Training Unit
Electrical Installation 2
Theory
No: EE 022
Training Unit
Electrical Installation 2
Theoretical Part
No.: EE 022
Edition:
2008
All Rights Reserved
Editor:
ELECTRICAL INSTALLATION 2
CONTENTS
Page
General ................................................................................................................6
1.2
1.2.1
1.2.2
1.2.3
1.2.4
1.3
1.3.1
Safety .............................................................................................................12
1.3.2
1.3.3
Pre-meter cables............................................................................................12
1.3.4
Voltage drop...................................................................................................12
METER PANELS........................................................................................................13
2.1
General ..............................................................................................................13
2.2
2.3
Type of fixing......................................................................................................14
2.3.1
2.3.2
General ..............................................................................................................16
3.1.1
Distribution fuses............................................................................................16
3.1.2
Distribution panels..........................................................................................16
3.2
4.2
4.2.1
Area of protection...........................................................................................18
4.2.2
4.2.3
4.2.4
4.3
4.3.1
4.4
4.4.1
4.5
4.5.2
4.6.1
4.6.2
Conductor installation.....................................................................................22
4.7
General ..............................................................................................................24
5.2
5.2.1
Safety .............................................................................................................24
5.2.2
5.3
Electrical installation.......................................................................................20
4.5.1
4.6
Fixed lights.........................................................................................................26
5.3.1
Cable..............................................................................................................26
5.3.2
Voltage requirement.......................................................................................26
5.4
5.5
5.6
5.6.1
Fusing ............................................................................................................27
5.6.2
Cable requirements........................................................................................27
5.6.3
Distribution units.............................................................................................28
General ..............................................................................................................29
6.2
6.2.1
6.2.2
6.2.3
Cable reel.......................................................................................................30
6.2.4
6.3
6.3.1
6.3.2
7.2
7.2.1
7.2.2
AC bells..........................................................................................................34
7.2.3
Buzzer ............................................................................................................34
7.2.4
DC bell ...........................................................................................................35
7.2.5
7.2.6
Door intercom.................................................................................................35
7.3
ELECTRICAL INSTALLATION 2
LEARNING OBJECTIVES
describe the construction, the size and the connections for a consumers meter panel
name the permitted cable materials for use outside, in the open or underground
describe briefly the methods of laying and making connections to high current cables
ELECTRICAL INSTALLATION 2
1.1
DOMESTIC CONNECTIONS
General
The cross section of the cable, used for the domestic connection should be such that
future extensions are possible.
If it is likely that there will be a later change from an overhead cable connection to an
underground cable connection, it is useful to provide a piece of conduit from the likely
place of the underground-cable entry in to the lowest floor distribution.
If motors above 1.1 kW, room heaters of 2.2 kW and other loads of above 3.3 kW are
present, the domestic connection must be a three-phase AC connection.
1.2
a)
Roof-pole connections
2)
Wall-box connections.
b)
Underground-cable connections.
c)
Special connections.
1.2.1
Overhead-cable connections
a)
Whip type
1)
of
the
system
is
sheltered
by
hemispherical cap.
2)
In order to connect the cable properly to the terminals of the supply fuses
on the one hand and to the overhead cable, on the other, the cable must be
approximately 1.5 metres longer than the pipe.
b)
In this roof-pole entry there is a separate run of individual cables in flexible armouredplastic conduit, 11 mm nominal diameter. The conduits must be taken to the edge of the
insulating cap of the roof-pole entry head, to the terminals of the fuses and to the neutral
terminal in the supply fuse box.
In order to connect the conductors properly, they must be approximately 1.5 metres longer
than the armoured-plastic conduit.
c)
The individual, double-sheathed cables (specific roof cable, nominal voltage 1,000 V) are
laid in the roof-pole conduit and stress relieved from above.
The cables are taken in a flexible-armoured conduit, 36 mm nominal diameter from the
supply connecting box to the roof-pole conduit. In order to connect the cables properly,
they must be approximately 1.5 metres longer than the armoured-plastic conduit plus the
roof-pole conduit. The armoured-plastic conduit should have a hole below the roof-pole
conduit so that condensed water can drain away.
1.2.2
10
1.2.3
Underground-cable connection
This type of connection is used mainly in City areas, where an underground cable is a
available or is laid for the supply. For underground entry into the building one must
provide a suitable space for connecting the cable which is accessible to the electric-supply
company.
For underground-cable connections, main cables in the cellar leading from the supply
connection box may only be laid in conduit mounted above the plaster. From the ceiling of
the cellar upwards, the main cables must be laid in ducts, conduit, channels or under the
plaster.
1.2.4
Special connections
a)
b)
11
1.3
1.3.1
Safety
1.3.2
Inside connection
The cable between the overhead-cable terminals and the supply connection box is called
the "inside connection".
The minimum cross section is 10 mm of copper and must be kept as short as possible.
The domestic entry cable or inside connection can be a single cable or a multi-core
sheathed cable.
Consumer fuses are normally installed inside the building.
The proper fuses for the system installed must be of the correct size.
1.3.3
Pre-meter cables
Pre-meter cables are cables between the supply connection box and the meter,
The minimum cross section for cable is 6 mm of copper.
A greater cross section is recommended for later extensions.
1.3.4
Voltage drop
The voltage drop between domestic connection and meter panel may not exceed 1% of
the rated voltage.
12
2.1
METER PANELS
General
The meter must always be mounted separately from the distribution device. In small
domestic installations (detached house), if the electric-supply company agrees, the meter
and consumers distribution unit may be installed on one panel.
The distribution fuses must always be situated above the meter.
Plugs, switches, and contactors may not be mounted on the distribution board with the
exception of circuit breakers.
All the equipment required for metering the power is situated on the meter panel. This
may consist of meters (active and reactive power meters) time clocks and audiofrequency carrier receivers. The size of the panel depends on the equipment required.
Minimum sizes are laid down for metering devices, which are stated as fixing areas of
sizes I, II and III.
2.2
Fixing areas
Minimum dimension
Fixing area
Width mm
Height mm
160
280
II
200
360
III
250
500
13
2.3
2.3.1
Type of fixing
Meter panels
Meter panels must be fixed in areas which are accessible at all times (stairways,
corridors).
In detached houses and blocks of flats or in farms the meter panel must be installed on
the ground floor.
The meter panel must be fixed so that the dials are not more than 1.6 metres above floor
level. This dimension can be reduced to 0.75 metres above floor level, if the meter panel
is fitted into a recess or box.
These boxes should have facilities for locking. This will under the control of the electricity
supplier.
2.3.2
Distribution Units
Distribution units manufactured in a factory and provided with meter panels (complete
distributors) must comply with the regulations as set forth in the country where they are
installed, and must be authorized by the electricity supplier. The distribution units can be
made of plastic or steel sheet.
Double insulation must be provided for steel-sheet distribution units as a protective
measure against voltage which is too high. Cables and earth leakage circuit breakers
must also be constructed with double insulation.
14
The distance between the meter panels and the front plate of the distribution unit must be
at least 165 mm.
Meter panels not made in a factory must be hinged so that they can be opened to an
angle of at least 60. These panels are made of eternite or hardboard. According to the
regulations of the electricity supplier, the panel must be capable of being sealed closed
The panels must have a handle and a lock to facilitate opening and closing.
Size of panel
Design
Material
Thickness of panel
minimum in mm
Up to 1.2 m
Over 1.2 m
Up to 1.5 m
Over 1.5 m
15
Eternite
12
Hardboard
10
Eternite
15
Hardboard
12
Eternite
12
Hardboard
12
Eternite
15
Hardboard
12
3.1
3.1.1
General
Distribution fuses
The distribution fuses (circuit fuses) which consist of a DIAZED or NEOZED fuses with
rating up to 63 A are mounted an these panels. Low-voltage, high-current fuses (NH) must
be used for currents above 63 A.
The cable from the supply must always be connected at the bottom connection of the
Diazed or Neozed fuse. Automatic circuit breakers may be used instead of fuses, but only
in conjunction with pre-fuses of 100 A maximum rating. Supply fuses, main fuses for each
floor of an apartment building and meter fuses connected before or after the meter are all
called pre-fuses.
3.1.2
Distribution panels
The distribution panels can be manufactured with a front plate which can be taken off.
Otherwise they may be made of erenite or laminated plastic, but they must be hinged so
that they can be turned.
N.B. Wood must not be used for distribution panels.
It must not be possible to touch live parts while in operation. The distance between live
parts and the metalwork or house structure at the back of the panel must be at least 15
mm.
The individual circuits in the distribution unit must be labelled with their intended purpose.
Distribution fuses may only be mounted above meters. The fusing circuit must always be
positioned after the meter circuit.
16
3.2
The voltage drop must not exceed the following values on full load:
a)
b)
c)
d)
17
4.1
g) Farms
h) Garages
i)
Electro-medical rooms
4.2
Cables going through bathrooms or shower rooms may only be used for supplying other
rooms if they are laid at least 2.25 metres above floor level.
4.2.1
Area of protection
The area of protection in a bath or shower is 0.6 metres an all sides, and 2 metres from
floor to ceiling. Switches or socket outlets may not be fitted within this protected area.
18
The exception to these regulations include fitted switches for water heaters and socket
outlets with isolating transformers up to 25 VA (shaver points). They are marked
4.2.2
Protective earthing
A conducting bathtub (or shower trough) must be connected with a copper wire of a least
6 mm area between the outlet and the freshwater pipe.
4.2.3
Electric heaters need not be protected by drip-proof enclosures but their lower edges must
be at least 2 metres above floor level.
All movable equipment, including movable heaters used in bathrooms must be double
insulated. Exceptions are washing machines and spin driers.
4.2.4
a) Under plaster
Cables in conduit (PVC), YM-cables and material for use under plaster
b) On top of plaster
Only YM-cables may be laid an insulating camps and only material suitable for damp
areas may be used
19
4.3
Damp and wet rooms where there is dampness (formation of condensed water).
Damp and wet rooms include the following areas:
a)
Laundries
e)
Stables
b)
Communal baths
f)
Greenhouses
c)
Dairies
g)
d)
Refrigerated rooms
4.3.1
Electrical installation
Only cables or sheathed cables (damp area cables), damp area sockets and damp area
fittings may be used for electrical installations in such rooms. Screwed connections in
damp areas must be sealed with damp area putty. Fixing screws of fittings must also be
protected against dampness.
The transition from damp area cables to conduit may only take place outside the damp
area. Lamps must have 1 P 5 protection (drip-proof) and be provided with protective
windows.
In areas with acid vapour, sheathed cables should not be laid in or under plaster, but
should be laid outside these areas as far as possible. Only short spurs should be laid in
this type of area.
4.4
Hot rooms
These are rooms where temperatures above 35C occur. They may also be wet or damp,
and include the following:
a)
Saunas
d)
Drying rooms
b)
Heated rooms
e)
Smelting chambers
c)
Boiler houses
20
4.4.1
Normal cables may be used up to 55C ambient temperature. However, the current
through them must be reduced according to the following table:
Room temperature C
correction factor
for current carrying capacity
30
92
35
85
40
75
45
65
50
53
55
38
In rooms where there are temperatures above 55C, only cables with increased thermal
resistance may be used.
At temperatures above 85C cables with asbestos insulation or mineral insulated cable
should be used.
4.5
These are rooms or areas where there is a danger of easily inflammable materials
touching electrical material, so that the higher temperatures of these materials constitute a
danger of fire.
4.5.1
Inflammable materials
Paper
e)
Wood shavings
b)
Textiles
f)
Cotton
c)
Hay
g)
Wool fibres
d)
Straw
h)
Wood
21
4.5.2
Cable in plastic conduit, flexible plastic conduit under the plaster, armoured conduit or
cable with flame-resistant sheath may be used for electrical installations.
All cables to a room where there is a danger of fire must have all poles capable of being
switched off at an easily accessible place.
4.6
These are areas where gases, vapours or dust can gather forming explosive mixtures on
their own or with air.
4.6.1
Areas where there is a danger of explosion include areas for storing or processing the
following items:
a)
Benzene
e)
Ether
b)
Benzol
f)
Alcohol
c)
Petrol
g)
Gas
d)
Spirits
h)
4.6.2
Conductor installation
Installations in these areas are carried out using cables or similar conductors which can
be switched off outside the potentially explosive area.
Explosion-proof equipment (with the sign "Ex"), locked with triangular headed set-screws,
is used for this type Installation.
22
4.7
23
5.1
General
Before starting installation work, the electricity-supply company determines the point or
connection to the distribution network. Only cables, sheathed conductors, Setra (self
supporting) cables or conductors mounted between insulators (overhead wires) may be
used for permanent cables.
Only rubber-sheathed conductors or plastic-insulated conductors of medium-heavy design
may be used for movable cables.
On building sites, such cables must be of heavy design.
The type of protection for fixed lights or equipment as well as for movable lights or
equipment must comply with local safety regulations.
5.2
5.2.1
Safety
24
If concrete vibrators or tile-grinding machines are used an building sites, they must be
operated either at low voltage (42 V), or via a protective isolating transformer (transformer
with separate windings) at voltages above 42 V.
Connection-distribution cubicles are recommended for small building sites. This means
that the supply connection, meter and distribution equipment are accommodated in one
cubicle.
For heavier loads, it has proved better to divide this into separate connection and
distribution cubicles.
5.2.2
Distributors at building sites with rated currents of 25, 63, 100 and 250 Amps are
preferred.
A permanent wiring diagram must be fixed inside the distribution unit.
25
5.3
Fixed lights
5.3.1
Cable
Cable or sheathed cable is to be used for installations. Apart from cables, lighting cables
can be used for temporary fixed lighting (e.g. Christmas-tree lights).
The fittings in accessible areas or out of doors must be made of plastic (insulating
material).
5.3.2
Voltage requirement
Low voltages should be used, if possible, for fixed lighting out of doors.
5.4
26
For such events, the cables should be laid in buildings, according to the regulations for
rooms where there is a danger of fire. Joints must be protected from being accidentally
broken. Meters must be protected against the effects of weather.
5.5
These connections must first be discussed with the electricity supplier, who will decide
whether a meter should be installed.
Such connections are made in existing domestic connections an the supply side of the
supply fuses and are provided with their own supply fuse. If searchlights are being used,
there should be no inflammable material in these areas.
5.6
Vehicle connections
5.6.1
Fusing
A sealable supply fuse must be mounted near the connection to the distribution network of
the electricity supplier.
5.6.2
Cable requirements
A sheathed cable of medium design is used for the connecting cable. These cables must
be protected from mechanical damage.
27
5.6.3
Distribution units
Camping site distribution units are also suitable for annual fairs and exhibitions.
The connecting cable between distributor and load should not be more than 25 metres
long.
28
6.1
General
Supply cables are used to transmit electrical energy over long distances. Power cables
are mainly used for electrical installations.
The cables may be laid in the ground, in water or in the open.
In densely populated areas, the cables are always laid underground. Paper and plastic
material are used as insulation for cables.
Cables with paper insulation require a sealed waterproof sleeve, which is usually made of
lead.
6.2
Laying cables
6.2.1
Cable temperature
When laying cables, the cable temperature should not be lower than +5 C. At lower
temperatures, the cables should be stored in a heated room at least for one day prior to
laying.
6.2.2
Bending radii
29
6.2.3
Cable reel
The supply-cable reel should be transported as near as possible to the place of use. The
drum should not be rolled. When reeling, the cable may only be unreeled from drums
mounted with bearings and the cable must be taken from the top and reeled in the same
direction.
The cable must be kept taut, but not over-tensioned and must not be pulled over edges or
in a curve.
If the supply cable reel cannot be brought to the equipment, then one should unreel via
guide rollers. A pulling rope and cable grip should be used.
6.2.4
Laying cable
Depths for laying cables are generally 60 to 80 cm (for high-voltage cables 0.8 to 1.2
metres). If pipelines are to be crossed, the cable trench should be dug gradually deeper
so that the cable will lie under these pipelines. Before laying the cable, the cable trench
should be checked for width, depth and absence of rocks. The cable trench should be
filled to a depth of 10 cm with bedding material or sand. The cable can then be laid, so
that there is some resilience in case of changes of length due to temperature or earth
movements. In order to protect the cable, it is covered by bricks or covers before filling in
the cable trench.
A yellow marker strip is laid about 30 cm below the surface.
30
1. soil
2. yellow marker
3. cable
4. sand bed
5. cover brick
If several power cables of up to 1 kV voltage rating are to be laid in one trench, then they
must be spaced by at least 6 cm apart. When laying several cables with a rating above 1
kV in one trench, these cables must be separated by bricks.
The cable must be laid through a clay, concrete or iron pipe when entering a building.
1. soil
2. yellow marker
3. sand bed
4. cover bricks
5. cables up to 1 kV rating
6. cables above 1 kV
NOTE
Single-core cables may not be pulled through closed metal conduit (induction voltages). If
a metal conduit is used (e.g. when passing through walls) then this must have a cut a long
its length.
31
6.3
Cable connections, T-offs and cable ends are made with their connections and
terminations in a mould filled with resin. With oil impregnated paper insulated cables,
moisture must be prevented from entering and oil from leaking.
a)
Connections
2)
Tee junctions
1.
tape
8.
wire binding
2.
half-lapped tape
9.
string binding
3.
resin
10.
4.
mould
11.
5.
lead sheath
12.
soldered connection
13.
tee-off clamp
6.
7.
32
b)
termination
1.
tape
8.
wire binding
5.
lead sheath
9.
string binding
10.
soldered connectors
steel sheath
11.
14.
6.
7.
6.3.1
insulation
6.3.2
Making terminations
Terminations are made in a manner similar to resin sleeves. In order to obtain good
sealing, the cores must be taped where they pass through the termination cap, and the
insulation removed for a certain distance, for outside terminations, so that resin can
penetrate and seal the cables.
33
This equipment is usually operated from a bell transformer fed from the supply
7.1
Installation material
Signal cables (bell wires) are used as installation material, utilizing the following
dimensions:
a) For cables up to 50 metres long the cable diameter is 0.6 mm
b) For cables up to 100 metres long the cable diameter is 0.8 mm
c) For cables up to 160 metres long the cable diameter is 1 mm.
7.2
7.2.1
Bell transformers
Bell transformers are short-circuit proof and give a voltage of 3, 5 and 8 V and a shortcircuit current of 1 to 3 A.
There are bell transformers with higher secondary voltages, e.g. 5, 10 and 15 V.
7.2.2
AC bells
The iron armature of the bell vibrates due to the alternating magnetic flux and this the bell
7.2.3
Buzzer
The construction is the same as that of the bell. Instead of a bell, the buzzer has a
resonant metal sheet.
34
7.2.4
DC bell
The current flows through the coil of the DC bell. The armature is attracted and hits the
bell. The current is interrupted by a contact which is normally closed and the armature
drops off. This process is repeated.
7.2.5
The electric door opener is taken for granted in modern flats. It guarantees the safety of
the door which is always closed, and makes it convenient to open and monitor the door
from the fiat.
Doors with electric door openers have only one door knob.
The doors are locked and can be opened either electrically with a door-opening pushbutton or mechanically with a key or from inside with the door handle.
When the door is opened electrically, a buzzing noise can be heard.
7.2.6
Door intercom
This is designed for verbal communication between the main entrance of a block of flats
and an individual fiat. It consists of a weatherproof microphone-loudspeaker combination.
The speaker in the flat has a pushbutton which operates the door opener. It is not possible
to speak from one flat to another.
The inhabitants of the flats may communicate with a person at the door via a loudspeaker
at the main entrance to the block of flats. The volume at the front door can be increased
with the aid of a transistor amplifier.
For flats on busy roads with a lot of traffic noise, an amplifier must be provided.
35
Schematic diagram
7.3
a)
Circuit examples
36
b)
37
EE 022
Electrical Installation 2
Theoretical Test
38
EE 022
ELECTRICAL INSTALLATION 2
TEST 1
QUESTIONS:
2. State the requirement for laying main cables in a cellar leading from the supply
connection box.
4. What is the minimum distance between meter panels and the front plate of the
distributor?
5. What is the maximum permissible voltage drop from the meter to the load for power
cables on full load?
7. Name at least 4 types of electrical equipment that may be used in the open (outdoors).
9. State the rule to be followed when laying two or more supply cables, for above 1 kV, in
the same trench.
39
EE 022
ELECTRICAL INSTALLATION 2
TEST 2
QUESTIONS:
2. State the basic construction characteristics for roof-pole entry using flexible armouredplastic conduit.
3. What is the maximum permissible voltage drop between supply connections and
meter panel?
9. What is the minimum distance between cables of up to 1 kV when more than one are
laid in the same trench?
40
EE 022
ELECTRICAL INSTALLATION 2
TEST 3
QUESTIONS:
1. Which type of supply connection must be used if loads of above 3.3 kW are present?
3. Explain the term "fixing area" in a distribution unit. Name the different fixing area
designations.
4. State the maximum permissible voltage drop from the meter to the load for lighting
cables on full load.
5. May switches or socket outlets be installed in the protected area of a shower or bath ?
6. State which type of cable may be used for a room where temperature is:
a) 55 to 85 C
b) above 85 C
9. State the sequence of layers which will be found when digging down into a cable
trench.
41
EE 022
ELECTRICAL INSTALLATION 2
TEST 4
QUESTIONS:
1. Approximately how much longer must the cable be than the pipe in a whip-type roof
pole entry?
4. State the maximum allowable voltage drop from the meter to the load for heating
cables on full load.
7. State the provision under which normal cables can be used in hot rooms.
42
EE 022
ELECTRICAL INSTALLATION 2
TEST 1
SOLUTION:
3. Premeter cables are cables between the supply connection and the meter.
4. 165 mm.
6. 0.6 metres on all sides and 2 metres from the floor to the ceiling.
8. +5 C.
10. The iron armature of the bell vibrates due to the alternating magnetic field and hits the
bell.
43
EE 022
ELECTRICAL INSTALLATION 2
TEST 2
SOLUTION:
4. Pre-fuses are supply fuses, main fuses for floors in apartment buildings and meter
fuses, connected before or after the meter.
5. Bathrooms, communal baths, hot rooms, farms, garage, damp and wet rooms, rooms
where there is danger of fire, rooms where there is danger of explosion, electromedical rooms.
9. 6 cm.
10. AC bells, buzzers, DC bells, door intercom and electric door openers etc.
44
EE 022
ELECTRICAL INSTALLATION 2
TEST 3
SOLUTION:
1. Three-phase AC connection.
2. The supply connection branches off from a distribution cable parallel to the house and
is taken inside the house through a conduit. The cables must be laid in flexiblearmoured plastic conduits which must be laid as close as possible to the overheadcable support and must end in the supply fuse box. The cables must be 1.5 m longer
than the flexible armoured-plastic conduits.
3. Fixing areas are areas that accommodate metering devices. Fixing areas I, II and III.
5. No.
8. 60 - 80 cm.
9. Sequence: soil, yellow marker, soil, cover brick, cable, sand bed.
10. The current flows through the coil. The armature is attracted and hits the bell. The
current is interrupted by a contact which is normally closed. Therefore, the armature
drops off. This process is repeated.
45
EE 022
ELECTRICAL INSTALLATION 2
TEST 4
SOLUTION:
2. "Inside connection" is the cable between the overhead-cable terminals and the supply
connections.
5. In the protective area (0.6 metres on all sides of a bath and 2 metres from floor to
ceiling). Exceptions: fitted switches for water heaters and socket outlets with
transformers up to 25 VA.
7. Only if their current rating is corrected by a factor dependant on the temperature. This
relationship can be found in the appropriate standards.
9. The cable trench is dug and is filled to a depth of 10 cm with bedding material or sand.
The cable is laid so that there is some resilience in case of changes of length and is
covered by bricks before filling in the cable trench. A yellow marker is laid about 30 cm
below the surface.
46
10.
47
KEY TO EVALUATION
PER CENT
MARK
88 100
75 87
62 74
50 61
0 49
48