IN THIS ISSUE
Vol. 28, No. 2
July - September 2005
- An Overview
Mobile Crushers
10
Construction Blasting
12
17
18
22
24
26
30
Kaleidoscope
230/115kV GIS energized
32
33
35
New Orders
38
40
43
44
Focus
As leaders in Engineering and
Construction, L&T is one of the largest
consumer of aggregates and sand for its
various construction activities. The Quarry
and Crushing Operations Dept. which
takes care of this function, is fully geared
to meet the ever-increasing needs of
aggregates mainly for road construction and
other infrastructure development projects.
Quarry Operations
Way back in 1968 ECC felt the
need to have its own quarries for
meeting the requirement of quality
boulders and aggregates for civil
construction projects in and around
Madras and a small beginning was
made in this direction by forming a
Quarry
Department.
The
Department has since then grown
by leaps and bounds, spreading its
wings all over India and
neighbouring countries like Nepal
and Bhutan.
In quantitative terms, with a base
of 0.085 million-ton aggregates
during the late 1960s to 2.00 million
tons in the year 2000 and over 6.5
million tons at the end of 2004-05
ECCs production capacity has
recorded phenomenal growth.
Some of the landmark
structures built during 1968-1972
Editor
V.S. Ramana
Editorial Team
K. Sridharan
Alexander Benjamin
V D S Prasad
V. Ramesh Kumar
Ashwin Chand
V. Eswar
Subha Anand
Photography
V.S. Natanavelu
Cover Design & Layout
Sanka Graphics Pvt. Ltd., Chennai-18
HCL-Malanjkhand Project
For Asias biggest opencast
copper mines at Malanjkhand
(Madhya Pradesh) for Hindustan
Copper Limited, ECC executed rock
excavation and removal of
overburden. The open-pit mining
extended over a length of 2.2 km
View of a stone crushing plant under erection
Explosives Engineering
Construction blasting by its very
nature is risky and hazardous work.
In terms of the hazards they pose,
explosives are next to nuclear /
biological weapons, but their use in
right proportion, at the right places
and with safety provisions is an Art
and Science which we have mastered
over a period of time. Following are
some of the projects, where most
critical construction blasting was
carried out by ECC:
Various grades of stones dumped in sea as a part of breakwater construction
at Project Seabird, Karwar
Project Seabird
For the breakwater construction
at Project Seabird for Indian Navy in
Karwar, over 8 million tones of rock
mass was quarried from the
Aligadde Hill within the project site,
on the basis of 1 metre of
breakwater consuming approximately 1600 tons of stone.
Approximately 4 million cu.m. of rock
A multi-pronged strategy to
outsource technology, ensure worldclass quality and production, safety
and economy has been adopted.
This is monitored at H.Q. level, which
guides and motivates the staff to set
targets and achieve them.
P.K. Govindaswamy
Sr. DGM & Head
Quarry & Crushing Operations
Quarryology
The Art & Science of Quarrying Stones
Aggregate industry is in a state
of growth sparked by the demand
of infrastructure developmental
projects. Aggregates are used in
nearly all residential, commercial and
industrial buildings and in roads,
highways, bridges, railway ballast,
dams, airports, water and sewage
systems and tunnels.
Construction of One Kilometre of
four lane National Highways requires
40,000 Metric tons of aggregates.
Many house owners realize that
construction of an average 3
bedroom house requires 50 tons of
aggregates and construction of one
average size hospital or school
requires 15,000 tons of aggregates.
Quarry operations
The
quarrying
profession
Crushing operations
The process is simple - make big
rocks into little rocks. With the
Aggregates stockpile
RMC
Construction industry has taken
a giant leap forward with the
advent of city-based ready-mix
concrete (RMC) plants catering
mainly to office/commercial
complexes and industrial projects.
Captive quarries with crushing plants
have become an essential support
facility for RMC plants to prevent
manipulation of aggregate prices by
some unscrupulous suppliers and to
ensure quality and steady supply. We
have successfully established such
quarry and crusher facilities in
Bangalore and Hyderabad and are
Crusher Sand
Non-availability or restricted
availability of river sand is becoming
a major area of concern for
contractors in big cities. Crushed
stone sand has become an accepted
substitute for river sand and we are
the first in the industry to introduce
impactors to produce it in our
captive crushing plants in Bangalore
and Hyderabad .
Looking ahead
In line with the Managements
long term strategy, we have chalked
out plans and initiated steps to
acquire additional quarry areas
wherever possible. We are scouting
for and blocking potential stone
deposits not only for RMC plants but
also for prospective mega projects.
With increasing transport leads to
plants, operational efficiency at the
quarry and processing need constant
fine tuning and it has become a must
for us to manage quarries within
accepted norms and efficiencies.
Further, in view of depleting stone
resources and increasing difficulties
in getting clearances, we have to
B.S. Ananthamurthy
Regional Quarry Manager, Hyderabad
Mobile Crushers
Going places producing aggregates
Stationary primary crushers, as
the name suggests, are crushers
permanently located on site, often
some distance from the quarry, mine
or workplace, and serviced with rock
by a system of transportation
through trucks or lorries. However,
there is a problem with this type of
installation - that is the cost of
transportation, which can sometimes
exceed more than half of all costs
(drilling, blasting, loading, crushing,
etc).
With a need to increase efficiency
and reduce costs, mine and quarry
owners have, rightly, seen
transportation as an area where cost
reductions are possible. These
savings have been achieved by
moving the permanent primary
crusher into the quarry/pit, thereby
reducing the haul distance, and
replacing the conventional methods
of transportation with newer ones.
This triggered the thought, Why
not eliminate the haul (and the
haulers) altogether? which paved
the way for mobile crushing
equipment.
10
R. Venkatramanan
Manager (Crushing)
11
Construction Blasting
The Art and Science of Creative Breaking
No construction is possible
without causing some amount of
destruction. Minimal destruction
and least possible damage to
environment are the guiding
principles for the practitioners of
Explosives Engineering.
When
mishaps
involving
explosives occur, they are often well
publicized and criticized, whereas a
great majority of blasting
operations, even the most
challenging ones, that pass off well,
go
unacknowledged
and
unappreciated.
Negative perceptions about
blasting can greatly affect
construction work. Many projects
are either delayed or stopped in
their tracks by pressure groups who
are genuinely concerned over
possible environmental hazards but
not well-informed about the safety
measures taken by the quarry
operators.
Challenge
For engineers, blasters and
project supervisors, managing risks
associated with blasting is becoming
an ever-increasing challenge,
particularly when it is to be carried
out in populated areas. In some
cases, owners and engineers simply
avoid the risk of blasting by
specifying that only mechanical
methods of breaking should be
used, even at the cost of delay and
increase in project cost.
It is true that by its very nature
blasting is hazardous work but most
of the times, the possibility of a mishap
and its consequences are exaggerated
by people with vested interests and
ulterior motives. Stringent ecologyrelated regulations, overzealous nongovernment organizations and
unfounded fears of vibrations and
stone missiles make the job of a
Blasting Engineer tense and
challenging.
Trenching operations
Trenches are excavated to
accommodate pipelines and cables
for industrial and domestic purposes.
Very often, this is done in crowded
residential/business areas or where
other product pipelines already exist.
One such example is the SidhpurSanganer Pipeline (SSPL) Project
where two charged oil pipelines
were situated at a horizontal distance
of 6 m and 12 m respectively.
Incidentally, the other neighbor
pipeline was also laid by ECC under
the Kandla-Bhatinda Pipeline Project.
In such circumstances, any vibrations
in excess of the permissible level, and
fly-rocks can be substantially
damaging. The SSPL job was carried
out successfully without any mishaps
or incidents.
12
Excavation
In any construction project
excavation is a major activity. It is
more so in the case of hydro-electric
projects where, when hard rock is
encountered, blasting poses a
challenge for the mining engineer
as it needs to be carried out adjacent
to structures like power house, dam,
etc. At the Kuttiyadi Hydro Project
in Kerala executed by ECC the
powerhouse was just one metre
away from the site of excavation.
Challenging as the work was, it was
not something new to ECC as similar
mass rock excavation work had
already been carried out at
Hindustan Copper Limited, Kaiga
Atomic Power Project, etc. The
Kuttiyadi work was successfully
executed with no record of any
explosives-related mishaps.
Road Excavation
As in other projects, in road
projects too blasting plays a vital role
in excavation activities. Blasting
pattern for a road cut, where special
emphasis is placed on the final rock
wall contour, smooth blasting or presplitting is commonly used. Drilling
with high precision is of utmost
importance for the final result.
Explosives demolition of
structures (Implosion)
Explosives demolition of
structures requires careful planning
and judicious use of explosives and
accurate initiation system.
ECC was the first to introduce /
carry out successful demolition of
structures in the country using
implosion. Some of the projects
One foot thick imported rubber mats being used at HITEC city project for the first time
in the country to cover the blasting and prevent fly rocks
13
Pre-blast Survey
The survey aims at assessing the
immediate environment and
evaluating the impact of blasting on
the environment. In many cases the
pre-blast survey involves interaction
14
15
16
17
Chikhli Quarry
For Shell Hazira Project
Quarry operations at Chikhli
Quarry in Gujarat have been
another success story of ECCs
Technical Cell (Quarry & Crusher
Operations). Forming an important
chapter of the story is Chikhli
Quarrys contribution to the LNG
Terminal Project that ECC executed
for Hazira LNG Private Limited, a
wholly-owned subsidiary of the
18
19
20
21
Geology of Oman
Granitic gneiss is the oldest rock
in Oman that is seen most
extensively in the southeastern part
while limestone of different varieties
is found in the rest of the country.
Limestone rocks are thinly bedded
with varying clay content, black
shale and oyster layers.
Rock Properties
The limestone rocks of Al-Hoti
plateau are formed as a result of
accumulation of organism-like shells
and oysters in the seabed. The Al-Hoti
plateau, where the caves are formed,
belong to the vanished Tethys ocean.
The rock belongs to the geological
era of cretaceous period between 65
and 136 million years ago, just after
the Jurassic Dinosaur disappeared
from the earth.
The rock is grey limestone of
dense variety with dry density of 2.65
to 2.70 Kg/M3, compressive strength
of <125 mpa and hardness of 5 in
Mohs scale of hardness. The
abrasion value is < 30 and crushing
strength 150 Kn.
Entrance
The age of the Stalactites and
Stalagmites inside the cave can be put
at 100,000 years. This cave is a good
example of the subterranean wadi
system. It has two big accessible
entrances: The Upper Alhuta Entrance
and Lower Al-Fallah Entrance.
The Upper Alhuta Entrance lies
on the elevated plain, approximately
1,040 m above sea level. The lower
Al-Fallah Entrance lies approximately
810 m above sea level. The maximal
difference in altitude inside the cave
is 230 m; it is the difference between
the main entrances. Both the
entrances seem to be having approx.
20 30 m free drops. The main
passage between the two main
entrances is about 4.4 km long.
Cave Tunnel
22
Developing Caves
The cave development work
included supply of electricity for
lighting, erection of access pathways
(utilizing concrete, iron frames and
sheets, stainless steel, handrails, etc.)
and lobbies for an easy access to the
underground and rough caves. As
an added attraction to the visitors a
mini theatre with special sound
effects is also being built inside the
caves.
Hurdles
Great care had to be taken in
developing and constructing the
Vibration monitoring
studies outside and
inside the caves
during blasting
24
J. Malavan
Construction Manager (Civil)
S.A. Thiyagarajan
Blasting Incharge
25
Synopsis
26
Quarry selection
Ideally selection of the quarry for
armour stone production should be
based on trial blast yield analysis,
which matches closest to the
specification requirements of the
proposed breakwater. This approach
is aimed primarily at minimizing
contractual disputes, blast related
problems and wastage handling. In
Suggested guidelines
Face mapping
Influencing Factors
Two main factors - controllable
and uncontrollable - influence
armour stone production during
blasting. The uncontrollable factors
are the geological characteristics of
the rock mass. The controllable
factors include drilling and blasting
geometry and explosive properties.
Work harbour constructed using different grades of stones - Project Seabird, Karwar
27
The
New
Tirupur
Area
Development Corporation Limited
(NTADCL) awarded the Tirupur Water
Supply & Sewerage Project to ECC
Division of L&T in November 2002.
The scope of work comprised of
laying pipelines over a distance of
about 500 km, which involved
excavation of five lakh cu.m. of hard
rock.
Approximately 75,000 cu.m. of
hard rock was to be excavated in
congested areas which, for better
pace and control of operations, were
divided into separate sites instead of
one single stretch. Around 60-70
percent of these sites were located
in very crowded localities. The
blasting operations were to be
carried out in close proximity of
health centers, schools, houses,
public roads and other important
sensitive structures.
28
N. Devan
Senior Construction Manager
Under
the
able
guidance of Mr. A.
Ravikumar, the quarry
team helped complete
the revetment work well
within the stipulated
time.
Arabinda Guha
Regional Manager
Ahmedabad
29
The
leading
multinational software
organization Microsoft
decided to set up one
more establishment,
Microsoft-Phase II, at
Hyderabad and awarded
the job to ECC.
The site was situated in
Gachi Bowli area of
Hyderabad City and was
surrounded by permanent
and important structures
like Microsoft-Phase I
building, public roads and
batching plant and
temporary office of L&T,
the distance of which
from the proposed
blasting site was 30
metres.
For
the
foundation
of
the
proposed structure, we
needed
to
blast
Tight controlled rock blasting carried out adjacent to
sensitive IT structures
Control of Fly-rock
During blasting
operations, small pieces
of rocks are likely to fly
upto a distance ranging
from a few metres to
Controlled rock blasting carried out adjacent to road
30
Muffing operation to control fly rock using one foot thick rubber mat
with
imported
seismographs.
Instantel
Control of Vibration
Ground
vibrations
are
generated when a part of explosive
energy, which is not utilized in
formation of fractures, spreads
through the rock strata. Presplitting and line drilling are
efficient techniques to control or
minimize such blast-induced
ground vibrations. At Microsoft
Phase II, pre-splitting method was
adopted. Ground vibrations at
different locations were measured
Controlled blasting for foundation work
31
Engineered by EDRC
EDRC,
Chennai
provided
complete engineering solutions for
the entire scope of work involving
design and detailed engineering for
new S/S, adequacy check of the
existing S/S and upgradation, vendor
sourcing, vendor drawing review of
equipment supplied by international
manufacturers using latest software,
apart from providing many other
unique engineering solutions.
32
Dismantling of structures/
equipments - 2250 tons, Dismantling,
salvaging and re-erection of
structures /equipments 1115 tons
Dismantling of Refractory materials
- 4405 tons, Fabrication & Erection
of BF Shell 414 tons, Fabrication
and Erection of Structures 1250
tons, Erection of Equipments
(CI Stoves/UH Coolers/Bustle Main etc)
1350 tons, Enabling Steel used
(Excluding Slabs) 170 tons, Erection
of Refractory 2900 tons, Excavation
1200 Cum, Concreting 840 Cum
Reinforcement 63 tons Dismantling
of RCC 252 Cum
List of Major P&M deployed
included:
One 750 t cap. FMC Link Belt
Crane, two 75 t cap.TATA cranes,
one 80t cap. tyre mounted crane,
one 30t cap. tyre mounted crane,
three 8t cap.Hydra cranes, one 75t
cap trailor , four 40 t cap. trailors, 6
Nos. 9t cap. truck/dumpers, four
300 Cfm cap. Compressors, 96 Nos.
MIG/Welding Generators, 11 Nos.
winches (Capacity - 10/7.5/5/3 t) and
two Fork Lifts.
33
34
LAKSHYA
Revenues
We achieved an impressive
revenue growth of 37% on the back
of 32% growth posted in 2003-04.
Over the last three years our order
book has grown at a compound rate
of 21%, while revenues have grown
at a compound annual rate of 33%.
For the year under review, sales &
service income stood at Rs. 13,269
crores against Rs. 9,807 crores last
year. Profit before tax (after interest
and depreciation charges), increased
by 67% to Rs. 1,286 crores from Rs.
769 crores. Profit after tax was up 85%
at Rs. 984 crores from Rs. 533 crores.
Even if we exclude income from
the sale of shares of Ultratech
Cement, the profit before tax at Rs.
933 crores and profit after tax at Rs.
631 crores show an impressive
growth of 21% and 18% respectively.
Order booking for 2004-05 was
Rs. 14,931 crores, and order backlog
on 31st March, 2005 was Rs. 17,808
crores.
Mr. A.M. Naik, Chairman & Managing Director, L&T, addressing the AGM
35
New Initiatives
Portfolio review remains a
continuous process in your Company,
and we have disinvested our stake
in Sharp office equipment business,
36
Talent Acquisition
All our plans hinge on our ability
to attract, retain, and develop the
skills of our manpower resources.
Talent identification and acquisition,
career planning and succession
planning are receiving priority of the
senior management
Company.
of
your
37
New Orders
Barbados Stadium
L&T has won an order valued
over Rs. 211 crore from World Cup
Barbados Inc (WCB), West Indies, for
the re-construction of the famed
Kensington Oval in Barbados. The
engineering, construction and
technology major will have total
responsibility for the construction
and execution of the project and
ensure
that
the
rigorous
specifications of the International
Cricket Council (ICC) are met before
the first ball is bowled at the historic
stadium.
L&T was initially selected by the
WCB in February 2005 as the
Construction
Management
Consultant. Its role was primarily
to carry out project planning,
formulate construction methods,
evaluate tenders and finalise
domestic sub-contractors during preconstruction period. This project
consultancy was successfully
completed by L&T at a value of Rs.
1.3 crore. Soon after, the WCB also
assigned the construction services to
L&T as General Contractor.
The entire project will be
completed by L&T in 16 months (by
January 31, 2007). For this purpose,
the entire scope of work has been
split into several packages, and
domestic sub-contractors under the
overall responsibility of L&T will
execute these packages. In addition,
New Hyderabad
International Airport
L&T has bagged an EPC
(Engineer-Procure-Construct)
contract valued at Rs. 495 crore for
38
14 workmen rescued
from Subansiri Tunnel
Close to midnight on August 7,
2005 a landslide above the adit to
the surge chamber at ECCs Lower
Subansiri Hydropower Project in
Arunachal Pradesh left tunnel
equipment viz., excavator, concrete
pump, hydraulic drill jumbo,
shotcreting machine, transit mixers,
DG sets and ventilation fans along
with cables, pipelines, air receiver
tanks, etc. buried under
a100metre high hill mass.
Fortunately, however, 14 of ECCs
workers on night shift were safe but
trapped in the adit tunnel where
power supply too was cut off, as the
cable had been severed by the
landslide. ECC-ites trapped inside
were Mr. P.D. Pressana Kumar, Tunnel
Foreman, Mr. Sadan Yadav,
Supervisor, Mr. Pandi Raja, Excavator
Operator, Mr. Srinath Singh,
Electrician and ten casual labourers
of the tunnel rock supporting crew.
Shift engineers from nearby
workstations rushed to the accident
spot and made makeshift
arrangements for the restoration of
power supply. The rescue operations
commenced within 15 minutes of
the landslide. High capacity
excavators, wheel loaders and
40
Hospital, Gogamukh
for further treatment.
One of the rescued
workers, electrician
Srinath Singh, said:
We were all huddled
together. All were silent
except for one or two
questions. We were
mostly wondering
about our fate. Pradip
Kumar Nath, another Rescued workers with the rescue team
rescued
worker,
echoed him, We were totally cut
We salute all those involved in the
off, unable to even hear what was rescue act in this saga of human
going on outside. It was only around resilience, faith and team work,
12 pm today that we could faintly toiling throughout the night and
hear the sound of machines at work day spanning 19 continuous hours,
just outside the tunnel.
fighting against all odds and
successfully coming out from the
J. Henry Robertson, executive
crisis.
director of the Subansiri Basin of the
National Hydro-Electric Power
Corporation (NHPC), said work on
the 2000 MW project would continue
V. K. Nagyan
as usual. The accident will not
DGM (Projects)
hamper work. It was a natural
calamity over which we have no
Rakesh Kumar Jha,
control. We are just happy that
Planning Engineer
nobody was harmed.
Subansiri Project Site
41
Modern Building
Maintenance
Systems
Mr. K. Parthiban, Manager Maintenance and Mr. S. Virapan,
Engineering Manager, BUCC,
presented a paper on Modern
Building Maintenance systems
organized by National Council for
Cement and Building Materials
during April 26-27, 2005 in Chennai.
The progamme was well attended
by participants from various
government and private sector
organizations.
42
only means to
understand the
problems
in
concrete
at
green
and
hardened stages.
A
holistic
assessment of
concrete structures by NDT methods
requires a sound knowledge of
structural engineering.
The lecture was well received by
the audience that included members
of the Chapter, practising engineers,
scientists, faculty from engineering
colleges and students.
S. Virapan
Seismic Base
elected Secretary Isolation on Noncum Treasurer
Engineered
IPA Chennai Chapter
Structures
Mr. S. Virapan, Engineering
Manager, Building Utilities and
Competency Cell was unanimously
elected Secretary cum Treasurer of
Indian Plumbing Association,
Chennai Chapter at a meeting of its
members on March 21, 2005 in
Chennai.
Mr. J. P. Nayak (left) receives the Superbrands trophy from Mr. Fraful Fatel,
Union Minister for Civil Aviation.
Designed by Sanka Graphics Pvt. Ltd., Chennai and printed by Srusti Ads & Communications, # 37, Venkatramana Colony, Khairatabad, Hyderabad - 500004.
Mobile : 98850 911199. Edited by Mr. V.S.Ramana for Larsen & Toubro Limited - ECC Division, from ECC - HQ., Manapakkam, Chennai - 600 089. The views expressed
in this magazine are not necessarily those of the management of Larsen & Toubro Limited. The contents of this magazine should not be reproduced without the written
permission of the Editor.
Not for sale - only for circulation among the employees, business associates and customers of ECC - L&T's Construction Division.