Project:

SAMSUN CCPP

Title: ITP of Switchgears

KKS Document No:

440-00-YG-QPH-KSR-002

Rev.:00

Purpose of issue:

Approval

Date:19/07/2011

Prepared:

KSR

Reviewed:

PPR

Approved:

OMV

Power Projects Ltd. reserve all rights on this document and on the information contained therein.
Reproduction, use or disclosure to third parties without Power Projects Ltd. written permission is strictly forbidden

KKS NO:

Rev:
0

Project: SAMSUN CCPP

Page No:
0

440-00-YG-QPH-KSR-002

LIST OF REVISIONS

Index

Date

19/07/2011

Pages

Raw Description

Previous Rev.

Current Rev.

00

Prepared

KSR

Checked

PPR

Approved

OMV

INSPECTION AND TEST PLAN

CCPP SAMSUN: Erection of Electrical System

KKS/Record
No:
Revision:

440-00-YG-QPH-KSR-002

Date:

19.07.2011

Switchgear Erection
No

2
3
4

Description

BEFORE ERECTION

TRANSPORTATION
INSTALLATION
UNPACK
INSTALATION
MV SWTCHGEARS
ERECTION

FINAL
DOCUMENTATION

Activity

Relevant
Document

KESIR
ENGINEERING

PPR

OMV

Packing list, Drawings


and Documents

SW

MoS & R.A.

Calibration
Certificate

TRANSPORTATION INSTALLATION

Installation Instruction

SW

SW

UNPACK INSTALATION

Installation Instruction

SW

COLUMNS INSTALLATION (LIFTING ALIGNMENT - LEVELING - FIXING ASSEMBLING) INSPECTION


ELECTRICAL JOINTS INSPECTION
(Installation Main Busbar, Bolts and Screws
Tightening )
EXTERNAL CABLE TERMINATIONS &
FASTENINGS (CLAMPS, ETC)
INSPECTION (Visual check in all
enclosures that sealing at cable entry points
and IP rating is maintained)
MECHANICAL COMPLETION
INSPECTION / TURN OVER PACKAGE
(1/Check that all components mounted in
doors are correctly fitted.
2/Check that all mechanical operated
components work properly.
3/Check that all clearance distances
between phases and between phase/earth
are correct.
4/Check that withdrawable units are moving
untroubled, and that position locks and
interlock systems are working correctly.)
CLEANLINESS INSPECTION
EARTHING CIRCUIT ERECTION
INSPECTION
DOCUMENTATION REVIEW (2 hard &
2soft copies will be submitted to PPR

Installation Instruction
MV Switchgear Front
View
Installation Instruction
MV Switchgear Wiring
diagrams

SW

SW

Visual Inspection
Report

Installation Instruction

Visual Inspection
Report

SW

Installation Instruction

Check list

SW

CHECKING THE EXISTENCE OF THE


LAST REVISION OF THE APPROVED
INSTALLATION DOCUMENTATION AND
MATERIALS
MoS and RISK ASSESMENT SHAL BE
SUBMITTEDTO PPR, BEFORE ERECTION
ALL VERIFICATION OF EQUIPMENT
CALIBRATION FOR ERECTION AND
INSPECTION

Specifications

Installation Instruction

Installation Instruction

SW

Drawings

Handover
Package

NOTES:
Definitions
E: Works Execution
R: Records review

SW: Spot witness point


W: Witness point
H: Hold point

Notes

Revision
0

Modifications

Prepared by
KESIR

Check by
PPR

Approved by
OMV

Date
19.07.2011