BR-1884
Advanced Ultra-Supercritical
Power Plant (700 to 760C)
Design for Indian Coal
Authors:
P.S. Weitzel, PE
J.M. Tanzosh
B. Boring
Babcock & Wilcox
Power Generation Group, Inc.
Barberton, Ohio, U.S.A.
N. Okita
T. Takahashi
N. Ishikawa
Toshiba Corporation
Tokyo, Japan
Presented to:
Power-Gen Asia
Date:
October 3-5, 2012
Location:
Bangkok, Thailand
Abstract
The advanced ultra-supercritical (A-USC) power plant
operating with steam temperatures at 700 to 760C (1292 to
1400F) will require nickel-based alloy materials in the steam
generator, critical steam piping and steam turbine. Nickelbased alloy development from the United States (U.S.)
Advanced Materials Research Program will be presented,
as well as issues related to component materials selection
for an Indian coal. Babcock & Wilcox Power Generation
Group, Inc. (B&W PGG) is developing an A-USC plant for
700C steam conditions in collaboration with turbine designer
and manufacturer, Toshiba Corporation (Toshiba). The plant
layout to accommodate the new equipment at the lowest
cost will need to consider new configuration arrangements.
The operability and maintainability is a major consideration
affecting arrangement. The steam generator design arrangement, plant layout and control methods will be described.
Operation at 700C provides an efficiency improvement to
reduce carbon dioxide (CO2) emissions and reduces coal infrastructure demands, some of the primary goals for A-USC
steam conditions. A cost comparison between conventional
power plant design and conditions, and those of an A-USC
plant, is included.
Introduction
A power industry goal is to reduce CO2 emissions from
coal-fired electric generating plants with improved thermal
efficiency by increasing steam temperatures to +700C. Costs
for carbon capture would be lower due to less CO2. There
Babcock & Wilcox Power Generation Group
N. Okita
T. Takahashi
N. Ishikawa
Toshiba Corporation
Tokyo, Japan
BR-1884
Welding development
The DOE/OCDO Boiler Materials Program, has developed the necessary welding procedure and weldment
property data for several new alloys. Dissimilar alloy welds
for many tubing combinations were performed and tested.
For thicker sections representing pipe and headers, large
plates and pipes have been welded and procedures qualified
in thicknesses never previously needed for boiler service.
Nickel alloy plates of 617, 230 and the new INCO 740 material for boilers were the selected candidates. Nickel alloy
282 has been more recently included in the program and
work is in progress to gain experience and develop welding
procedures for ASME Code acceptance.
Materials selection
The materials shown in Table 1 are available for application in steam generators designed to ASME Section I, except
for Haynes 282 which is being prepared for submittal of a
code case. Alloy 740H was approved in Code Case 2702.
For current design studies, the materials chosen are carbon
steel, T12, T22, T92, 347HFG and 740H. Nickel alloys
617 and 230 are also candidates, but have lower allowable
stress properties than 740H. For economic reasons, 740H
presently has the advantage for tube and pipe selection where
lower weight will be required. This material has the highest
strength, as well as very good steam side and fireside corrosion resistance, at a price per weight comparable to the
other candidate alloys.
The allowable stress values for materials listed in Table
1 are graphically depicted in Figure 2.
Carbon steel
T12
1Cr-0.5Mo
Water walls
T22
2.25Cr-1Mo
Water walls, RH
T23
2.25Cr-1.6W-VNb
Water walls, RH
T91
9Cr-1Mo-V
Water walls, RH
T92
9Cr-2W
347 HFG
18Cr-10Ni-Nb
SH, RH
310 HCbN
25Cr-20Ni-Nb-N
SH, RH
Super 304H
18Cr-9Ni-3CuNb-N
617
55Ni-22Cr-9Mo12Co-Al-Ti
230
57Ni-22Cr-14W2Mo-La
740H
50Ni-25Cr-20Co2Ti-2Nb-V-Al
282
58Ni-10Cr-8.5Mo2.1Ti-1.5Al
Piping, headers
Turbine materials
Table 2 shows candidate materials for application in
high temperature turbine components designed by Toshiba.
For current A-USC turbine design studies, it is necessary
to apply nickel-based alloys for rotor forging materials.
Nickel-based alloys for rotors are required for high creep
strength at elevated temperatures. (See Table 3.) The ability
to forge and weld are also important issues for large rotor
production. The castings of a steam turbine are large structures with complex shapes that must provide the pressure
containment for the steam turbine. The major requirement
for casing materials is the ability to cast them into the
required size and shape through the air casting process.
Weldability is also an important issue for pipe connecting
Table 2
Properties
Candidate Materials
Rotor
TOS1X
TOS1X-II
Casing
Alloy625
TOS3X
etc.
Valve chest
Alloy625
TOS3X
etc.
Table 3
Ni
Cr
Al
Ti
Mo
Co
Ta
Nb
Alloy 617
Bal.
0.05 ~
0.15
20.0 ~
24.0
0.8 ~ 1.5
<0.6
8.0 ~ 10.0
10.0 ~
15.0
--
--
TOS1X
TOS1X-II
Bal.
0.05
23
1.6
0.3
12.5
0.1
0.3
Bal.
0.07
18
1.25
1.35
12.5
0.1
0.3
Performance
A comparison of the technical operating parameters between 600C USC and 700C A-USC is summarized in Table
4. Thermal efficiency is improved by 6% with 700C A-USC
steam conditions.
Steam turbine generator consists of one single flow HP
turbine, one double flow IP turbine, one double flow LP turbine, and one generator in a tandem arrangement. (See Figure
8.) The overall length of the turbine-generator is 42 m. The
LP turbine is downward exhaust. The turbine is rated at 840
MW gross with steam inlet conditions of 30 MPa and 700C,
reheat to 730C. The rated speed is 3000 rpm.
Main steam from the boiler flows through the four main
stop valves and four control valves and enters the HP turbine.
It expands through the HP turbine and exhausts as cold reheat
to the boiler. Hot reheat steam from the boiler flows through
the four reheat stop valves and four intercept valves and
enter the IP turbine. It expands through the IP turbine and
then enters the crossover piping, which transports the steam
to the LP turbine. The steam expands through the LP turbine
and exhausts into the condenser. The steam turbine is oper-
Table 4
Operating Parameters for 600C USC and 700C A-USC Turbine Arrangement
General output
Main steam (pressure and temp.)
Reheat steam (pressure and temp.)
Condenser pressure
Boiler feedwater temp.
Thermal efficiency
600C USC
700C A-USC
840 MW
840 MW
30 MPa, 700C
683 mm Hg vac.
292C
Base
683 mm Hg vac.
330C
6% improvement
Steam turbine
Tandem-compound
(three casings)
Single flow
Double flow
Double flow
Rated speed
3000 rpm
MSV/CV
CRV
Overload valve
Feedwater pumps
Heater
4 valves
De-superheater
4 valves
1 valve
Electrically driven
1 or 2
HP heater
4 heaters
Deaerator
1 deaerator
LP heater
4 heaters
Generator
Number of poles
Power factor
0.85
Rated output
1005000 kVA
Cooling
Babcock & Wilcox Power Generation Group
Conclusion
A primary need in A-USC development is to confirm the
capability of suppliers to support the new materials required
and to meet the schedule demands so plant projects may be
initiated. Suppliers will need to make investments based on
increased certainty of the timing when the A-USC market
demand will form. First generation demonstration plants are
needed to establish a working understanding of the necessary
relationships and put into practice the procurement standards
for A-USC components.
The value of owning an A-USC power plant will be
determined by the balance of lifecycle cost saving of the
impact to resource demands and infrastructure requirements
with the increased capital cost of using nickel-based alloys.
Water
7
References
1. Topper, J., Status of Coal Fired Power Plants WorldWide, IEA, www.iea-coal.org.
2. Bennett, A.J., Weitzel P.S., Boiler Materials for Ultrasupercritical Coal Power Plants Task 1B, Conceptual Design, Babcock & Wilcox Approach, USC T-3,
Topical Report, DOE DE-FG26-01NT41175 & OCDO
D-0020, February 2003.
3. Booras, G., Task 1 C, Economic Analysis, Boiler
Materials for Ultra-supercritical Coal Power Plants,
DOE Grant DE-FG26-01NT41175, OCDO Grant
D-00-20, Topical Report USC T-1, February 2003.
4. Viswanathan, R., Shingledecker, J., Phillips, J., In
Pursuit of Efficiency in Coal Power Plants, (ed. Sakrestad, BA) 35th International Technical Conference on
Clean Coal and Fuel Systems 2010, Clearwater, FL,
June 2010.
5. Duffy, T., et.al., Advanced High Performance Steam
Systems for Industrial Cogeneration, Final Report
on DOE Contract No. AC02-85CE40746, DOE/
CE/40746-TI (1987)
6. Weitzel, P.S., Steam Generator for Advanced UltraSupercritical Power Plants 700 to 760C, ASME
Power 2011, Denver, CO (2011).
7. Rao, K.R., (ed.), Energy and Power Generation Handbook, ASME, New York, 2011.
8. Kitto, JB, Stultz, SC., Steam/its generation and use,
Edition 41, The Babcock & Wilcox Company, Barberton, OH 2005.
9. Silvestri, G.J., Eddystone Station, 325 MW Generating Unit 1-A Brief History, ASME, March 2003.
10. Silvestri, G.J., et.al., Optimization of Advanced
Steam Condition Power Plants, Diaz-Tous, I.A., (ed.),
Steam Turbines in Power Generation PWR-Vol. 3,
Book No. H00442, ASME, 1992.
Benson is a registered trademark of Siemens AG.
Disclaimer
Although the information presented in this work is believed to be reliable, this work is published with the
understanding that Babcock & Wilcox Power Generation Group, Inc. (B&W PGG) and the authors are supplying
general information and are not attempting to render or provide engineering or professional services. Neither
B&W PGG nor any of its employees make any warranty, guarantee, or representation, whether expressed or
implied, with respect to the accuracy, completeness or usefulness of any information, product, process or apparatus discussed in this work; and neither B&W PGG nor any of its employees shall be liable for any losses or
damages with respect to or resulting from the use of, or the inability to use, any information, product, process
or apparatus discussed in this work.
8