Anda di halaman 1dari 9

Technical Paper

BR-1884

Advanced Ultra-Supercritical
Power Plant (700 to 760C)
Design for Indian Coal

Authors:
P.S. Weitzel, PE
J.M. Tanzosh
B. Boring
Babcock & Wilcox
Power Generation Group, Inc.
Barberton, Ohio, U.S.A.
N. Okita
T. Takahashi
N. Ishikawa
Toshiba Corporation
Tokyo, Japan
Presented to:
Power-Gen Asia
Date:
October 3-5, 2012
Location:
Bangkok, Thailand

Advanced Ultra-Supercritical Power Plant (700 to 760C)


Design for Indian Coal
P.S. Weitzel
J.M. Tanzosh
B. Boring
Babcock & Wilcox
Power Generation Group, Inc.
Barberton, Ohio, USA
Presented at:
Power-Gen Asia
Bangkok, Thailand
October 3-5, 2012

Abstract
The advanced ultra-supercritical (A-USC) power plant
operating with steam temperatures at 700 to 760C (1292 to
1400F) will require nickel-based alloy materials in the steam
generator, critical steam piping and steam turbine. Nickelbased alloy development from the United States (U.S.)
Advanced Materials Research Program will be presented,
as well as issues related to component materials selection
for an Indian coal. Babcock & Wilcox Power Generation
Group, Inc. (B&W PGG) is developing an A-USC plant for
700C steam conditions in collaboration with turbine designer
and manufacturer, Toshiba Corporation (Toshiba). The plant
layout to accommodate the new equipment at the lowest
cost will need to consider new configuration arrangements.
The operability and maintainability is a major consideration
affecting arrangement. The steam generator design arrangement, plant layout and control methods will be described.
Operation at 700C provides an efficiency improvement to
reduce carbon dioxide (CO2) emissions and reduces coal infrastructure demands, some of the primary goals for A-USC
steam conditions. A cost comparison between conventional
power plant design and conditions, and those of an A-USC
plant, is included.

Introduction
A power industry goal is to reduce CO2 emissions from
coal-fired electric generating plants with improved thermal
efficiency by increasing steam temperatures to +700C. Costs
for carbon capture would be lower due to less CO2. There
Babcock & Wilcox Power Generation Group

N. Okita
T. Takahashi
N. Ishikawa
Toshiba Corporation
Tokyo, Japan
BR-1884

will be an increase in generating capital due to the required


use of nickel alloys. The means to limit the cost increase
is the reduction in equipment size per MW, less resources
consumed, less impact to infrastructure demands, and the
lower cost of emission control. Improving the utilization of
abundant and affordable coal is being undertaken worldwide
by organizations through materials development programs.
A plant operating at 700C/730C plant compares favorably
with the current state-of-the-art steam generating plant
operating at 600C/610C by requiring approximately 11%
less coal and producing 11% less CO2 to generate the same
power output.
Considerable progress has been made in the development of new alloy materials needed for an advanced ultrasupercritical +700C plant. Boiler materials development
programs to address needs and qualification by design
codes have been underway for more than 10 years in Europe
(Thermie AD700) and the United States [U.S. Department
of Energy/Ohio Coal Development Office (DOE/OCDO)].
The METI Cool Earth program in Japan started in 2008 [1].
Laboratory, pilot-scale and in situ boiler component tests
have been performed on various materials. Programs in
Europe, the U.S., and Japan are intended to further develop
materials understanding and carefully put the technology
into practice [2, 3, 4].
Some of the newly developed nickel alloy products
(740H, 282) offer better performance and will need to undergo tests on larger diameter pipes in service conditions.
Planning for these component tests, along with other needed
parts and accessories, has begun. Another previous program
1

to note is the High Performance Steam System (HPSS)


sponsored by the U.S. Department of Energy (U.S. DOE) in
the mid-1990s and conducted by Solar Turbines to develop
a 1500F/1500 psig steam turbine for cogeneration. A 4 MW
steam turbine, throttle control valve, and once-through steam
generator was constructed and operated at full temperature
conditions [5]. By making an assessment of the previous
A-USC component testing already conducted, and then
completing the further testing of newer component materials, the industry and future owner-operators will be able to
reduce the risks for proceeding to the prototype plant phase.
The next step to take is the planning, design, fabrication,
construction and operation of the lead prototype +700C demonstration plants. Demonstrating the commercial viability
and success in meeting the value required in the market place
is the next milestone. Proving the capability of the supply
chain, actually performing the plant installation, and placing
the equipment in the control of the personnel that operate
and perform maintenance will demonstrate whether or not
the risks are acceptable to the industry.
The designs for A-USC boilers started with the currently
acceptable configurations which are two-pass or tower style
arrangements [6, 7]. The earliest proposed designs have been
employed for about the last half century. An important need
is the recognition to carefully consider the arrangement of
the steam generator and the location in the plant arrangement
relative to the steam turbine because of the need to use high
cost nickel alloy steam leads. The steam generator steam
outlets would be moved closer to the steam turbine inlets
by physical repositioning or by using non-conventional arrangements. There have been designs proposed to arrange
the boiler to have horizontal gas flow or to put part of the
steam turbine up near the top of the steam generator close
to the superheater outlet to shorten the high energy steam
piping. Traditionally, the power industry is very conservative and reluctant to accept radical changes to designs and
procedures before adequate testing and demonstrations are
conducted to prove the economics and technical benefits.
However, there appears to be some recognition in the power
generation community of the need for a new arrangement
paradigm. There are earlier steam generator design arrangements that employ some of these proposed features.

MPa, 649C, 565C, 565C ) in 1959 can provide valuable


lessons in meeting challenges [8, 9]. The low height of the
Philo 6 steam generator should be noted as it provides an
example of a configuration that is extremely different than
currently accepted boiler configurations, and has the feature
of reducing the length of steam lead run to the steam turbine.
See Figure 1.
B&W PGG is a member in the consortium for the U.S.
DOE/OCDO Materials Development Program for A-USC
along with other suppliers and research organizations. The
major aspects of this program are to perform work tasks in:
conceptual design and economic analysis, mechanical properties, steam side oxidation, fireside corrosion, weldability,
ease of fabrication, coatings, and design data and rules.
As an example, the program developed a new formula for
calculating material thickness, Appendix A-317, adopted by
Section I of the American Society of Mechanical Engineers
(ASME) code, and the code case acceptance of alloy INCO
740 nickel for pipe and tube in the ASME I Code. This and
other new materials allow for improved design performance
of a +700C steam generator [6]. There is also a DOE/OCDO
program associated with the development of steam turbine
materials with participation of major turbine suppliers.

Welding development
The DOE/OCDO Boiler Materials Program, has developed the necessary welding procedure and weldment
property data for several new alloys. Dissimilar alloy welds
for many tubing combinations were performed and tested.
For thicker sections representing pipe and headers, large
plates and pipes have been welded and procedures qualified
in thicknesses never previously needed for boiler service.
Nickel alloy plates of 617, 230 and the new INCO 740 material for boilers were the selected candidates. Nickel alloy
282 has been more recently included in the program and
work is in progress to gain experience and develop welding
procedures for ASME Code acceptance.

Steam generator materials development


The advancement to 700C steam temperatures for coal
firing represents an increase of 166C (300F) above the average predominant operating experience. The current stateof-the-art plant uses 600C (1112F) technology, which is not
widely applied so that vast industry experience is lacking
or limited in the knowledge base. The introduction of the
700C technology has to overcome the reluctance to adopt
A-USC plants by conducting development programs that test
and demonstrate that the risk is acceptable for a very capital
intensive industry. Pioneering technology introductions such
as American Electric Power Philo 6 (31MPa, 621C, 565C,
538C) in 1957, and Philadelphia Electric Eddystone 1 (34.5
2

Fig. 1 AEP Philo 6 universal pressure steam generator,


B&W Contract UP-1.
Babcock & Wilcox Power Generation Group

Materials selection
The materials shown in Table 1 are available for application in steam generators designed to ASME Section I, except
for Haynes 282 which is being prepared for submittal of a
code case. Alloy 740H was approved in Code Case 2702.
For current design studies, the materials chosen are carbon
steel, T12, T22, T92, 347HFG and 740H. Nickel alloys
617 and 230 are also candidates, but have lower allowable
stress properties than 740H. For economic reasons, 740H
presently has the advantage for tube and pipe selection where
lower weight will be required. This material has the highest
strength, as well as very good steam side and fireside corrosion resistance, at a price per weight comparable to the
other candidate alloys.
The allowable stress values for materials listed in Table
1 are graphically depicted in Figure 2.

Steam generator configuration


New boiler arrangements have been proposed that primarily change the steam lead terminal point on the steam
generator. There has been some consideration for placing the
boiler partially in the ground and/or raising the steam turbine
pedestal. Some have considered dividing the turbine; for example, the high pressure (HP) and intermediate pressure (IP)
sections could be located at the higher elevation and the low
pressure (LP) section could be located at the conventional
pedestal condenser location. One designer has proposed a
boiler design that lays the boiler down with a horizontal gas
flow and the steam turbine immediately at the side.
Table 1

Materials Selection for Steam Generator Components


Composition
Alloy
Application
(Nominal)
210C, 106C

Carbon steel

Econ, piping, headers

T12

1Cr-0.5Mo

Water walls

T22

2.25Cr-1Mo

Water walls, RH

T23

2.25Cr-1.6W-VNb

Water walls, RH

T91

9Cr-1Mo-V

Water walls, RH

T92

9Cr-2W

Water walls, RH, piping

347 HFG

18Cr-10Ni-Nb

SH, RH

310 HCbN

25Cr-20Ni-Nb-N

SH, RH

Super 304H

18Cr-9Ni-3CuNb-N

SH, RH, piping, headers

617

55Ni-22Cr-9Mo12Co-Al-Ti

SH, RH, piping, headers

230

57Ni-22Cr-14W2Mo-La

SH, RH, piping, headers

740H

50Ni-25Cr-20Co2Ti-2Nb-V-Al

SH, RH, piping, headers

282

58Ni-10Cr-8.5Mo2.1Ti-1.5Al

Piping, headers

Babcock & Wilcox Power Generation Group

Fig. 2 Expected material ASME I Code allowable stress.

For U.S. coals the B&W PGG design arrangement for


the conventional 600C boiler is a two-pass type (Carolina)
with parallel gas path biasing for reheat steam temperature
control, shown in Figure 3. The two-pass boiler is considered
to have the following advantages:
1. shorter steel structure than a tower design,
2. time savings of parallel construction sequence,
3. less complicated high temperature tube sections support,
4. more economical to erect, and
5. less sootblowing required to clean the pendant surfaces
than high temperature horizontal surfaces in the tower
design.
The tower design is considered to have the following
advantages:
1. better gas flow distribution resulting in lower tube
metal upset temperatures,
2. wider tube spacing allowing high fuel ash removal to
a single furnace hopper,
3. more drainable heating surface,
4. steam lead outlets positioned closer to the steam
turbine,
5. increased ability to handle internal oxidation exfoliation with distribution along the tubes, and
6. ability to successfully fire high fouling brown lignite.
The modified tower combines features of both designs:
the structure is shorter than the standard tower design, and
steam leads are shorter and nearer to the steam turbine.
B&W PGG is also developing a modified tower for AUSC (a folded tower similar to the two-pass style with
horizontal tube banks) and parallel gas path biasing in the
downpass. This arrangement is not new to the industry. For
an A-USC boiler using Indian coal, the modified tower with
gas recirculation (GR) is used in a series back pass arrangement because the gas velocity limits are very low due to
the very high ash content in the Indian coal and the heating
surface area becomes larger and less effective without GR.
(See Figure 4.) To achieve a wider range of reheat (RH)
temperature control turndown, gas bias with a parallel pass
and GR might also be included. RH control priority in this
design would be to position the biasing dampers and then
complement with gas recirculation flow.
3

Fig. 3 Conceptual design of a two-pass (Carolina) A-USC


boiler using U.S. coal.

Design of a steam generator using indian coal


Indian coals that are widely used for new power projects
in India are generally low sulfur content and have a reduced
likelihood of fireside corrosion problems. U.S. western coals
from the Powder River Basin (PRB) are similarly low in
sulfur and have fared much better regarding coal ash corrosion testing. Low sulfur U.S. coals are preferred in the fuels
selection for A-USC applications by providing lower risk to
fireside corrosion. Low sulfur Indian coals are expected to
have this same lower risk for fireside corrosion.
However, the ash content of Indian coals is very high
and the silica/quartz content is very high, thus very erosive,
requiring much lower gas velocities passing through the
convection tube banks, about 50% less than a higher grade
U.S. coal. Special erosion protection provisions are also required on the pulverizers and boiler components. The impact
to the design arrangement and cost is significant. The size
of the gas flow area increases about 50% and the amount of
heating surface increases due to lower heat transfer rates.
Compared to a boiler using U.S. eastern bituminous coal,
the furnace of a boiler using Indian coal is about 78% larger
in volume and about 50% taller. Lower furnace exit gas
temperatures are specified. The furnace width is about 38%
more, impacting the length of the nickel alloy superheater/
reheater outlet headers. Furnace wall average absorption
rates are lower while the peak rates will be expected to be
nearly the same. Staged firing for nitrogen oxides (NOx)
reduction may be required at some plants. The lower furnace
walls may be fabricated starting with lower chrome steel,
T12, and T22 for the middle water walls. The A-USC upper
water walls of the furnace will operate at about 55C (100F)
higher temperature than current practice and thereby require
different material. At this higher temperature T92 tubing
is preferred for wall construction and brings new welding
procedures to the furnace erection requirements. B&W PGG
4

has been performing R&D on T92 panel fabrication, erection


and repair procedures [6].
Convection heating surface is arranged sequentially as
follows: 1) from the furnace exit plane with the primary
superheater platen, 2) three superheater banks in parallel gas
flow, 3) reheat outlet banks in parallel/counter flow, 4) over
the pendant crossover with the pendant reheat inlet bank,
5) primary superheater banks interlaced with the horizontal
reheat banks, and 6) economizer banks.
A vertical or spiral tube furnace enclosure may be used
based on the steam flow to perimeter ratio. With Indian
coal and its larger furnace perimeter requirement, a spiral
design is used. The heating surface arrangement and steam
temperature control method will need to result in component
operating temperatures that change very little versus load,
refer to reference [6]. It is desirable not to have large magnitude changes in the material temperature of thick components
like the superheater and reheater outlet headers. Rapid cyclic
temperature changes will cause fatigue damage and reduce
component life. The vertical steam separator (VS) is a thick
wall component that must be located in the steam generator
flow sequence considering the cyclic temperature changes
of start up and load changing. The location will also impact
the Benson point load where the steam generator will begin
to operate in once-through mode.

Fig. 4 Conceptual design of an 840 MW modified tower


A-USC.
Babcock & Wilcox Power Generation Group

A-USC steam generator control and


operation
The B&W PGG A-USC plant design operates at full load
above critical pressure 22.1 MPa (3208 psia) and on a variable pressure ramp at lower load so it is capable of permitting
appropriately located dryout to occur when the furnace is in
the subcritical pressure two-phase region.
Control must handle the transition from the minimum
circulation flow recirculating mode for initial firing using the
boiler circulation pump to the once-through mode where all
the water entering the economizer leaves from the superheater outlet. Control of the equipment must achieve cold startup,
warm restarts, hot restarts, load cycling and shutdown. The
load where the vertical steam separator runs dry is called the
Benson point. For A-USC, this is estimated to be at about
45% load. At this dry separator point, the boiler circulation
pump is shut off and the boiler feed pump is controlled so
the feedwater flow will meet the demanded furnace enthalpy
pickup function (from the economizer outlet to the primary
superheater inlet) in once-through operation. Final steam
temperature control range meets set point from about 50 to
100% load. Reheat steam temperature control range meets
set point from about 60 to 100% load.
Steam temperature is controlled by multiple stages of
spray attemperation. The steam temperature control for
faster transients must account for the time delay of the water entering the economizer to leave the superheater outlet,
which takes about 15 minutes at minimum circulation flow
load, and about 3 minutes at maximum continuous rating
(MCR) load.

A-USC turbine conditions


The OCDO/DOE study conditions at the boiler terminals
are: 792 MW gross; 34.6 MPa (5015 psia) throttle and 36.2
MPa (5250 psia) superheater; 735.6C (1356F) / 761C (1402);
333C (631F) feedwater; 508.4 kg/s (4,035,000 lb/hr) main
steam; and 389.2 kg/s (3,089,000 lb/hr) reheat. HP cooling
steam is 7.6 kg/s (60,318 lb/hr) at 566C (1050F) from the
primary superheater outlet. Since this study began (in 2002),
the throttle pressure has not been changed, although a lower
pressure is now considered very likely. Studies in the 1980s
and early 1990s used 44.8 MPa (6500 psi) [10]. The available energy with a given steam temperature reaches a flat
gradual optimum as a function of pressure so that the expense
of high design pressure will increase cost more rapidly than
the benefit to thermal efficiency.
In the current B&W PGG and Toshiba design study using
an Indian coal specification, the steam conditions are: 30 MPa
(4350 psia), 700C (1292F throttle / 730C (1346F) reheat,
330C (626F) feedwater, to produce 840 MW gross generation.

Fig. 5 Steam turbine welded rotor.

sure turbine rotor or intermediate pressure turbine rotor is


over 20 tons.
The materials and design for rotors are unique to each
manufacturer. Rotors for Toshibas A-USC design involve
welding nickel-based alloy and ferrite steel to minimize
use of expensive nickel-based alloy, and due to difficulties
in producing a large ingot for mono-block nickel-based
alloy rotors. As shown in Figure 5, the middle of the rotor
is nickel-based alloy, and the ends are ferrite steel. Actual
size weld trials are being conducted that test welding nickelbased alloy TOS1X-II to ferrite steel, and welding TOS1X-II
to TOS1X-II. The welds will be evaluated for mechanical
properties later this year.

Turbine materials
Table 2 shows candidate materials for application in
high temperature turbine components designed by Toshiba.
For current A-USC turbine design studies, it is necessary
to apply nickel-based alloys for rotor forging materials.
Nickel-based alloys for rotors are required for high creep
strength at elevated temperatures. (See Table 3.) The ability
to forge and weld are also important issues for large rotor
production. The castings of a steam turbine are large structures with complex shapes that must provide the pressure
containment for the steam turbine. The major requirement
for casing materials is the ability to cast them into the
required size and shape through the air casting process.
Weldability is also an important issue for pipe connecting
Table 2

Candidate Materials for High Temperature Turbine


Components
Components

Properties

Candidate Materials

Rotor

High creep strength


Good forge-ability
in the large size
Good weld-ability

TOS1X
TOS1X-II

Casing

High creep strength


Good cast-ability
in the large size
Good weld-ability

Alloy625
TOS3X
etc.

Valve chest

High creep strength


Good cast-ability
in the large size
Good weld-ability

Alloy625
TOS3X
etc.

Blade and bolt

High creep strength


Machine-ability

Alloys used in gas


turbines (U520,
IN738LC, etc.)

Turbine rotor welding development


The rotor is one of the largest components of the steam
turbine system. (See Figure 5.) The weight of a high presBabcock & Wilcox Power Generation Group

Table 3

Chemical Composition of Nickel-Based Alloys for Turbine Rotors

Ni

Cr

Al

Ti

Mo

Co

Ta

Nb

Alloy 617

Bal.

0.05 ~
0.15

20.0 ~
24.0

0.8 ~ 1.5

<0.6

8.0 ~ 10.0

10.0 ~
15.0

--

--

TOS1X
TOS1X-II

Bal.

0.05

23

1.6

0.3

12.5

0.1

0.3

Bal.

0.07

18

1.25

1.35

12.5

0.1

0.3

and repair welding. Blades and bolts will also be made of


nickel-based alloys.
Figure 6 shows the creep rupture strength of conventional
steels and nickel-based alloy for turbine rotor candidates.
TOS1X and TOS1X-II have higher creep strength than alloy 617. These materials have demonstrated good forging
and welding characteristics. For turbine casing and valve
chest, TOS3X provides potentially better creep strength
than alloy 625.

Steam turbine configuration


Figure 7 shows a conceptual drawing of Toshibas single
reheat steam turbine system of a 840 MW power plant with
30 MPa (4350 psi), 700C (1292F) for main steam, and 6
MPa (870 psi), 730C (1346F) for reheat steam. It consists
of a single flow HP turbine, a double flow IP turbine, and a
double flow LP turbine with 48 in. last stage blade length.
For the HP and IP turbines, nickel-based alloys are applied to those parts directly in contact with high temperature
steam. These include the inner casing, high temperature
rotor, nozzle box (first stage nozzle), and higher temperature nozzles and blades. The other parts are constructed of
conventional ferrite steel. Rotor designs require dissimilar
welding nickel-based alloys (TOS1X-II) and ferrite steels to
minimize the weight of expensive nickel-based alloys, and
due to difficulties in producing a large mono-block nickelbased alloy ingot. Conventional cast steel can be used for
the outer casing because high temperature steam is isolated
by cooling steam.
Materials and configuration for the LP turbine are similar
to that for the 600C class USC turbine.

Performance
A comparison of the technical operating parameters between 600C USC and 700C A-USC is summarized in Table
4. Thermal efficiency is improved by 6% with 700C A-USC
steam conditions.
Steam turbine generator consists of one single flow HP
turbine, one double flow IP turbine, one double flow LP turbine, and one generator in a tandem arrangement. (See Figure
8.) The overall length of the turbine-generator is 42 m. The
LP turbine is downward exhaust. The turbine is rated at 840
MW gross with steam inlet conditions of 30 MPa and 700C,
reheat to 730C. The rated speed is 3000 rpm.
Main steam from the boiler flows through the four main
stop valves and four control valves and enters the HP turbine.
It expands through the HP turbine and exhausts as cold reheat
to the boiler. Hot reheat steam from the boiler flows through
the four reheat stop valves and four intercept valves and
enter the IP turbine. It expands through the IP turbine and
then enters the crossover piping, which transports the steam
to the LP turbine. The steam expands through the LP turbine
and exhausts into the condenser. The steam turbine is oper-

Fig. 7 Conceptual drawing of an A-USC turbine (840 MW,


30 MPa, 700/730C).

Fig. 6 105 hour creep rupture strength of turbine rotor alloys.


6

Fig. 8 Plan view of A-USC turbine (840 MW, 30 MPa,


700/730C).
Babcock & Wilcox Power Generation Group

Table 4

Operating Parameters for 600C USC and 700C A-USC Turbine Arrangement

General output
Main steam (pressure and temp.)
Reheat steam (pressure and temp.)
Condenser pressure
Boiler feedwater temp.
Thermal efficiency

600C USC

700C A-USC

840 MW

840 MW

24.1 MPa, 600C

30 MPa, 700C

4.3 MPa, 600C

6.0 MPa, 730C

683 mm Hg vac.
292C
Base

683 mm Hg vac.
330C
6% improvement

ated in throttle governing, sliding pressure. Sliding pressure


improves the efficiency of partial load operation.
The turbine provides for nine feedwater extraction points.
Final feedwater temperature at full load is 330C with desuperheaters. The steam turbine exhaust pressure at design
conditions was selected based on typical Indian conditions at
the condenser. The electrical generator is rated at 1050 MVA,
50Hz with a power factor of 0.85.
Table 5 lists the turbine and major auxiliary equipment
design parameters.

A-USC steam generator and steam


turbine cost allowance with U.S. coal
In 2003 as part of the DOE/OCDO Boiler Materials Development project, the current U.S. two-pass steam generator
design arrangement was evaluated on the basis of economic
Table 5

Turbine and Major Auxiliary Equipment

Steam turbine

Tandem-compound
(three casings)

High pressure section

Single flow

Intermediate pressure section

Double flow

Low pressure section

Double flow

Rated speed

3000 rpm

MSV/CV
CRV
Overload valve
Feedwater pumps
Heater

4 valves

De-superheater

4 valves
1 valve
Electrically driven
1 or 2

HP heater

4 heaters

Deaerator

1 deaerator

LP heater

4 heaters

Generator
Number of poles

Power factor

0.85

Rated output

1005000 kVA

Cooling
Babcock & Wilcox Power Generation Group

viability.[2, 3] It was determined that with the improved heat


rate for the 750 MW net A-USC plant, the breakeven cost of
electricity was attainable when the capital cost was within
13% above the cost of a conventional subcritical plant. The
higher plant efficiency allowed cost reductions because of
the lower fuel cost per MW and smaller size of the equipment
for the steam generator and the boiler balance of plant (fuel
handling, emissions systems, fans and auxiliary power, etc.).
The steam generator cost would need to stay within 40%
above the cost of the steam generator of a subcritical plant.
The DOE/OCDO A-USC steam generator had 7% more
suspended weight than the conventional supercritical unit
while it was 20% narrower. The narrower arrangement
reduces the cost of the alloy headers and piping. There is a
13% weight increase of the overall tubing due to the lower
temperature difference of the flue gas to steam resulting in
lower heat transfer rates. The resulting cost estimate for
the A-USC steam generator was 28% above the subcritical
boiler and within the 40% allowance.
Nickel alloy tubing is estimated to cost 46 times the cost
of a T22 tubing. A current estimate is being developed to
adjust to a newer assessment of nickel alloy cost for the
steam leads between the boiler and steam turbine. The allowance for capital cost of the steam generator and steam
turbine is expected to require less than a 25% increase over
a subcritical plant.

Conclusion
A primary need in A-USC development is to confirm the
capability of suppliers to support the new materials required
and to meet the schedule demands so plant projects may be
initiated. Suppliers will need to make investments based on
increased certainty of the timing when the A-USC market
demand will form. First generation demonstration plants are
needed to establish a working understanding of the necessary
relationships and put into practice the procurement standards
for A-USC components.
The value of owning an A-USC power plant will be
determined by the balance of lifecycle cost saving of the
impact to resource demands and infrastructure requirements
with the increased capital cost of using nickel-based alloys.

Water
7

References
1. Topper, J., Status of Coal Fired Power Plants WorldWide, IEA, www.iea-coal.org.
2. Bennett, A.J., Weitzel P.S., Boiler Materials for Ultrasupercritical Coal Power Plants Task 1B, Conceptual Design, Babcock & Wilcox Approach, USC T-3,
Topical Report, DOE DE-FG26-01NT41175 & OCDO
D-0020, February 2003.
3. Booras, G., Task 1 C, Economic Analysis, Boiler
Materials for Ultra-supercritical Coal Power Plants,
DOE Grant DE-FG26-01NT41175, OCDO Grant
D-00-20, Topical Report USC T-1, February 2003.
4. Viswanathan, R., Shingledecker, J., Phillips, J., In
Pursuit of Efficiency in Coal Power Plants, (ed. Sakrestad, BA) 35th International Technical Conference on
Clean Coal and Fuel Systems 2010, Clearwater, FL,
June 2010.
5. Duffy, T., et.al., Advanced High Performance Steam
Systems for Industrial Cogeneration, Final Report
on DOE Contract No. AC02-85CE40746, DOE/
CE/40746-TI (1987)

6. Weitzel, P.S., Steam Generator for Advanced UltraSupercritical Power Plants 700 to 760C, ASME
Power 2011, Denver, CO (2011).
7. Rao, K.R., (ed.), Energy and Power Generation Handbook, ASME, New York, 2011.
8. Kitto, JB, Stultz, SC., Steam/its generation and use,
Edition 41, The Babcock & Wilcox Company, Barberton, OH 2005.
9. Silvestri, G.J., Eddystone Station, 325 MW Generating Unit 1-A Brief History, ASME, March 2003.
10. Silvestri, G.J., et.al., Optimization of Advanced
Steam Condition Power Plants, Diaz-Tous, I.A., (ed.),
Steam Turbines in Power Generation PWR-Vol. 3,
Book No. H00442, ASME, 1992.
Benson is a registered trademark of Siemens AG.

Copyright 2011 by Babcock & Wilcox Power Generation Group, Inc.


a Babcock & Wilcox company
All rights reserved.
No part of this work may be published, translated or reproduced in any form or by any means, or incorporated
into any information retrieval system, without the written permission of the copyright holder. Permission requests should be addressed to: Marketing Communications, Babcock & Wilcox Power Generation Group, Inc.,
P.O. Box 351, Barberton, Ohio, U.S.A. 44203-0351. Or, contact us from our website at www.babcock.com.

Disclaimer

Although the information presented in this work is believed to be reliable, this work is published with the
understanding that Babcock & Wilcox Power Generation Group, Inc. (B&W PGG) and the authors are supplying
general information and are not attempting to render or provide engineering or professional services. Neither
B&W PGG nor any of its employees make any warranty, guarantee, or representation, whether expressed or
implied, with respect to the accuracy, completeness or usefulness of any information, product, process or apparatus discussed in this work; and neither B&W PGG nor any of its employees shall be liable for any losses or
damages with respect to or resulting from the use of, or the inability to use, any information, product, process
or apparatus discussed in this work.
8

Babcock & Wilcox Power Generation Group

Anda mungkin juga menyukai