Anda di halaman 1dari 7

Ralph C. Whitley Sr.

From: Ralph C. Whitley Sr. [backflow2@verizon.net]


Sent: Tuesday, May 25, 2010 9:23 AM
To: backflow2@verizon.net
Cc: HorizonSupport@oegllc.com; home.news@thetimes.co.uk; info@deepwater.com; 'Innovative Technology'
Subject: URGENT FOR ALL TO REVIEW 052510 @ 0923 AM Eastern 2:23 PM England
Attachments: Friction Plug Design.JPG; Kuwaiti Oil Fires Techniques for Controll 1991 7.jpg; Plugs Kuwait Pat Nos.JPG

FOR ALL TO REVIEW:

Please see http://sfawbn.com/news/?p=1933 as it would appear the LIVE FEED from the BOP area might not show
TRULY what is happening and pipes splitting perhaps above or below the BOP. My concern now would be the BOP
section of pipe underneath same BEING BENT with this push of materials causing it to fracture then blowout below the
BOP but such could perhaps allow a ROV with circular cut saw 50 inch like owned by Oceaneering to cut CLEAN and
lift the BOP away exposing the pipe riser then with the FRICTION PLUG already laid out on the surface the crane and
ROV could guide it quickly to the bottom and the great length, weight with extra steel round RINGS onboard could
allow the ROV to position OVER the gushing pipe with downward tip sharp then tapering larger to be dropped straight
down rapidly sealing the RISER unless the CPP with PIPE AND SHUTOFF is available. Such would require TWO
CRANES with TWO UNITS….. One Crane to lift away or take tension on the BOP while ROV makes the CUT clean just
under ROV then the second Crane would have lowered the CPP with Pipe and Shutoff already inches above the ocean
floor waiting to be moved over the RISER since the BABIC CPP WITH PIPE AND SHUTOFF would possibly have a
beveled thick washer welded to the pipe PLUS a sleeve of PIPE leaving only 1 inch space OR EVEN 3 INCHES to be
slipped over the riser sealing the flow of oil and gas then sending SAME up through the pipe past the shutoff and out of
the flange going toward the top where perhaps there would be a 20 foot section of flexible pipe with flanges and
shutoff’s to join surface piping.

All concentrating on the VERTICAL CONNECTION WITH CPP HAVING PIPE, SHUTOFF VALVE, FLANGE ALREADY
LOWERED ONCE THE BOP WAS CUT BELOW SAME. The PIPE MAY BE CRIMPED OVER AND DIFFICULT SO THE KEY IS
IMMEDIATELY TAKING XRAYS OF THE PIPING BELOW BOP.

NEW TASK FOR USCG XRAY --- FIND OUT IF THE BOP TOP HAS A FLANGE WHICH CAN BE MADE UP ABOVE ON LAND,
WELDED WITH SHUTOFF AND FLANGE OUTGOING TO ALLOW UNHOOKING BOP TOP FLANGE WITH THE SPECIAL
RISER PIPE FLANGE REMOVED THEN NEW RISER FLANGE AND SHUTOFF PLUS ANOTHER UPWARD RISER FLANGE

1
ATTACHED TO FLEXIBLE HOSE. I see this proven in a pool with high pressure water and air. It should work just like
the first flange connection of riser pipe 21 inches to the BOP or shortly above same.

Some PHOTOS showed the RISER CONNECTION BENT OVER BRUTALLY PUTTING PIPING ON THE GROUND. SUCH
MAY HAVE BENT THE RISER PIPE A LITTLE UNDER THE BOP CAUSING FRICTION TO CUT AWAY AT THE PIPE FROM
INSIDE WHICH MAY MAKE THAT SECTION SUPER THIN AND FRACTURE EASY. FRACTURE WITHOUT CRANE AND
EQUIPMENT ON STATION COULD LEAD TO IXTOC 2 IN THE GULF FOLKS.

Now is the time to scramble, make up the Friction Plug WEIGHTED RISER SEALER to lower down over the riser just
clearing then CUT THE GEAR UNIT FREE FALLING STRAIGHT INTO THE RISER TO JAM PIPE SHUT. NOT TOO MUCH IN
SIZE OR IT MAY SPLIT THE RISE PIPE WHICH IS HOPEFULLY HEAVY WALL STEEL.

Second OPTION would be having the CPP with Pipe and Shutoff ready to also insert over the riser if XRAY from two
sides does not show any DISTORTION. Check with USCG and NAVY DIVERS on same.

PRAY FOR NO ELECTRICITY STRIKES FROM CLOUD FORMATIONS IGNITING THE SCENE BELOW !

Ralph Charles Whitley, Sr. CFCO32631


Backflow Prevention, Inc.
4532 W. Kennedy Blvd. PMB-276
Tampa, Florida 33609-2042 USA
Phone: 813-286-2333
SCRIBD: ralphwhitleysr
052510
WEB PAGE: http://www.scribd.com/ralphwhitleysr

From: Branko R Babic [mailto:babic.branko@virgin.net]


Sent: Sunday, May 23, 2010 1:19 PM
To: backflow2@verizon.net; 'President Barack Obama'; president@whitehouse.gov; bobby.jindal@la.gov; 'charlie crist'; HorizonSupport@oegllc.com;
info@deepwater.com; 'Innovative Technology'; 'CFO Alex Sink'; storms.ronda.web@flsenate.gov; bill@billnelson.senate.gov; 'Bill McCollum'
Subject: RE: MAYDAY MAYDAY MAYDAY TWO - Flange to Flange BALL VALVE ALLOWS SHUTTING DOWN OIL SPILL without ROV Welding.

2
From: Ralph C. Whitley Sr. [mailto:backflow2@verizon.net]
Sent: 23 May 2010 14:27
To: 'Branko R Babic'; President Barack Obama; president@whitehouse.gov; bobby.jindal@la.gov; 'charlie crist'; HorizonSupport@oegllc.com;
info@deepwater.com; 'Innovative Technology'; CFO Alex Sink; storms.ronda.web@flsenate.gov; bill@billnelson.senate.gov; 'Bill McCollum'
Subject: MAYDAY MAYDAY MAYDAY TWO - Flange to Flange BALL VALVE ALLOWS SHUTTING DOWN OIL SPILL without ROV Welding.
Importance: High

Branko R Babic
53A Middle Way
Summertown
OXFORD OX2 7LE
UK
Tel/Fax: +44 (0)1865 310772
E-mail: babic.branko@virgin.net
Visit our www:
http://homepage.virgin.net/babic.branko/

Dear Ralph,

Thank you very much for your persistence. The people who ought to know about the availability of the counter Pressure Plugs (CPP) , do know about the
technology but they refuse to use it. I do not know why the engineers refuse to stop the flow of escaping oil but they clearly ARE avoiding the use of my
patented technology.

The flow of specific information from the engineers directly involved in containing the damaged oil well is limited so we can only guess as to how best to apply
the CPP. Depending on the nature of the effusive problem as to which plug would be used but even in the worse case scenario, where the pipe in the ground has
fractured or has longitudinal cracks in it, has a solution, see “Friction Plug”. In Kuwait in 1991, there were old installations with cracked pipes which I considered
a damage limitation and deigned a long heavy plug that is inserted into the damaged pipe and the CPP lowered below the crack. The tolerances between the
internal diameter of the riser ducting oil and the diameter of the “Friction Plug” was small. The frictional forces of any flowing oil in the gap between the plug
3
and the pipe was very high. The friction provided a high back pressure and prevented the escape of anything but small volumes of oil. This last resort solution
was intended as a loss, loss situation but one which prevented the escape of all but a small quantity of oil, giving engineers access to the site and time to make
decision on how best to tackle the problem.

Anything which reduces the escape of oil from the Gulf of Mexico well would be an advantage but my plug designs will work.

I do not know why the engineers will not use the CPPs.

Kind regards,
Branko R Babic.

This E-mail is from Branko R Babić. The E-mail and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom they are addressed. Any unauthorised dissemination or copying of this E-
mail or its attachments and any use or disclosure of any information contained in them, is strictly prohibited and may be illegal. If you have received this email in error please call telephone 01865 310772 and delete it from your system.
MAYDAY MAYDAY MAYDAY TWO -- FLANGE TO FLANGE BALL VALVE ALLOWS SHUTTING DOWN OIL SPILL WITHOUT
ROV WELDING !

Ladies and Gentlemen:

Earlier we have continuously stated OVER AND OVER that the Branko R. Babic Counter Pressure PLUG or CPP WITH
OR WITHOUT THROUGH PIPING AND SHUTOFF VALVE would easily shut down the Runaway Well in the Gulf of Mexico
where Deepwater Horizon CRIME SCENE is located.

After sleeping over 8 hours on the problem last night it was revealed that the Actual Riser Pipe is in 90 foot sections of
HMF-ClassH 21 Inch Riser 90 foot FLANGED SECTIONS. See picture:

4
NOW THINK OF THIS. Take one 90 foot
SECTION and cut away the Bottom and
TOP flange, weld a 15,000 PSI BALL VALVE
PERHAPS WITH ROUND WHEEL FOR ROV TO
TURN OFF. Use Oceaneering ROV to CUT
BOLTS AND NUTS ON ONE SECTION AWAY
FROM BOP OR ON TOP OF BOP THEN PUT
ONE LONG BOLT THROUGH WELDED TOP
NUT TO BODY OF FLANGE TO KEEP IN PLACE
THEN TAKE IT TO THE SITE, REMEMBERING
WHICH WAY IS INLET SIDE AND LOWER TO
OCEAN FLOOR WHERE ROV WILL POSITION
AND ATTACH NUTS PLUS WASHER UNTIL
ALMOST DOWN TO FLANGE CONTACT. THEN
SWING UNIT OVER IN POSITION WITH BALL
VALVE AND UPPER FLANGE WIDE OPEN AND EVEN
ATTACH PERHAPS A SHORT 10 FOOT FLEXIBLE STEEL
PIPE SO THE PRESSURE AND OIL CAN STAY AWAY
FROM THE CONTACT FLANGE THEN ROTATE OVER THE
PROPER LOCATION AND PUSH DOWN INTO PLACE.

5
ONCE IN PLACE INSERT NEW LONG BOLTS WITH ROV
USING DEEP WELL SOCKET TO HYDRAULICALLY TIGHTEN
SAME THEN LEAVE THE LONG BOLT IN PLACE TIGHTENING
NUTS ON SAME UNLESS DAMAGED THEN THE TACK WELD
CAN BE CUT AWAY AND NEW BOLT INSTALLED.

ONCE THIS IS SEATED THEN ROV CAN ATTACH PIPING TO


THE FLEXIBLE STEEL PIPE WHICH HAS A SHUTOFF VALVE
AND FLANGE AT THE TOP TO HOOK UP LINES TO THE
SURFACE.

ADVANTAGE --- NO GAS, OIL, WATER FLOWING INTO THE GULF


IN A SPILL ATTITUDE. NO HYPERBARIC CHAMBER AND ROV WELD.
YOU CAN CHECK ALL WELDS ABOVE GROUND WITH XRAYS THEN
BE SURE IT WILL NOT LEAK OR FRACTURE.

BENEFIT ---- PRICELESS ! AND SAVING THE GULF AND EAST COAST
PLUS ISLANDS !

YOU CAN DO IT WITHIN 8 HOURS ALSO FOLKS…..ONE SECTION OF RISER


SACRIFICED BUT THINK OF REMOVING ONE 90 FOOT SECTION CUT AWAY
WITH THE CHOP SAW AT A POINT WHERE THE FLANGED BALL VALVE CAN
BE INSERTED IMMEDIATELY AND SAVE THE GULF SHUTTING DOWN THE
SPILL SUPER FAST.

THINK ABOUT IT BP AND GET THE EXPERTS TO LOOK AT THE SECTION


IN A YARD THEN THINK OF ATTACHING VALVES WELDED ON THE TWO
SIDE PIPES WHICH USED TO ALLOW HYDRAULIC FLUID TO THE BOP AND
ALLOW MUD PERHAPS TO THE UNIT. THAT TOO CAN HAVE NEW HOOKUPS TO ALLOW USE IN THE FUTURE WITH
LINES FROM THE SURFACE IF DESIRED. SEE http://www.scribd.com/ralphwhitleysr

MAYDAY MAYDAY MAYDAY TWO -- FLANGE TO FLANGE BALL VALVE ALLOWS SHUTTING DOWN OIL SPILL WITHOUT
ROV WELDING !

6
Ralph Charles Whitley, Sr. CFC032631
Backflow Prevention, Inc.
4532 W. Kennedy Blvd. PMB-276
Tampa, Florida 33609-2042
Phone: 813-286-2333
Skype: ralphwhitleysr

052310 @ 9:26 AM Eastern or 14:26 PM UCT England