Union University
References
Technical Issues
Fuel cost in $/mmBtu
Electrical cost in cents/kwh
Operating hours/year
Electric load in MW
Steam load in '000 lbs/hr
Steam Pressure requirement in psig
Political Issues
Utility friendly?
State is on board with this technology?
Environmental Issues
ol
//www.armstrong-intl.com)
GEN_Cogen_Guide.pdf
o_prince.pdf
***********************************************************************************************************************************************
Assumptions:
The following assumptions, which are standard, have been made. Change if better information is available
Electric load factor
80 %
Steam load factor
80 %
Shaft efficiency
35 %
Electrical capacity factor (ave kw output for the period per system kw capacity)
90 %
Thermal capacity factor (ave pph steam output for the period /system capacity)
95 %
Installed cost of the cogeneration unit
1100 $/kw
***********************************************************************************************************************************************
Calculations:
The following calculations have been performed from the above given data
$
$
2,628,000
5000 kw
963,600
3,591,600
$
$
$
$
$
$
35,040,000
307,431
35,040,000
15,952
4,400,000
1,424,746
480,000
140,160
72,337
2,117,243
Economics:
Net savings
Simple Payback
ROI
Environmental:
kwh
mmbtu
kwh
pph
$4,100,000
$3,600,000
Operating
Cost
$3,100,000
$2,600,000
$2,100,000
$1,600,000
$1,100,000
$600,000
$100,000
3.5
Payback Period (yrs)
3
2.5
2
1.5
1
0.5
0
Sensitivity Analysis of G
$4,000,000
$3,500,000
$3,000,000
Cost $2,500,000
$2,000,000
$1,500,000
$1,000,000
$500,000
c Analyses
l Are Required)
$ per kw.mo
******************************
tter information is available.
3.0
21
3.0
21
to generate electricity
00
00
00
00
00
00
00
00
25
20
15
10
5
0
***********************************************************************************************************************************************
Assumptions:
The following assumptions, which are standard, have been made. Change if better information is availabe
Electric load factor
Steam load factor
Shaft efficiency
Electrical capacity factor (ave kw output for the period per system kw capacity)
Thermal capacity factor (ave pph steam output for the period per system capacity)
Installed cost of cogeneration unit
Steam-to-power rating
***********************************************************************************************************************************************
Calculations:
The following calculations have been performed from the above given data
Annual electric cost
Peak demand
Annual fuel cost
Cost without cogen option
Site's total electrical requirement
unit's power output
Fuel input
Electrical output
Steam output
Installed cost
Cost of fuel
Supplemental cost of electricity
Supplemental cost of steam
Cost of standby power
O&M cost
Economics:
Environmental:
$7,000,000
$7,000,000
Payback Period (yrs)
$6,000,000
Operating Cost
$5,000,000
2.5
$4,000,000
1.5
$3,000,000
$3,000,000
$2,000,000
0.5
$2,000,000
$1,000,000
$1,000,000
$6,000,000
$5,000,000
Cost $4,000,000
*************************************************************
e been made. Change if better information is availabe.
80 %
80 %
30 %
90 %
95 %
700 $/kw
22 pph/kw
*************************************************************
m the above given data
$
$
$
$
$
$
$
$
$
$
35,040,000 kwh/yr
3000 kw
298,891 mmbtu
23,652,000 kwh
66,000 pph
2,100,000
3,854,400
854,100
254,390
600,000
52,560
5,615,450
866,950 per year
2.4 years
27
to generate electricity
2.4222861398
2.4222861398
27
27
$7,000,000
30
$6,000,000
25
$5,000,000
20
Cost $4,000,000
15
$3,000,000
10
$2,000,000
$1,000,000
***********************************************************************************************************************************************
Assumptions:
The following assumptions, which are standard, have been made. Change if better information is available
Electric load factor
Steam load factor
Shaft efficiency
Electrical capacity factor (ave kw output for the period per system kw capacity)
Thermal capacity factor (ave pph steam output for the period per system capacity
Installed cost
percent system availability per year
80 %
80 %
40 %
90 %
95 %
1000 $/kw
90 %
***********************************************************************************************************************************************
Calculations:
The following calculations have been performed from the above given data
Annual electric cost
Annual fuel cost
$
$
2,628,000
963,600
3,591,600
$
$
$
$
$
$
67,251 mmbtu/yr
8,760,000 kwh
3,490 pph
1,000,000
1,017,683
1,971,000
120,000
78,840
15,824
Fuel input
Electrical output
Steam generated
Installed cost
Cost of fuel
supplemental cost of electricity
Cost of standby power
O&M cost
Supplemental boiler fuel
Economics:
Environmental:
$
$
3,203,347
388,253 per year
2.6 years
25
3,530 metric tons /yr
$3,800,000
$3,300,000
Operating Cost
$2,800,000
$2,300,000
$1,800,000
$1,300,000
$800,000
$300,000
3
2.5
2
1.5
1
0.5
0
$3,800,000
$3,300,000
$2,800,000
Cost $2,300,000
$1,800,000
$1,300,000
$800,000
$300,000
Please select ROI tab to review the Return on Investments of the 3 cogeneration technologies
mic Analyses
Are Required)
$ per kw.mo
*****************************
ter information is available.
*****************************
to generate electricity
2.57564
0
25
25
30
25
20
15
10
5
0
$
$
$
$
$
$
$
$
$
$
$
$
Cogeneration Technology
Economic Consideration
$1,000,000
$900,000
$800,000
Investment
Cost
$700,000
$600,000
$500,000
$400,000
$300,000
$200,000
$100,000
$-
30
25
20
15
10
5
0
ment Calculations
$
$
$
$
$
$
Environmental Benefits
Greenhouse Gas Emission Equivalent acres of
Reduction Metric Tons CO2 Trees to be planted
Gas Turbine
13,403
2,949
Steam Turbine
7,881
1,734
Recip Engine
3,530
777