SECTION 6
Conveyor Maintenance
Chapter 26.............................................................................. 414
Conveyor Accessibility
Chapter 27.............................................................................. 424
Conveyor System Survey
Chapter 28.............................................................................. 434
Maintenance
Chapter 29.............................................................................. 444
The Human Factor
413
Figure 26.1
In a bulk-material
handling system, access
means observation
points, entry doors, and
workspace for repairs
and cleaning.
Chapter 26
26
Conveyor
Accessibility
Access: Making It Easy................................................................................ 415
Space Around Conveyors.............................................................................. 416
Guarding................................................................................................... 418
Observation and Entry Doors.. ....................................................................... 419
Confined Space.......................................................................................... 420
Safety Concerns......................................................................................... 421
Typical Specifications................................................................................... 422
The Benefit of Access.. ................................................................................ 422
414
In this Chapter
26
C. Easy to replace
If an equipment problem is known,
but unnecessarily requires an outage to
correct, the broken equipment is likely
to remain out of order for an extended
period.
When systems are too difficult to see,
reach, and replace, plant operations or
maintenance personnel may attempt short415
cuts during repairs. Such shortcuts often increase risks to safety, as well as add the potential for additional damage to equipment.
Taking shortcutswhether intentionally or
because of the lack of proper access and,
therefore, the inability to follow proper
maintenance procedurescan easily result
in reduced safety, shorter equipment life,
reduced process efficiency, and an increase
in the emission of fugitive materials.
SPACE AROUND CONVEYORS
Figure 26.3
26
416
26
Figure 26.4
Anywhere a person
must stand or kneel
to perform service or
inspection, the head
room should be at
least 1200 millimeters
(48 in.).
417
26
It is not uncommon
to see a conveyor
or transfer point
captured in a web
of electrical conduit,
dust-suppression
piping, control
panels, or sprinkler
systems.
Figure 26.6
A barrier guard is
a fence, or other
obstacle, to keep
personnel away from
a conveyor and its
components.
418
In many facilities, conventional physical barriers are being replaced with newer
technologies that monitor area perimeters
and detect entry to hazardous areas.
However, these newer technologies, such
as laser beams and infrared light curtains,
are effective only when power is on, and
they can be fooled by someone determined
to gain entrance to a secure area. These
systems require care and good maintenance
in order to be reliable. For example, they
might not function well where airborne
dust can settle onto the electric eye receivers. It is wise to have mechanical accesscontrol systems as redundant or back-up
systems, as a failure of the high-tech
devices may not be obvious.
OBSERVATION AND ENTRY DOORS
Observation Requirements
Figure 26.7
Visual inspection
of conveyor
components and
access to lubrication
points should be
possible without
removal of the barrier
guards.
Figure 26.8
Barrier guards may
be hinged, allowing
them to be moved
out of position, or
they may be bolted in
place.
Figure 26.9
Flow problems within
chutes may be more
easily solved if the
material path can be
observed through an
inspection door.
Figure 26.10
A poorly placed
door will not allow
observation of the
path of material flow.
419
26
Inspection doors should be side opening and sized so personnel can easily and
safely view the components inside the
structure. Doors must be installed on the
non-wearing side(s) of the chute (that is, the
side(s) away from the flow of impacting, or
abrasive, material).
Doors should be designed for easy operation in tight clearances, with corrosionresistant hinges and latching systems. It
is important that all ports be dust-tight
through use of a securely sealing door.
Hinged metal doors with easy-opening
latches are now available to provide access
26
Figure 26.11
Hinged metal doors
with easy-opening
latches are available
to provide access.
420
26
Figure 26.12
CEMA recommends
that warning labels
are to be placed in a
conspicuous location
near or on the access
door that warn of
potential hazards that
may be encountered
when the door is
opened.
421
Figure 26.13
Another approach
is to design nonconfined-space chute
access that allows
whole sections of
chutes to be easily
opened.
C. Access
Suitable access for viewing and service
will be provided to the conveyor, the
transfer point, and other related systems.
Sufficient openings will be provided to
allow inspection of all interior areas.
D. Viewing ports
A. Walkways
To facilitate inspection and service, the
conveyor will be fitted with walkways on
both sides. These walkways will provide
sufficient space for the required maintenance activities at points where service
work will need to be performed.
B. Guards
26
422
This chapter regarding Conveyor Accessibility is the first chapter in the section
Conveyor Maintenance. The following
chapter, Conveyor System Survey, continues the discussion about the type of
maintenance needed to extend the life of
the conveyor system and reduce dust and
spillage.
References
26.1 Mine Safety and Health Administration (MSHA). (2004). MSHAs Guide
to Equipment Guarding. Other Training Material OT 3, 40 pages. U.S.
Department of Labor. Available as
a free download: http://www.msha.
gov/s&hinfo/equipguarding2004.
pdf
26.2 Giraud, Laurent; Schreiber, Luc;
Mass, Serge; Turcot, Andr; and
Dub, Julie. (2007). A Users Guide
to Conveyor Belt Safety: Protection from
Danger Zones. Guide RG-490, 75
pages. Montral, Quebec, Canada:
IRSST (Institut de recherche RobertSauv en sant et en scurit du
travail), CSST. Available in English
and French as a free downloadable
PDF: http://www.irsst.qc.ca/files/
documents/PubIRSST/RG-490.
pdf or html: http://www.irsst.qc.ca/
en/_publicationirsst_100257.html
26.3 Conveyor Equipment Manufacturers
Association (CEMA). (2004). CEMA
SPB-001 (2004) Safety Best Practices
Recommendation: Design and Safe Application of Conveyor Crossovers for Unit
Handling Conveyors. Naples, Florida.
26.4 Conveyor Equipment Manufacturers
Association (CEMA). (2005). BELT
CONVEYORS for BULK MATERIALS,
Sixth Edition. Naples, Florida.
26
423
Figure 27.1
Walking the belt
is used to evaluate
the state of the
equipment and provide
opportunities for
routine maintenance,
adjustment, and cleanup
of the various conveyor
components.
Chapter 27
Conveyor
System Survey
27
In this Chapter
27
425
Table 27.2
Function
Anemometer
Angle Finder
Decibel Meter
Durometer Reader
Infrared Thermometer
Level
Soap Stone
Tachometer
Tape Measure
Measure distances
Flashlight
Camera
Record data
Tool Belt/Harness
Date:
Conveyor ID [name or number]
Location
Length-Pulley Centers [m (ft)]
Conveyor Capacity [tons/h (st/h]
Total Lift (Elevation Change) [+/-m (ft)]
Hours Conveyor Runs/Day [hours]
Days Conveyor Operates/Week [days]
Belt Width [mm (in.)]
Belt Speed [m/sec (ft/min)]
Trough Angle [degrees]
Belting
27
Material Conveyed
Material Size (Maximum Lump) [mm (in.)]
Material Temperature [Celsius (F)]
Material Drop Height [m (ft)]
Moisture Content (Maximum) [%]
Moisture Content (Normal) [%]
Conveyor Drive
426
Table 27.2
Continued
Carrying Idlers
Impact Idlers
Impact Cradles
Belt-Support Cradles
Return Idlers
Airflow
Components
27
Misalignment Switches
Carrying-Side Training Devices
Return-Side Training Devices
Primary Belt-Cleaning Systems
Secondary Belt-Cleaning Systems
Tail-Protection Plows
Dust Collectors
Dust-Suppression Systems
Chute Flow-Aid Devices
Access Doors
427
design information and any change records. Best practice is to regularly update
the data with changes as part of a regular
inspection cycle.
Maintenance Inspection
Walking the Belt for Routine
Inspection
27
428
There may come a time when the inspector sees something that poses so much risk
to the belt, to the conveyor, or to plant
personnel that the belt must be stopped
immediately. The problem might be a piece
of tramp iron or sharp lump of material
lodged into the structure where it could
slash the belt. Or it might be an overheating idler, smoldering material buildup,
or other condition that could lead to a
fire. The belt walkerand the rest of the
plants operating and maintenance crew
and management staffmust understand
that the essential mission is to ensure safety
and preserve the equipment, even at the
expense of an unscheduled outage.
What to Look For
It is extremely important that the individual performing the survey has a list of the
general components that should be checked
during every walking the belt conveyor
inspection. This guide can be used as a
checklist for the worker to complete the
inspection. (See Chapter 28: Maintenance for the
list of items to be considered and evaluated.)
The maintenance recommendations of
the manufacturer for various components
and subsystems (such as samplers, scales,
metal detectors, and magnets) should be
added to each plants specific checklist.
SITE SURVEY
Hand Offs
Unanticipated
Results
Training
Code Requirements
Access
Utilities
Hazards
Elevated Work
Confined Spaces
Waste Disposal
Facilities
Are there facilities (e.g., break room, toilets, shower facilities) for
project workers?
Weather
Will weather and time of day (e.g., system available only on second shift) affect the ability to complete the project?
Deliverables
Table 27.3
27
429
27
430
Unskilled or inexperienced contract laborers may not provide any benefit; they might
not know what to look for or what they
are seeing. More experience will cost more
but provide a real benefit. A basic understanding of conveyors operating in similar
industries is helpful. It is important that the
expertise be found in the individual(s) who
will actually perform the work, and not
just in the person who sold the service. It
is better if the personnel already have the
skill setand the tool setto perform the
required service when noted, rather than
having to get permission and then go back
to perform it later.
These outside resources are, by definition, not employees of the operation. But
they will need to take ownership of the
conveyor system and of the plants efficient and productive use of that system.
They must demonstrate a dedication to the
operation and to their responsibilities and
duties. Wisely chosen and effectively used,
these outside personnel will improve the
conveyors and add value to the operation.
What to Do When the Walk is
Done
27
431
Looking Ahead
Figure 27.2
A regular walk of
the conveyor belt(s)
is an effective
way to assess the
system, catalog its
components, and
identify areas that
need service or that
offer opportunities for
improved efficiency.
27
432
References
27
433
Figure 28.1
No matter how wellengineered and
-constructed, conveyors
and their component
systems require timely
maintenance to keep
performance at design
levels.
Chapter 28
28 Maintenance
Maintenance Planning.. ................................................................................ 435
Personnel and Procedures.. .......................................................................... 436
Maintenance Schedules............................................................................... 438
Maintenance Matters.................................................................................. 438
Safety Concerns......................................................................................... 439
Advanced Topics......................................................................................... 442
The Dollars and Sense of Maintenance.. .......................................................... 442
434
Maintenance | Chapter 28
In this Chapter
28
28
Figure 28.2
Using contractors
for conveyance
installation and
maintenance allows
plant personnel to
be deployed on core
activities unique to
the operation.
436
Maintenance | Chapter 28
Routine maintenance inspections can extend belt- and component-life and improve
performance by keeping minor, easily corrected problems from turning into major
and costly headaches.
In some of the best operations, maintenance workers routinely walk the conveyor system, looking for indications of
potential trouble (Figure 28.3). (See Chapter
27: Conveyor System Survey). It is important
that the conveyor walker be unencumberedso the surveyor can be safe and
efficient during the inspection tour.
437
28
Conveyor service intervals and the specific service requirements for a conveyor will
depend both on its construction and components and on the volume and nature of
materials moving over it. The manufacturers guidelines for inspection, maintenance,
and repairs should be followed. However,
if there are no published guidelines, some
basic rules to help guide or establish a service schedule are given (Table 28.1). Many
conveyor components can and should be
inspected while the belt is in operation.
Care should be taken to only inspect the
conveyor components while the belt is in
operation, rather than to actually attempt
to service them. If items are discovered that
are in need of maintenance, these items
should be documented. Many maintenance
activities can be performed only when the
conveyor is not in operation. (For additional
maintenance information, see Martin Engineerings
website [Reference 28.1].)
28
MAINTENANCE MATTERS
Manuals
438
Maintenance | Chapter 28
Spare Parts
Conveyor inspection
and maintenance can pose
significant risks to employees, because
these activities bring the workers into
close proximity to the conveyor system
under potentially dangerous conditions
(Figure 28.4). There are many systems
designed to provide safe conditions for
both personnel and equipment. The best
approach to safety is a safety program
that develops and maintains a healthy
respect by engineers, operations personnel, and maintenance staff for the power
of the conveyor and the potential risks of
its operation.
Some adjustments can be made only
with the belt running, and it is advantageous to perform some routine maintenance while the belt is in operation. Most
safety regulations recognize this need and
provide that only trained personnel who
are aware of the hazards may perform
these routines. There are systems designed to provide safe conditions for both
personnel and equipment when inspection and maintenance follow established
procedures. Training for these procedures
is usually available from suppliers of the
systems. It is important that only competent, well-trained personnel, equipped
with proper test equipment and tools,
perform conveyor maintenance. (A thorough review of Chapter 2: Safety and Chapter
28: Conveyor System Survey is essential.)
28
Figure 28.4
Conveyor inspection
and maintenance
can pose significant
risks to employees,
because these
activities bring the
worker into close
proximity to the
conveyor system
under potentially
dangerous
conditions.
439
SAFETY CONCERNS
Always inspect work area for hazards prior to
commencement of inspections or performing work.
LOCATION
Bend Pulleys
PROCEDURE: Weekly
Ensure belt is centered on pulley
LOCATION
Head Pulley
Loading Zone
Safety
Switches
Snub Pulley
28
Gravity TakeUp
Splices
Tail Pulley
Guards
Conveyor
Structure
Conveyor
Belting
PROCEDURE: Weekly
Always inspect work area and review job procedure for hazards prior to commencement of inspection or performing work.
Review local and company safety requirements before conducting any maintenance activities. Some facilities may allow certain specified inspection and/or maintenance activities to be performed on moving conveyors by appropriately-certified and
-trained technicians. For those procedures that cannot be safely performed while the belt is in operation and/or those facilities
that do not allow maintenance while the belt is in operation, Lockout / Tagout / Blockout / Testout procedures must be followed prior to performing any work.
440
Maintenance | Chapter 28
SAFETY CONCERNS
Always inspect work area for hazards prior to
commencement of inspections or performing work.
LOCATION
Bend Pulleys
PROCEDURE: Monthly
Check bushings for evidence of
movement on shaft
Check bearing condition and locking
collars for tightness
LOCATION
Gravity TakeUp
Snub Pulley
Safety Horns
Safety
Switches
Tracking
Idlers
LOCATIONS
Brakes/
Backstops
Conveyor
Structure
Loading Zone
Safety
Switches
Warning
Devices/Signs
PROCEDURE: Monthly
LOCATION
PROCEDURE: Yearly
Electrical
System
Check for open wiring, damaged conduit, overloading and system grounds
Interlocks
Safety
Switches
LOCATION
Splices
PROCEDURE: Special
Circumstances
After new splice: Check for crooked
splice*
441
28
28
ADVANCED TOPICS
The Cost of Unscheduled
Shutdowns
Conveyors are often the lifeline of an operation, and the availability (or uptime) of
these systems has a direct impact on profitability. In many operations, lost production
attributed to conveyor downtime results in
a lost opportunity that cannot be recovered.
442
While the relationship between conveyor availability and profits is obvious, the
relationships among effective maintenance,
component quality, and the fundamental
conveyor design assumptions are not so
obvious. Because the effects of these conditions and practices are hard to identify, the
root causes of conveyor downtime often
are not addressed, leading to conveyors
with chronic problems. Research published
by the Australian Coal Association indicates that when the root cause of conveyor
downtime is related to component quality,
the cost of downtime is on the order of five
times the cost of replacing the component.
When the root cause of downtime is related
to the basic conveyor design, the downtime
cost is approximately two times the cost of
the redesign (Reference 28.2). At first these
ratios may seem to be incorrect, or even
backward, but consider that a component
failure often involves maintenance with a
relatively short downtime window for replacement, whereas a basic design mistake
often involves a significant capital expense
and a prolonged outage for correction.
Each situation is different, but it is clear
that treating the symptom rather than the
root cause results in repetitive downtime
costs. With cost of downtime established
at two to five times the cost of the corrective action, it is clear that keeping accurate
records and performing a thorough analysis of the problem can justify almost any
needed corrective action.
When calculating the cost of downtime,
common expenses to include are:
A. Lost opportunity cost
B. Purchase cost for replacement components
C. Maintenance labor cost
D. Subcontractor cost
E. Consulting and engineering fees
F. Testing and analysis costs
The opportunity cost can be calculated
by multiplying the production rate per hour
and number of hours of downtime by the
Maintenance | Chapter 28
selling price of the product. Since conveyors can transport large quantities per hour,
this cost adds up quickly. For example, a
coal mine that produces 4000 tons per
hour, that it sells for $50 USD per ton, loses
the opportunity to sell $200,000 USD of
coal for every hour of unscheduled downtime. One must add to that the expense for
outside services, replacement components,
and the total cost of downtime for the overall cost for that incident.
Using this lost opportunity cost is a good
way to capture an operations direct and
indirect costs, because included in the selling price are all the costs of production,
management, and administration, as well
as the profits. While it can be argued that
the coal that was not mined can be sold at a
later date, this may or may not be the case,
depending on the market and the mines
contract with the customer. In any event,
the cash flow for that downtime period has
been lost.
THE DOLLARS AND SENSE OF
MAINTENANCE
Unscheduled shutdowns are very expensive. One author listed the cost for service
to be three to seven times more in an emergency shutdown than during scheduled
downtime. In 2002, another source calculates downtime costs in longwall coal mines
at $30,000 USD per hour. Depending on
the plants size, a one-percent difference in
system availability for a coal-fired power
plant could be worth one to two million US
dollars in annual revenue. An unscheduled
conveyor outage or failure that decreases
generating availability even one-tenth of
one percent is a significant cost. The cost
of even the shortest unscheduled outage
is prohibitive. Obviously, maintenance to
prevent unscheduled downtime is a critical
factor in the operations overall profitability.
Looking Ahead
In Closing
References
Efficient and effective maintenance lowers costs, not just for the maintenance department, but for the total operation. The
goal is to provide quality work with minimal disruption to the production routine.
This will produce benefits in operating efficiency, system availability, and, ultimately,
the bottom line.
28
443
Figure 29.1
The personnel who
operate and manage
a material-handling
system are a key to its
success.
Chapter 29
The Human
29 Factor
Limitations of Hardware............................................................................... 445
Process for Continuous Improvement.. ............................................................ 446
Education and Training.. ............................................................................... 446
Importance of Service................................................................................. 447
Consulting with Experts.. .............................................................................. 447
Developing Partnerships with Suppliers........................................................... 448
For Total Material Control.. ........................................................................... 450
444
In this Chapter
the work environment can create fugitivematerial fatigue. Over time, those who
work in this environment every day accept
the conditions, and they simply no longer
see the conditions as a problem. Even when
some improvements are implemented, the
results quickly become accepted as the
norm. Without a process for continuous
improvement, the earlier upgrades will
soon become accepted as the best that can
be achieved.
To make truly beneficial and long-lasting
improvements in the performance of hardware systems, it is critical that the attitude
and actions of plant personnel, at all levels,
be transformed into a desire to improve
continuously. Plant personnel who expect
higher performance standards, take the
steps required to achieve these levels, and
commit to maintaining even higher standards will see improvements in efficiency,
working conditions, and safety.
The improved hardware systems for material containment and dust management
described in this book are important steps
in achieving total material control. However, it is the human factor that will provide
the ultimate key to success.
Limitations of Hardware
29
445
29
446
Commitment to Improvement
A key aspect of the process for continuous improvement is the training of personnel. Employees need to be trained to fully
understand the purpose and capabilities
of the equipment they will operate, while
developing a level of comfort and confidence in their own abilities. This education
should include how to identify challenges,
how to troubleshoot, and how to take corrective action by adjusting equipment to
correct and minimize problems.
29
447
29
Figure 29.3
By making an
important contribution
to a plants success,
suppliers move from
vendors to partners.
448
In order to accomplish its goals for process improvements in any area, especially
in material handling, the plant must take
advantage of the knowledge base available
from qualified key suppliers (Figure 29.3).
29
449
References
In Closing
There are many new and proven technologies and upgraded hardware solutions
discussed in this edition. They range from
engineered flow chutes to improved beltcleaning systems, all aimed at achieving
total material control. However, the single
key ingredient to success in containing
spillage and controlling dust is the people
those who operate and maintain the conveyors and the rest of the plant. It is, and
always will be, the human factor that will
ultimately determine a material-handling
systems success or failure.
Looking Ahead
This chapter, The Human Factor, concludes the section Conveyor Maintenance,
in which we discussed various aspects of
maintenance required to reduce fugitive
materials and extend the life of the conveyor system. The following chapter begins the
section The Big Picture of Bulk-Materials
Handling, starting with the chapter that
will focus on Total Project Management.
29
450
29
451