FOREWORD
The Oil Industry in India is more than 100 years old. Because of various
collaboration agreements, a variety of international codes, standards and
practices have been in vogue.
Exploration & Production Industry, Oil Industry Safety Directorate, 7 Floor, New
Delhi House, 27-Barakhamba Road, New Delhi - 110 001.
COMMITTEE FOR
PREPARING STANDARD ON
COMBINED OPERATIONS
2000
---------------------------------------------------------------------------------------------------Name
Organisation
Position in Committee
----------------------------------------------------------------------------------------------------1. Shri J.T. Mahavar
ONGC
Leader
ONGC
Member
3. Shri D. Kumar
OIL
Member
ONGC
Member
ONGC
Member
6. Shri T.Singh
OISD
Coordinator
-----------------------------------------------------------------------------------------------------
(ii)
COMMITTEE FOR
REVIEW OF GUIDELINES ON
SIMULTANEOUS OPERATIONS IN
EXPLORATION & PRODUCTION INDUSTRY
2008
---------------------------------------------------------------------------------------------------Name
Organisation
Position in Committee
----------------------------------------------------------------------------------------------------1. Shri Rajesh Kakkar
ONGC
Leader
ONGC
Member
ONGC
Member
OIL
Member
5. Shri A. Bora
OIL
Member
6. Shri D.K.Varshney
OISD
Coordinator
-----------------------------------------------------------------------------------------------------
(iii)
Description
Page
No
1
1.0
Introduction
2.0
Scope
3.0
Definition
4.0
4.1
4.2
4.3
5.0
13
13
5.1
5.2
14
21
24
hired rig
25
27
28
30
31
32
(iv)
OISD-GDN-186
INTRODUCTION
This document presents the procedures for safe conduct of drilling, workover,
production, revamping / construction and other related activities simultaneously from
the same well platform / process platform / well site / production installation.
The purpose of this document is to specify the limitations under which various
operations can be carried out simultaneously such as to ensure the safe conduct of
operations.
Simultaneous operations should be thoroughly analysed and planned with the
objective of limiting additional risk imposed by multiple activities and operations being
undertaken at the same place or in the vicinity at the same time as opposed to the
risk associated with the execution of these individually. Risk assessment studies
should form the basis for deciding upon simultaneous operations.
2.0.
SCOPE
The guidelines broadly cover the following related to simultaneous operations
(SIMOPS) in E&P industry:
3.0.
Practices to be followed.
DEFINITION
3.1 Cold work: An activity which does not produce sufficient heat to ignite a flammable
air - hydrocarbon mixture or a flammable substance.
3.2 Drilling: A process to produce cylindrical hole in earth, called well, using a drilling
rig, to access hydrocarbon bearing reservoir.
3.3 Hot work: An activity that can produce a spark or flame or other source of ignition
having sufficient energy to cause ignition, where the potential for flammable vapours,
and gases exists.
3.4 PPE - Personal Protective Equipment: Devices or clothing used to insulate an
individual from the chemical, thermal, explosive, electric shock or other hazards
presented by the environment in which one is working. Some of PPEs are Safety
goggles, Apron, Safety shoes, Chemical-resistant gloves, helmet etc.
3.5 Process platform / production installation: Facility, in offshore / onshore, where
produced fluid is processed (oil / water / gas separation, gas dehydration etc.) before
onward transportation.
3.6 Simultaneous operations (SIMOPS): Also called combined operations are
those where more than one major activity e.g. drilling, production, workover
operation, revamping / construction etc. is undertaken at the same place or in the
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
vicinity along-with activities such as material handling and hot work in an environment
where oil / gas is present or produced nearby.
3.7 Station bill: A written list posted in the crews quarters and other conspicuous
places, listing the station of the crew.
3.8 Workover: It involves any well maintenance / repair job, water shut off job,
installation / repair of artificial lift /changing of production zone etc by using workover /
drilling rig. The term includes any associated cold work.
3.9 Xmas tree: An assembly of valves and fittings in upper part of well, to control flow of
fluids from the well.
4.0
The above scenarios are indicative only. The companies should develop their own
scenarios based on the risk assessment of various SIMOPS activities.
4.1
4.1.1
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
The person responsible for SIMOPS should be the custodian of SIMOPS document
and it is the responsibility of the custodian to seek agreement or approval from
appropriate authority for any amendment.
4.1.2
Responsibilities
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
In the event of an emergency on the well platform or rig, the manual ESD buttons
should be operated.
On evaluation of the audibility of hooter of the rig, at the well platform, extension of
the same should be provided on the well platform, if necessary.
Persons working on rig should be trained in use of ESD systems, during rig induction
for SIMOPS.
(f) Well Platform Gas Venting
Required venting from the lubricators should be controlled by permit to work (PTW)
system. A gas detector should be installed below the cantilever to monitor the venting
gas.
(g) Fire Water System
In order to fight any fires on the well platform, which does not have fire water line
provision, the rig should install an adequate size sea water line from the rig to the
well platform. It should be kept pressurised with adequate pressure in readiness to
fight fires. Fire fighting hoses and nozzles should be strategically positioned, and
regularly tested, by the production representative.
(h) Communication and Coordination
Appropriate interfacing and good communication is required between the well
platform personnel and drilling rig crew throughout the simultaneous activities. A prestart meeting should be held onboard drilling rig with attendance of senior personnel
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
from process platform. The company man / rig OIM, as the case may be, should
conduct a daily meeting either in person or over radio / phone with the in-charge of
the project activities / offshore installation manager (OIM) / production representative
at a mutually convenient time. There must be regular telephonic conversation
between offshore installation manager (OIM) and the company man / rig OIM to
ensure communication on PTW and work plan. Radio contact should be established
between the involved installations and communication channel maintained.
During rig approach, piling activity, rig skidding, jack down and pull away from well
platform;
II. During drilling- with diverter system, regular drilling and H2S environment;
III. During well completion, well testing and well control;
IV. During hot work;
V. During helicopter operation.
I.
During rig approach, piling activity, rig skidding, jack down and pull away
from well platform;
Moving a jack up rig from and to an oil / gas production well platform is a critical
operation due to safety and environmental hazards associated with it. There are
number of oil, gas and water injection pipelines around the well platforms. Sea bed
survey is to be carried out to protect the pipelines during positioning of the rig. After
the sea bed survey, when the jack up rig approaches the well platform for docking, its
legs are lowered to touch the seabed and then the rig is pulled / positioned by the
towing boats.
(i)
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
(ii)
(iii)
Complete drawings of pipelines laid within 1000-m radius of the jacket should
be available on board of the jack up rig. The pipelines in the vicinity of the well
platform are required to be marked with buoys prior to approach of the rig to
the well platform.
(iv)
Platform should be handed over by OIM to company man / rig OIM, as the
case may be, when the rig is moved to the well platform and when the rig is
moved out, the company man / rig OIM, as the case may be, should hand over
well platform to OIM as per Annexure-D.
(v)
All pipelines (oil, gas, and gas injection) of the well platform are required to be
isolated from both ends to ensure no ingress of inventory. Information about
the pipelines, which are not connected to the jacket but are laid in the close
vicinity of the platform should be available with the rig before the rig movement
to decide upon the requirement of isolation of any of these lines, depending
upon their distance from the likely positions of spud tanks. The underwriters
may require the company to provide specific means to monitor the distance
between the pipeline and the spud tank continuously either by deploying the
divers or by providing transponders and receivers.
(vi)
In order to have good visibility, co-ordination and control of the tugs, the
approach to the well platform should be done only during daylight.
(vii)
(viii) Adjacent wells should be kept closed during rig approach, rig skidding and pull
away. Wells can be kept on production, during piling activity.
(ix)
II. During drilling- with diverter system, regular drilling: and H2S environment
(i)
(ii)
During regular drilling, adjacent wells can be kept on production and most of
the routine activities on the well platform are permitted. However, based on
risk perception, activities like ESD maintenance, well acidizing, line pigging,
wire line operations, flow line hook up may require prior approval.
(iii)
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
well platform during drilling in H2S environment. Adjacent wells can be kept on
production.
III. During well completion, well testing and well control
(i)
(ii)
During running of explosives / radio active resources in the hole and during
well control activities, operations namely crane operations, sampling / leak test,
approach of supply vessel, maintenance of gas and fire detectors, ESD
maintenance, well acidization, wire line work on adjacent wells, flow line hookup are not permitted on well platform. Also, all nearby radio communication to
be switched off during running of explosives / radio active resources. However,
adjacent wells can be kept on production during running of explosives /
radioactive sources in the hole. During well control activities, flowing of
adjacent wells is to be decided by OIM and company man / rig OIM, as the
case may be, on case-to-case basis.
When the hot job is planned in the well bay or in vicinity of the wells, wells on
production, approach of supply vessel, maintenance of gas and fire detectors,
sampling / leak test, ESD maintenance, well acidization are not permitted.
However, allowing of crane operation, line pigging, wire lining and flow line
hook-up should be decided by OIM and company man / rig OIM, as the case
may be.
(ii)
During rig approach, piling activity, rig skidding, jack down and pull away from well
platform;
II. During drilling- with diverter system regular drilling and H2S environment;
III. During well completion, well testing and well control;
IV. During hot work;
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
During rig approach, piling activity, rig skidding, jack down and pull away from
well platform
(i)
(ii)
Pressure testing and diving activity within 100 meters from rig / well platform
are not permitted during jack down and pull away. Other revamping /
construction related activities can be carried out with prior approval of OIM and
company man / rig OIM, as the case may be.
II. During drilling - with diverter system, regular drilling and H2S environment
(i)
Diving activity within 100 meters from rig / well platform, working at height and
night operations are not to be performed when drilling with diverter system
where there is potential of shallow gas.
(ii)
(iii)
During hot work in the well bay or in the vicinity of the wells, the platform wells
are to be kept closed. The various activities related to revamping and
construction activities on well platform are permitted to be performed with prior
approval except pressure testing.
(ii)
4.2.1
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
10
can be continued / can be continued with prior approval (at appropriate level),
emergency response plan, etc.
The person overall responsible for SIMOPS should be custodian of SIMOPS
document and it is the responsibility of the custodian to seek agreement or approval
from appropriate authority for any amendment.
4.2.2
Responsibilities
Offshore Installation Manager (OIM)
Has the overall responsibility for SIMOPS. Is responsible for the safety of personnel
and equipment on the process platform. SIMOPS on a process platform should be in
the knowledge of OIM.
Process Manager
Responsible for SIMOPS related to production activities and marine operations on a
process platform. Ensures that all SIMOPS are carried out in a safe manner as per
approved SIMOPS procedures. Maintains continuous liaison with OIM regarding
SIMOPS.
Logistics manager, if stationed on the process platform to deal with the activities
related to marine operations, should be responsible for SIMOPS related to marine
operations, instead of process manager.
Maintenance Manager
Responsible for SIMOPS related to revamping / construction activities pertaining to
process equipment. Ensures that all SIMOPS are carried out in a safe manner as per
approved SIMOPS procedures. Maintains continuous liaison with OIM and
engineering and construction representative regarding SIMOPS.
Engineering and Construction Representative
Responsible for revamping / construction activities, liaises with OIM and process
manager / maintenance manager for day to day activities related to revamping /
construction and works closely with them to ensure adherence to SIMOPS
procedures. Obtains necessary work permit and clearance from OIM / process
manager / maintenance manager before commencing revamping / construction
activities.
Contractor representative
The onsite representative of contractor engaged for revamping / construction
activities, follows the directions of the engineering and construction representative.
Ensures that the contractors personnel carry out tasks in a safe manner in
accordance with SIMOPS procedures and conditions laid out in work permit. Also
ensures that the contractors personnel have been imparted mandatory HSE trainings
before being deployed for the job at site, and that they use PPE while on the job.
Master of the vessel
Responsible for following the marine procedures / guidelines for vessels operations.
Liaises with the concerned process platform personnel, OIM and process manager /
logistics manager during SIMOPS involving marine operations.
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
4.2.3
11
I.
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
12
approach, maintenance of gas and fire detectors and fire suppression system,
maintenance of life saving appliances, etc carried out on process platform.
(i)
(ii)
When any of these systems namely fire suppression system, gas and fire
detectors is under maintenance, operations like well intervention, opening of
hydrocarbon line, instrumentation calibration, testing of PSVs, helicopter
operations, crane operations involving heavy lifts, maintenance of life saving
appliances are to be performed in a restricted manner with approval of OIM.
(iii)
During diving operations, the routine operations can be carried out on process
platform. However, during diving operations, supply vessel approach is not to
be permitted, helicopter operation and crane operations with small lifts can be
performed with prior approval from OIM, on case- to- case basis.
(ii)
(iii)
During the hot job in the hazardous area on process platform, operations like
opening of hydrocarbon line, testing of PSVs, crane operations, maintenance
of fire suppression system, gas and fire detectors, life saving appliances and
sampling / leak test / venting are not permitted to be performed on platform.
However, other operations can be carried out after taking permission from the
offshore installation manager (OIM).
(iv)
(v)
When the load is transferred above / near process facility by barge, on process
platform, activities namely well intervention, crane operations, maintenance of
life saving appliances, fire suppression system, gas and fire detectors,
sampling / leak test / venting, radiography, hot work in the process area are not
to be carried out.
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
13
(vi)
(vii)
When testing ESD / F&G interlocks, operations viz. well intervention, opening
of hydrocarbon line, helicopter operations, crane operations, maintenance of
gas and fire detectors, sampling / leak test / venting, load transfer above / near
the process facility and night operations are not to be carried out.
(ii)
Supply vessel approach on the same side is not to be allowed during diving
from vessel / barge.
(iii)
(iv)
During riser installation and infield line pipe installation in the vicinity of
platform, the following operations should have prior approval of OIM- supply
vessel approach, diving from platform, radiography, running of anchors, diving
from vessel / barge and load transfer between platform and vessel / barge.
The above scenarios are typical cases. It is recommended that organisation should
develop their own SIMOPS matrix, covering all the envisaged activities related to
process platform indicating activities which are permitted, which are not permitted
and which require prior approval.
4.3
5.0
The above scenarios are indicative only. The companies should develop their own
scenarios based on the risk assessment of various SIMOPS activities.
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
5.1
14
Responsibilities
OISD-GDN-186
15
production activities can continue during all phases of drilling rig / workover
rig activities with / without some restriction.
production activities are to be suspended only till rig building stage and
thereafter during rig dismantling and its transportation stage.
Only after the additional control measures are in place, corresponding to one of the
above scenarios, drilling rig / workover rig related activities should be undertaken
under that scenario.
(c) Hazardous Areas
If rig is to be inside the installation, hazardous area classification drawing of the
installation and rigs hazardous area classification drawing should be combined to
establish a composite hazardous area classification drawing.
(d) Fire water System
The rig should have independent fire suppression system which can handle fire on
the rig and the cluster well. Fire fighting hoses and fire nozzles should be strategically
positioned, and regularly tested.
(e) Communication and Coordination
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
16
Appropriate interfacing and good communication between the installation and drilling
rig / workover rig throughout the simultaneous activities is to be maintained.
Company man / rig manager, as the case may be, should hold regular meetings, as
per written down schedule, with all the concerned personnel to review SIMOPS.
(f) Drilling Station Bill & Mustering
The drilling rig / workover rig should initiate a SIMOPS Induction for all personnel
when they arrive on the rig. The personnel should be aware about the mustering
points which should be used in case of emergency.
(g) Emergency response
In the event of any emergency on the rig involving a cluster well or installation having
rig inside, it is the responsibility of the company man / rig manager, as the case may
be, to initiate and co-ordinate all emergency response actions as per approved
SIMOPS documents, in close liaison with IM.
5.1.4
I.
II. Skidding of drilling rig and shifting of drilling rig / workover rig in cluster
location,
III. Drilling / workover on one well and activation of / wireline job on another well in
the cluster,
IV. Drilling / workover on one well and CTU / Stimulation job on another well in the
cluster,
V. Drilling rig / workover rig inside the installation.
At a cluster location, more than one well is drilled from the same plinth. These may
involve simultaneous operations like well drilling / workover operations / production
related activities, at the same location. The SIMOPS may take place under various
scenarios like:
(a)
One well is under production and the rig building is in progress for drilling
second well.
(b)
One or more wells are on production and the drilling / workover operation is
in progress on another well.
(c)
One well is under drilling, another well is under workover operations and
other wells are under production. This scenario should be avoided.
The cluster wells are generally adequately spaced for carrying out drilling / workover
operations in each well without creating any hindrance during transportation, rig
building and rig dismantling.
The routine operations involved in a producing well include:
(a)
Mechanical scraping,
(b)
(c)
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
17
(i)
In cluster drilling, a concern is below surface collision of the well with the
neighbouring well. The higher risk is in the upper part where all the wells are
close to each other, but risk at depth still exists. Precautions should be taken
while preparing well programme (well profile) to avoid this kind of situation
otherwise consequences can be serious when the producing well is hit.
(ii)
(iii)
(iv)
The escape routes of drilling rig / workover rig should be free from any
obstruction.
(v)
(vi)
The Xmas tree of cluster wells and flow lines / injection lines should be
protected by means of temporary physical barrier above and around it, so that
the same may not be damaged by falling objects and inadvertent hitting by rig
equipment. The cluster wells should be taken up for temporary protection
before the drilling rig / workover rig moves in.
(vii)
(viii)
(ix)
Flow line and gas injection line from / to the producing wells should be laid at
an adequate distance from substructure of rig and buried as far as possible or
re- routed, if required to avoid damage during drilling / workover, rig building /
dismantling, transportation etc.
(x)
Caution notice board mentioning "DANGER - High pressure gas line / oil flow
line" should be displayed at appropriate places. Caution board mentioning
"DANGER - Well on production" should be displayed at the producing well(s).
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
18
(xi)
In case of high pressure wells (high flowing tubing head pressure) in the
cluster locations, a pneumatically / hydraulic controlled valve should be
installed on the X-mas tree (wing valve) with remote control on the derrick floor
near driller's control panel to shut-off flow in case of emergency.
(xii)
Before carrying out of servicing, monitoring jobs etc on a producing well, preplanning of jobs should be done, keeping in view the drilling / workover
operations in the vicinity. Special / additional procedures to be followed and
safety precautions to be taken, under SIMOPS situation, should be clearly
spelt out.
(xiii)
Clearance from SIMOPS incharge (company man / rig manager, as the case
may be) should be obtained before undertaking any job on any cluster well and
close coordination between well servicing / monitoring personnel and drilling /
workover rig personnel should be maintained throughout.
(xiv)
I.
Movement of drilling rig / workover rig around the producing oil / gas wells
The risks involved during transportation of rig are fire and pollution due to damage of
well flow lines / injection lines. The rig manager and logistic manager should inspect
the route to check for any obstructions like overhead power lines, sharp bends, over
ground pipelines etc. Thereafter, the route to be followed for rig movement by
logistics should be decided prior to movement of the rig.
(i)
During transportation over the underground pipelines, the vehicle should pass /
cross over with utmost care. All vehicles, heavy earth moving equipment and
the cranes should be fitted with spark arrestor. No unauthorized person should
be allowed to enter in the operational area at drill site. It should be ensured that
the flowlines / injection lines at the location, protected before the rig moves in,
are at an adequate distance away from load carrying activities / vehicular
movement.
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
(ii)
19
The producing wells should be checked for any leakage of gas / oil before and
during movement of rig equipment in / around the area. IM should be informed
in advance of the rig movement into his area.
II. Skidding of drilling rig and shifting of drilling rig / workover rig in cluster location
There are two methods of rig movement in a cluster location.
(a)
Rig skidding
(b)
The rig skidding involves skidding of the rig structure along with mast through a small
distance over the concrete foundation, while retaining other equipment e.g. mud
handling system, power packs, diesel / water tanks etc. at the original position for
undertaking drilling at new point in the cluster.
Shifting of the rig involves mast lowering and dismantling of the mast and
substructure thereafter shifting to the required location and subsequent erection.
(i)
Company should develop their SIMOPS matrix covering all the envisaged
activities related to shifting / skidding of rig indicating activities which are
permitted, which are not permitted and which require prior permission.
(ii)
Pre-operation meeting should be conducted and plan prepared for safe shifting
/ skidding of rig and its material.
(iii)
Before deciding for skidding, the risk of collapsing / toppling of mast should be
evaluated. It may damage the adjoining producing well resulting in leakage of
oil / gas which may cause fire and environment pollution, besides equipment
damage.
(iv)
(v)
Skidding of rig is not to be permitted if the flow lines / injection lines are not at a
safe distance from the skidding route.
(vi)
The rig should be allowed to skid / shift only when it is ensured that there is no
leakage of gas / oil from cluster wells as spark, which may occur during
skidding / shifting, may lead to fire.
(vii)
The skidding / shifting operations are permitted in day time only and after
carrying out of visual inspection of the mast and substructure for cracks,
misalignment etc.
(viii) SRP units operation in the cluster location, should be stopped during rig
skidding / shifting.
(ix)
SRP units operation on the adjoining well (s) to be stopped, during rig down /
up.
III. Drilling / workover on one well and activation of / wireline job on another well in the
cluster
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
20
These operations involve drilling rig / workover rig on well by the side of another well
which is being activated by displacement, compressor, nitrogen application etc. or
under wireline job.
(i)
Company should develop their SIMOPS matrix covering all the envisaged
activities related to drilling / workover on one well and activation of / wireline job
on another well indicating activities which are permitted, which are not
permitted and which require prior permission.
(ii)
Hazards associated with activation jobs are fire due to gas spread, accidental
damage to X-mas tree, wellhead, flow line etc. During activation, no hot work is
to be permitted in the hazardous zone.
(iii)
Activation job is permitted only when the area is hydrocarbon free and checked
with the help of gas detector and all connections, flow lines & joints tested up to
maximum expected pressure. Personnel not related to the job are not
permitted to go near the flow lines and activation units. Activation jobs should
be carried out in day time only.
(iv)
(v)
During wireline job, immediate work area should be kept free of non-essential
workers to avoid potential hazards of being struck by wireline & wireline
equipment or getting caught in wire line.
IV. Drilling / workover on one well and CTU / Stimulation job on another well in the
cluster
These operations involve drilling rig / workover rig on a well in the cluster and CTU /
stimulation job on another well.
(i)
Company should develop their SIMOPS matrix covering all the envisaged
activities related to drilling / workover on one well and CTU / stimulation job on
another, which are permitted, which are not permitted and which require prior
permission.
(ii)
(iii)
Hazards associated with these jobs are fire due to gas spread, sparking due to
loose motor connection, handling of heavy objects and accidental damage to
Xmas tree, wellhead, flow lines etc. and handling of hazardous chemicals
including concentrated acids.
(iv)
Personnel not related to the job are not permitted to go near the high pressure
lines and stimulation / CTU units. During stimulation job namely acidisation or
hydraulic fracturing, hot work is to be permitted only in designated area.
Stimulation jobs should be carried out in day time only.
(v)
(vi)
Stimulation job is to be permitted only when the area is hydrocarbon free and
all connections, flow lines and joints are tested up to maximum expected
pressure.
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
(vii)
21
Company should develop their SIMOPS matrix covering all the envisaged
activities related to drilling / workover operations inside the installation
indicating activities which are permitted, which are not permitted and which
require prior permission.
(ii)
(iii)
(iv)
Only spark arrestor fitted vehicle should be allowed inside the installation.
(v)
Gas concentration is to be checked before shifting of the rig and during rig
operations and recorded. Hot jobs are to be permitted only after prior approval
from company man / rig manager, as the case may be, and IM, and should be
avoided during rig skidding. Refer OISD-STD-105 for requirements related to
work permit.
(vi)
Before deciding for skidding, the risk of collapsing / toppling of mast should be
evaluated. It may damage the adjoining flow lines, process units and crude oil
storage tanks resulting in leakage of oil / gas which may cause fire and
environment pollution.
(vii)
5.2.1
5.2.2
Responsibilities
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
22
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
23
The area, in which the project activities are being undertaken, should be
demarcated and caution board should be displayed around the construction
site.
(ii)
(iii)
(iv)
Adequate fire fighting facility should be available during hot jobs. Gas
concentrations should be taken before and during the job and recorded. No hot
job is to be carried out if the gas concentration is beyond the acceptable limit.
**********
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
24
Annexure-A
Delegation of Authority Letter, in case of hired rig
Company Address:
No.:
Date:
DELEGATION OF AUTHORITY
He is authorized to have the signatory control of issuing all hot work and safety critical
permits related to SIMOPS, and shall ensure that all the activities comply with the
requirements of the companys policy / procedures and applicable Govt. of India regulations.
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
25
Annexure-B
Pre-Operations Check List (Offshore)
The following check list should be used as a guideline and should be signed by the company
man / rig OIM, as the case may be:
Action
Timing
7
8
9
10
11
12
13
Company
man / rig
OIM
signature
as
is
as
After stairway is
established
Contd./"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
26
Action
Timing
14
15
16
17
18
As
soon
as
practical
after stairway is
established
Prior
to
commencing
well operations.
As
soon
as
stairway is
established
As
soon
as
stairway is
established
As
soon
as
stairway is
established
19
Prior
commencing
operations
Company
man / rig
OIM
signature
to
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
27
Annexure-C
Documents / Information (Offshore)
Well platform details related to safety valves and their control system, gas and fire
detection system etc.
Well platform handover as per Annexure D and delegation of authority letter as per
Annexure A, if applicable.
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
28
Annexure-D
Platform Handover Form for Drilling / Working over well no(s) _________
_________Platform Handover from____________ to __________ Date : ________
S.No Description
Condition during
handover
OIM to
company man
/ rig OIM
Remarks
Company
man / rig
OIM to OIM
platform wells)
1
Any leaks
Any
hydraulic
oil
leaks
from
control lines
Panel
board
covered
with
Crane
1
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
29
S.No Description
Condition during
handover
OIM to
company
man / rig
OIM
Remarks
Company man /
rig OIM to OIM
Consumables Stock
1
General
1
Condition of helideck
Condition of DG
Swing ropes
Life raft
Navigation lights
Fog horn
_________________
Signature
Company man /
RIG OIM
____________
Date
____________________
Signature OIM
__________
Date
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
30
Annexure-E
Post - Operations Check List (Offshore)
This check list, to be signed by the company man / rig OIM, as the case may be, covers the
removal of the temporary services extended around the platform. The following to be
checked prior to rig move:
Action
2
3
All wells on the platform are shut in and de-pressured during moving
away from the platform.
Recover all the temporary facilities from the platform.
10
11
Company
man / rig
OIM
signature
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
31
Annexure-F
NP
NP
NP
PPA
NP
NP
PPA
NP
NP
NP
NP
NP
NP
PPA
Helicopter operations
PPA
NP
_____________
NP
____________
Crane operations
Wells on production
_ _ _ _ _ _ _ _ _ __ _ _ _ _ _
_ _ _ _ _ _ _ _ _ __ _ _ _ _ _
_ _ _ _ _ _ _ _ _ __ _ _ _ _ _
P - Permitted
NP - Not permitted
PPA- Permitted with prior approval
"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."
OISD-GDN-186
32
Annexure-G
SIMOPS Check list (Onshore)
The following check list should be used as a guideline before the rig moves to cluster location
/ inside the installation and should be signed by the company man / rig manager &
installation manager:
Action
Observations
Remarks
the
SIMOPS
programme
and
identified
and
are
free
from
any
obstruction
4
Frequency
of
gas
checking
and
temporarily
physically
cluster
location
have
been
buried
underground.
Contd./"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from
use of the OISD Standards/ Guidelines/ Recommended Practices."