4-Dec-16
18-Dec-16
18-Dec-16
19-Dec-16
21-Dec-16
14-Jan-17
27-Dec-16
28-Dec-16
11-Jan-17
11-Jan-17
12-Jan-17
14-Jan-17
7-Feb-17
20-Jan-17
21-Jan-17
4-Feb-17
4-Feb-17
5-Feb-17
7-Feb-17
20-Feb-17
9-Jun-16
31-Jul-16
24-Aug-16
17-Sep-16
24-Oct-16
17-Nov-16
11-Dec-16
4-Jan-17
28-Jan-17
6-Feb-17

Actual
Start

Actual
Finish

Activity %
Complete

Activity Name
Pent House
Lower Basement
Upper Basement
Ground Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Pent House
Lower Basement
Upper Basement
Ground Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Pent House
Lower Basement
Upper Basement
Ground Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Pent House
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Pent House

Original
Duration
25
271
10
12
15
15
25
25
25
25
25
25
25
296
5
5
30
25
35
35
35
35
35
35
30
307
5
5
8
8
20
20
20
20
20
20
10
183
15
15
15
15
15
15
15
15

BL Start

BL Finish

27-Jan-17
30-Jun-16
30-Jun-16
25-Jul-16
14-Sep-16
8-Oct-16
14-Nov-16
8-Dec-16
1-Jan-17
25-Jan-17
18-Feb-17
22-Feb-17
3-Mar-17
20-Jul-16
20-Jul-16
16-Aug-16
9-Oct-16
2-Nov-16
19-Dec-16
12-Jan-17
5-Feb-17
11-Mar-17
30-Mar-17
3-Apr-17
12-Apr-17
25-Jul-16
25-Jul-16
21-Aug-16
23-Nov-16
9-Dec-16
7-Feb-17
3-Mar-17
27-Mar-17
30-Apr-17
4-May-17
8-May-17
12-May-17
15-Nov-16
15-Nov-16
13-Jan-17
6-Feb-17
2-Mar-17
5-Apr-17
24-Apr-17
28-Apr-17
2-May-17

20-Feb-17
27-Mar-17
9-Jul-16
5-Aug-16
28-Sep-16
22-Oct-16
8-Dec-16
1-Jan-17
25-Jan-17
18-Feb-17
14-Mar-17
18-Mar-17
27-Mar-17
11-May-17
24-Jul-16
20-Aug-16
7-Nov-16
26-Nov-16
22-Jan-17
15-Feb-17
11-Mar-17
14-Apr-17
3-May-17
7-May-17
11-May-17
27-May-17
29-Jul-16
25-Aug-16
30-Nov-16
16-Dec-16
26-Feb-17
22-Mar-17
15-Apr-17
19-May-17
23-May-17
27-May-17
21-May-17
16-May-17
29-Nov-16
27-Jan-17
20-Feb-17
16-Mar-17
19-Apr-17
8-May-17
12-May-17
16-May-17

Actual
Start

Actual
Finish

Activity %
Complete

Activity Name
Lower Basement
Upper Basement
Ground Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Seventh Floor
Sixth Floor
Pent House
Parapet Block work
Water proofing works, screed and tiles

MEP Works in slab


Installation of sleeves under raft foundation
Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Installation of sleeves/pipes under raft foundation
Install drainage piping
High level water supply piping
Test drainage piping
Lay water supply pipe in wall
Test/Insulate water supply pipe lines
High level fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes
Installation of DX units
Installation of ventilation fans
Fixing of grilles

MEP Works in slab

Original
Duration
294
4
4
20
20
20
20
20
20
20
20
20
55
25
30
478
197
194
15
7
4
7
10
15
5
10
185
7
15
15
6
12
7
75
30
6
10
92
10
4
15
10
5
152
141
15

BL Start

BL Finish

25-Jul-16
25-Jul-16
21-Aug-16
24-Oct-16
15-Nov-16
13-Jan-17
6-Feb-17
2-Mar-17
5-Apr-17
21-Apr-17
24-Apr-17
25-Apr-17
11-Feb-17
11-Feb-17
8-Mar-17
9-Feb-16
9-Feb-16
9-Feb-16
9-Feb-16
14-Feb-16
7-Jun-16
4-Jul-16
16-Jul-16
26-Jul-16
10-Aug-16
11-Aug-16
17-Feb-16
17-Feb-16
20-Jun-16
22-Jun-16
5-Jul-16
1-Aug-16
13-Aug-16
24-May-16
24-May-16
28-Jun-16
28-Jul-16
24-May-16
24-May-16
26-May-16
31-May-16
15-Jun-16
19-Aug-16
26-Apr-16
29-Apr-16
29-Apr-16

14-May-17
28-Jul-16
24-Aug-16
12-Nov-16
4-Dec-16
1-Feb-17
25-Feb-17
21-Mar-17
24-Apr-17
10-May-17
13-May-17
14-May-17
6-Apr-17
7-Mar-17
6-Apr-17
31-May-17
23-Aug-16
20-Aug-16
23-Feb-16
20-Feb-16
10-Jun-16
10-Jul-16
25-Jul-16
9-Aug-16
14-Aug-16
20-Aug-16
19-Aug-16
23-Feb-16
4-Jul-16
6-Jul-16
10-Jul-16
12-Aug-16
19-Aug-16
6-Aug-16
22-Jun-16
3-Jul-16
6-Aug-16
23-Aug-16
2-Jun-16
29-May-16
14-Jun-16
24-Jun-16
23-Aug-16
24-Sep-16
16-Sep-16
13-May-16

Actual
Start

Actual
Finish

Activity %
Complete

Activity Name
Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install cold water booster pumps
Install drainage piping
High level water supply piping
Test drainage piping
Lay water supply pipe in wall
Test/Insulate water supply pipe lines
High level fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes
Installation of DX units
Installation of ventilation fans
Fixing of grilles

MEP Works in slab


Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install drainage piping
High level water supply piping
Test drainage piping
Lay water supply pipe in wall
Test/Insulate water supply pipe lines
Fixing of final accessories
Install fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes

Original
Duration
4
7
10
15
5
10
124
30
20
30
7
10
15
67
25
7
10
70
10
4
15
10
5
167
165
7
20
25
15
15
10
10
120
20
30
7
10
10
20
92
20
7
15
87
35
30

BL Start

BL Finish

29-Jul-16
29-Jul-16
10-Aug-16
20-Aug-16
4-Sep-16
7-Sep-16
26-Apr-16
26-Apr-16
12-Jul-16
14-Jul-16
1-Aug-16
3-Aug-16
13-Aug-16
20-Jul-16
20-Jul-16
14-Aug-16
15-Sep-16
12-Jul-16
12-Jul-16
14-Jul-16
19-Jul-16
3-Aug-16
15-Sep-16
19-Jun-16
19-Jun-16
19-Jun-16
17-Aug-16
20-Sep-16
20-Oct-16
4-Nov-16
19-Nov-16
21-Nov-16
5-Aug-16
5-Aug-16
7-Aug-16
25-Aug-16
27-Aug-16
6-Sep-16
13-Nov-16
5-Aug-16
5-Aug-16
25-Aug-16
21-Oct-16
5-Aug-16
5-Aug-16
7-Aug-16

1-Aug-16
4-Aug-16
19-Aug-16
3-Sep-16
8-Sep-16
16-Sep-16
27-Aug-16
25-May-16
31-Jul-16
12-Aug-16
7-Aug-16
12-Aug-16
27-Aug-16
24-Sep-16
13-Aug-16
20-Aug-16
24-Sep-16
19-Sep-16
21-Jul-16
17-Jul-16
2-Aug-16
12-Aug-16
19-Sep-16
2-Dec-16
30-Nov-16
25-Jun-16
5-Sep-16
14-Oct-16
3-Nov-16
18-Nov-16
28-Nov-16
30-Nov-16
2-Dec-16
24-Aug-16
5-Sep-16
31-Aug-16
5-Sep-16
15-Sep-16
2-Dec-16
4-Nov-16
24-Aug-16
31-Aug-16
4-Nov-16
30-Oct-16
8-Sep-16
5-Sep-16

Actual
Start

Actual
Finish

Activity %
Complete

Activity Name
Installation of VRF indoor units
Installation of ventilation fans
Fixing of grilles

MEP Works in slab


Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install drainage piping
High level water supply piping
Lay water supply pipe in wall
Test drainage piping
Test/Insulate water supply pipe lines
Fixing of final accessories
Install fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes
Installation of VRF indoor units
Installation of ventilation fans
Fixing of grilles

MEP Works in slab


Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install drainage piping
High level water supply piping
Test drainage piping
Lay water supply pipe in wall
Test/Insulate water supply pipe lines
Fixing of final accessories

Original
Duration
15
15
10
184
166
8
30
25
15
15
15
7
120
20
30
10
7
15
20
105
20
7
10
108
35
30
10
15
10
219
184
8
30
25
15
15
15
7
155
20
30
7
10
15
20
128

BL Start

BL Finish

12-Aug-16
27-Aug-16
21-Oct-16
26-Jun-16
26-Jun-16
26-Jun-16
12-Sep-16
16-Oct-16
18-Oct-16
26-Oct-16
10-Nov-16
2-Dec-16
29-Aug-16
29-Aug-16
31-Aug-16
11-Sep-16
18-Sep-16
30-Sep-16
7-Dec-16
29-Aug-16
29-Aug-16
18-Sep-16
2-Dec-16
29-Aug-16
29-Aug-16
31-Aug-16
5-Sep-16
30-Nov-16
2-Dec-16
20-Jul-16
20-Jul-16
20-Jul-16
13-Oct-16
27-Nov-16
29-Nov-16
7-Dec-16
22-Dec-16
13-Jan-17
22-Sep-16
22-Sep-16
24-Sep-16
12-Oct-16
25-Oct-16
4-Nov-16
4-Feb-17
22-Sep-16

26-Aug-16
10-Sep-16
30-Oct-16
26-Dec-16
8-Dec-16
3-Jul-16
11-Oct-16
9-Nov-16
1-Nov-16
9-Nov-16
24-Nov-16
8-Dec-16
26-Dec-16
17-Sep-16
29-Sep-16
20-Sep-16
24-Sep-16
14-Oct-16
26-Dec-16
11-Dec-16
17-Sep-16
24-Sep-16
11-Dec-16
14-Dec-16
2-Oct-16
29-Sep-16
14-Sep-16
14-Dec-16
11-Dec-16
23-Feb-17
19-Jan-17
27-Jul-16
11-Nov-16
21-Dec-16
13-Dec-16
21-Dec-16
5-Jan-17
19-Jan-17
23-Feb-17
11-Oct-16
23-Oct-16
18-Oct-16
3-Nov-16
18-Nov-16
23-Feb-17
27-Jan-17

Actual
Start

Actual
Finish

Activity %
Complete

Activity Name
Install fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes
Installation of VRF indoor units
Fixing of grilles
Installation of ventilation fans

MEP Works in slab


Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install drainage piping
High level water supply piping
Test drainage piping
Lay water supply pipe in wall
Test/Insulate water supply pipe lines
Fixing of final accessories
Install fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes
Installation of VRF indoor units
Fixing of grilles
Installation of ventilation fans

MEP Works in slab


Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install drainage piping

Original
Duration
20
7
10
143
35
30
10
10
15
219
184
8
30
25
15
15
15
7
155
20
30
7
10
15
20
128
20
7
10
143
35
30
10
10
15
219
184
8
30
25
15
15
15
7
155
20

BL Start

BL Finish

22-Sep-16
12-Oct-16
18-Jan-17
22-Sep-16
22-Sep-16
24-Sep-16
29-Sep-16
18-Jan-17
28-Jan-17
13-Aug-16
13-Aug-16
13-Aug-16
6-Nov-16
21-Dec-16
23-Dec-16
31-Dec-16
15-Jan-17
6-Feb-17
16-Oct-16
16-Oct-16
18-Oct-16
5-Nov-16
18-Nov-16
28-Nov-16
28-Feb-17
16-Oct-16
16-Oct-16
5-Nov-16
11-Feb-17
16-Oct-16
16-Oct-16
18-Oct-16
23-Oct-16
11-Feb-17
21-Feb-17
6-Sep-16
6-Sep-16
6-Sep-16
30-Nov-16
14-Jan-17
16-Jan-17
24-Jan-17
15-Feb-17
2-Mar-17
9-Nov-16
9-Nov-16

11-Oct-16
18-Oct-16
27-Jan-17
11-Feb-17
26-Oct-16
23-Oct-16
8-Oct-16
27-Jan-17
11-Feb-17
19-Mar-17
12-Feb-17
20-Aug-16
5-Dec-16
14-Jan-17
6-Jan-17
14-Jan-17
29-Jan-17
12-Feb-17
19-Mar-17
4-Nov-16
16-Nov-16
11-Nov-16
27-Nov-16
12-Dec-16
19-Mar-17
20-Feb-17
4-Nov-16
11-Nov-16
20-Feb-17
7-Mar-17
19-Nov-16
16-Nov-16
1-Nov-16
20-Feb-17
7-Mar-17
12-Apr-17
8-Mar-17
13-Sep-16
29-Dec-16
7-Feb-17
30-Jan-17
7-Feb-17
1-Mar-17
8-Mar-17
12-Apr-17
28-Nov-16

Actual
Start

Actual
Finish

Activity %
Complete

Activity Name
High level water supply piping
Test drainage piping
Lay water supply pipe in wall
Test/Insulate water supply pipe lines
Fixing of final accessories
Install fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes
Installation of VRF indoor units
Fixing of grilles
Installation of ventilation fans

MEP Works in slab


Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install drainage piping
High level water supply piping
Test drainage piping
Lay water supply pipe in wall
Test/Insulate water supply pipe lines
Fixing of final accessories
Install fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes
Installation of VRF indoor units
Fixing of grilles
Installation of ventilation fans

MEP Works in slab


Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System

Original
Duration
30
7
10
15
20
128
20
7
10
143
35
30
10
10
15
236
184
8
30
25
15
15
15
7
189
20
30
7
10
15
20
133
20
7
15
172
35
30
10
10
15
218
184
8
30
25

BL Start

BL Finish

11-Nov-16
29-Nov-16
14-Dec-16
24-Dec-16
24-Mar-17
9-Nov-16
9-Nov-16
29-Nov-16
7-Mar-17
9-Nov-16
9-Nov-16
11-Nov-16
16-Nov-16
7-Mar-17
17-Mar-17
30-Sep-16
30-Sep-16
30-Sep-16
24-Dec-16
7-Feb-17
9-Feb-17
17-Feb-17
11-Mar-17
26-Mar-17
9-Nov-16
9-Nov-16
11-Nov-16
29-Nov-16
7-Jan-17
17-Jan-17
27-Apr-17
3-Dec-16
3-Dec-16
23-Dec-16
31-Mar-17
3-Dec-16
3-Dec-16
5-Dec-16
10-Dec-16
24-Apr-17
9-May-17
24-Oct-16
24-Oct-16
24-Oct-16
17-Jan-17
3-Mar-17

10-Dec-16
5-Dec-16
23-Dec-16
7-Jan-17
12-Apr-17
16-Mar-17
28-Nov-16
5-Dec-16
16-Mar-17
31-Mar-17
13-Dec-16
10-Dec-16
25-Nov-16
16-Mar-17
31-Mar-17
23-May-17
1-Apr-17
7-Oct-16
22-Jan-17
3-Mar-17
23-Feb-17
3-Mar-17
25-Mar-17
1-Apr-17
16-May-17
28-Nov-16
10-Dec-16
5-Dec-16
16-Jan-17
31-Jan-17
16-May-17
14-Apr-17
22-Dec-16
29-Dec-16
14-Apr-17
23-May-17
6-Jan-17
3-Jan-17
19-Dec-16
3-May-17
23-May-17
29-May-17
25-Apr-17
31-Oct-16
15-Feb-17
27-Mar-17

Actual
Start

Actual
Finish

Activity %
Complete

Activity Name
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install drainage piping
High level water supply piping
Test drainage piping
Lay water supply pipe in wall
Test/Insulate water supply pipe lines
Fixing of final accessories
Install fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes
Installation of VRF indoor units
Fixing of grilles
Installation of ventilation fans

MEP Works in slab


Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install drainage piping
High level water supply piping
Test drainage piping
Lay water supply pipe in wall
Test/Insulate water supply pipe lines
Fixing of final accessories
Install fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes
Installation of VRF indoor units
Fixing of grilles

Original
Duration
15
15
15
7
154
20
30
7
10
15
20
128
20
7
10
148
35
30
10
10
15
195
164
8
30
25
15
15
15
7
131
20
30
7
10
15
20
108
20
7
10
128
35
30
10
10

BL Start

BL Finish

5-Mar-17
13-Mar-17
4-Apr-17
19-Apr-17
27-Dec-16
27-Dec-16
29-Dec-16
16-Jan-17
31-Jan-17
10-Feb-17
10-May-17
27-Dec-16
27-Dec-16
16-Jan-17
24-Apr-17
27-Dec-16
27-Dec-16
29-Dec-16
3-Jan-17
24-Apr-17
9-May-17
17-Nov-16
17-Nov-16
17-Nov-16
26-Jan-17
7-Mar-17
9-Mar-17
17-Mar-17
8-Apr-17
23-Apr-17
20-Jan-17
20-Jan-17
22-Jan-17
9-Feb-17
9-Feb-17
19-Feb-17
11-May-17
20-Jan-17
20-Jan-17
9-Feb-17
28-Apr-17
20-Jan-17
20-Jan-17
22-Jan-17
27-Jan-17
28-Apr-17

19-Mar-17
27-Mar-17
18-Apr-17
25-Apr-17
29-May-17
15-Jan-17
27-Jan-17
22-Jan-17
9-Feb-17
24-Feb-17
29-May-17
3-May-17
15-Jan-17
22-Jan-17
3-May-17
23-May-17
30-Jan-17
27-Jan-17
12-Jan-17
3-May-17
23-May-17
30-May-17
29-Apr-17
24-Nov-16
24-Feb-17
31-Mar-17
23-Mar-17
31-Mar-17
22-Apr-17
29-Apr-17
30-May-17
8-Feb-17
20-Feb-17
15-Feb-17
18-Feb-17
5-Mar-17
30-May-17
7-May-17
8-Feb-17
15-Feb-17
7-May-17
27-May-17
23-Feb-17
20-Feb-17
5-Feb-17
7-May-17

Actual
Start

Actual
Finish

Activity %
Complete

Activity Name
Installation of ventilation fans

MEP Works in slab


Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install drainage piping
High level water supply piping
Lay water supply pipe in wall
Test drainage piping
Test/Insulate water supply pipe lines
Fixing of final accessories
Install fire fighting pipes
Testing of fire fighting pipes
Install sprinkler heads & Equipments
Installation of AC ducting with accessories
Install refrigerant pipes
Installation of VRF indoor units
Fixing of grilles
Installation of ventilation fans

MEP Works in slab


Wall conduits, GI Boxes & Back Boxes
Wiring for Power/Lighting/Low Current System
Cable tray/Trunking
Cabling Works
Install DBs dressing & Termination
Installation of final accessories
Install drainage piping
Test drainage piping
Lay water supply pipe in wall
Fixing of water tanks & pumps
Test/Insulate water supply pipe lines
Install refrigerant pipes
Installation of VRF outdoor units
Testing of refrigerant pipes

Original
Duration
15
172
149
8
30
25
15
15
15
7
106
20
30
10
7
15
20
78
20
7
10
108
35
30
10
10
15
134
134
8
30
30
15
20
10
7
104
10
5
40
30
10
50
40
30
15

BL Start

BL Finish

13-May-17
11-Dec-16
11-Dec-16
11-Dec-16
9-Feb-17
16-Mar-17
18-Mar-17
26-Mar-17
10-Apr-17
2-May-17
13-Feb-17
13-Feb-17
15-Feb-17
23-Feb-17
5-Mar-17
5-Mar-17
10-May-17
13-Feb-17
13-Feb-17
5-Mar-17
22-Apr-17
13-Feb-17
13-Feb-17
15-Feb-17
20-Feb-17
22-Apr-17
17-May-17
5-Jan-17
5-Jan-17
5-Jan-17
10-Mar-17
9-Apr-17
12-Apr-17
22-Apr-17
7-May-17
12-May-17
23-Jan-17
23-Jan-17
2-Feb-17
10-Mar-17
7-Apr-17
19-Apr-17
6-Feb-17
6-Feb-17
26-Feb-17
13-Mar-17

27-May-17
31-May-17
8-May-17
18-Dec-16
10-Mar-17
9-Apr-17
1-Apr-17
9-Apr-17
24-Apr-17
8-May-17
29-May-17
4-Mar-17
16-Mar-17
4-Mar-17
11-Mar-17
19-Mar-17
29-May-17
1-May-17
4-Mar-17
11-Mar-17
1-May-17
31-May-17
19-Mar-17
16-Mar-17
1-Mar-17
1-May-17
31-May-17
18-May-17
18-May-17
12-Jan-17
8-Apr-17
8-May-17
26-Apr-17
11-May-17
16-May-17
18-May-17
6-May-17
1-Feb-17
6-Feb-17
18-Apr-17
6-May-17
28-Apr-17
27-Mar-17
17-Mar-17
27-Mar-17
27-Mar-17

Actual
Start

Actual
Finish

Activity %
Complete

Original
Duration
142
120
80
80
30
164
160
150
120
282
30
30
30
30
30
30
30
30
30
30
30
140
22
35
35

BL Start

BL Finish

9-Jan-17
9-Jan-17
8-Feb-17
10-Mar-17
1-May-17
25-Oct-16
25-Oct-16
8-Nov-16
8-Nov-16
20-Jul-16
20-Jul-16
16-Aug-16
21-Sep-16
2-Nov-16
19-Dec-16
12-Jan-17
5-Feb-17
1-Mar-17
23-Mar-17
25-Mar-17
29-Mar-17
18-Nov-16
18-Nov-16
30-Nov-16
16-Feb-17

30-May-17
8-May-17
28-Apr-17
28-May-17
30-May-17
6-Apr-17
2-Apr-17
6-Apr-17
7-Mar-17
27-Apr-17
18-Aug-16
14-Sep-16
20-Oct-16
1-Dec-16
17-Jan-17
10-Feb-17
6-Mar-17
30-Mar-17
21-Apr-17
23-Apr-17
27-Apr-17
6-Apr-17
9-Dec-16
3-Jan-17
22-Mar-17

Paving & Walkways, Fillings, Wall Guards, Car Parkings IIdentification, Speed Breaker

40

26-Feb-17

6-Apr-17

External Painting

30
35
35
30
30
30
30
30
47
30
27
1

8-Mar-17
3-Mar-17
3-Mar-17
3-Mar-17
3-Mar-17
3-Mar-17
3-Apr-17
3-Apr-17
16-Apr-17
16-Apr-17
3-May-17
1-Jun-17

6-Apr-17
6-Apr-17
6-Apr-17
1-Apr-17
1-Apr-17
1-Apr-17
2-May-17
2-May-17
1-Jun-17
15-May-17
29-May-17
1-Jun-17

Activity Name
Install Car brackets & guide rails
Lift shaft trunking and conduits etc and wiring of lift shaft
Install Car frame and platform, Car wall panels
Testing and Commissioning
Glazing works
Vanity cabinet works
Metal Works
Lower Basement
Upper Basement
Ground Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Pent House
Sixth Floor
Seventh Floor
Water Proofing (Stone Cladding)
Fixing of Stone Cladding
External Plastering

Main Power connection to Government


Plumbing Works (Provision)
Electrical Works (Provision)
Lightning Protection Works
Authority approvals from various departments
Testing & Commissioning
Snagging & Review
Handing Over

Actual
Start

Actual
Finish

Activity %
Complete