Anda di halaman 1dari 24

Question 1 of 20

5.0/ 5.0 Points

What don't you do during review preparing?


A. Logging and sending to conductor all defects found

B. Gathering all comments and questions from reviewers

C. Preparing agenda and reviewing facilities

D. Identifying reviewers

Question 2 of 20

5.0/ 5.0 Points

What is the MAIN objective when reviewing a software deliverable?


A. To identify spelling mistakes in a requirements specification.

B. To identify potential application failures by use of a test specification.

C. To identify standards inconsistencies in the code

D. To identify defects in any software work product.

Question 3 of 20

5.0/ 5.0 Points

What is difference between Verification(VER) and Validation (VAL)?


A. VER focuses on "building the right thing" while VAL focuses on "building the thing
right"
B. VER focuses on testing while VAL focuses on reviewing

C. VER focuses on "building the thing right" while VAL focuses on "building the right

thing"
D. They have same objectives and focuses

Question 4 of 20

5.0/ 5.0 Points

Which is not a review output?


A. Review report

B. Filled-up checklist

C. Updated work products

D. Meeting minutes

Question 5 of 20

0.0/ 5.0 Points

How many main steps are there during Verification process?


A. 4
B. 5
C. 3
D. 2

Question 6 of 20

Which is not a step during "Perform Peer Reviews" process?


A. Prepare for Peer Reviews

B. Analyze Peer Review Data

5.0/ 5.0 Points

C. Perform Verification

D. Conduct Peer Reviews

Question 7 of 20

5.0/ 5.0 Points

The purpose of Validation is to assure that selected work products meet their specified
requirements
True
False

Question 8 of 20

0.0/ 5.0 Points

Peer review is one of the step during the Veririfcation process?


True
False

Question 9 of 20

0.0/ 5.0 Points

The project team can find defects, omissions, and educate team members by which of the
following peer-review techniques?
A. Formal inspection

B. Walkthrough

C. Technical review

D. Audit

Question 10 of 20

Which is a Validation product in Fsoft software process?

0.0/ 5.0 Points

A. Delivery schedule

B. Test cases

C. Review schedule

D. Test plan

Part 2 of 2 - Extra_Quiz_Lession2
Question 11 of 20

31.67/ 50.0 Points


5.0/ 5.0 Points

Testing is done to prove, that


- The software works
- The software doesnt work
True
False

Question 12 of 20

1.67/ 5.0 Points

Defects are found by which of the following activities?


A.Reviewing

B.Designing

C.Inspection

D.Testing

Question 13 of 20

Which document is the base of performing system test?

0.0/ 5.0 Points

A. User Requirement

B. Coding

C. Software requirement specification

D. Architechture design

Question 14 of 20

5.0/ 5.0 Points

What must testers do when project has Change Requirements?


A. Update Test Case

B. Re-test

C. Regression Test

D. All above

Question 15 of 20

0.0/ 5.0 Points

What is Defect rate?


A. Weighted defects/ project size (in UCP)

B. Weighted defects found after release/ project size

C. Weighted defects/ Test effort

D. Number of test cases executed

Question 16 of 20

5.0/ 5.0 Points

Which is not a testing type?


A.Functional testing

B.Performance testing

C.White box test

D.Unit test

Question 17 of 20

5.0/ 5.0 Points

Which of the following should NOT normally be an objective for a test?


A. To find faults in the software

B. To debug defects

C. To assess whether the software is ready for release.

D. To demonstrate that the software doesnt work.

Question 18 of 20

5.0/ 5.0 Points

Which document identifies and describes test scenarios that will be implemented and executed?
A. Test Plan

B. Test report

C. Test script

D. Test case

0.0/ 5.0 Points

Question 19 of 20

What will Test leader do in Definition phase?


A. Write test Plan

B. Write test case

C. Write test report

D. Prepare test data

5.0/ 5.0 Points

Question 20 of 20

In formal review, Rework: fixing defects found typically done by _________


A. Reviewer

B. Conductor

C. Author

Question 1 of 20

5.0/ 5.0 Points

What is the MAIN objective when reviewing a software deliverable?


A. To identify potential application failures by use of a test
specification.
B. To identify standards inconsistencies in the code

C. To identify spelling mistakes in a requirements specification.


D. To identify defects in any software work product.

Question 2 of 20

5.0/ 5.0 Points

Please chose the type of review which is to make sure all objectives of the
current stage are met, all its work products have been approved as
planned, and project is able to proceed to the next stage
A. Post-mortem review
B. Contract review
C. Quality gate review
D. Code review

Question 3 of 20

5.0/ 5.0 Points

What is difference between Verification(VER) and Validation (VAL)?


A. They have same objectives and focuses
B. VER focuses on "building the thing right" while VAL focuses on
"building the right thing"
C. VER focuses on "building the right thing" while VAL focuses on
"building the thing right"
D. VER focuses on testing while VAL focuses on reviewing

Question 4 of 20

0.0/ 5.0 Points

In case a meeting required, you do gathering all comments, questions from

reviewers in which reviewing step?


A. Preparing
B. Following up
C. Evaluating review results
D. Executing review & logging defects

Question 5 of 20

0.0/ 5.0 Points

Which is a Validation product in Fsoft software process?


A. Test plan
B. Test cases
C. Delivery schedule
D. Review schedule

Question 6 of 20

Which is not a type of review?


A. Management approval
B. Inspection
C. Technical review

5.0/ 5.0 Points

D. Walkthrough

Question 7 of 20

5.0/ 5.0 Points

Peer review is one of the step during the Veririfcation process?


True
False

Question 8 of 20

5.0/ 5.0 Points

Which is not a step during "Perform Peer Reviews" process?


A. Conduct Peer Reviews
B. Analyze Peer Review Data
C. Perform Verification
D. Prepare for Peer Reviews

Question 9 of 20

0.0/ 5.0 Points

The project team can find defects, omissions, and educate team
members by which of the following peer-review techniques?
A. Audit
B. Formal inspection
C. Technical review
D. Walkthrough

Question 10 of 20

5.0/ 5.0 Points

Which is not a quality control activity?


A. Software testing
B. Audit
C. Software product review
D. Functional specification

Part 2 of 2 - Extra_Quiz_Lession2

45.0/ 50.0 Points

Question 11 of 20

5.0/ 5.0 Points

Which of the following will be the best definition for Testing:


A. The purpose of testing is to demonstrate t hat the program does
what it is supposed to do
B. The goal / purpose of testing is to demonstrate that the program
works.
C. The purpose of testing is to demonstrate that the program is defect
free.
D. Testing is executing Software for the purpose of finding defects to
verify that it satisfies specified requirements
Question 12 of 20

Which document is the base of performing integaration test?


A. Software requirement specification

5.0/ 5.0 Points

B. Architechture design
C. Coding
D. Requirement analysis

Question 13 of 20

5.0/ 5.0 Points

What statement do you consider to be most important?


A. Testing has the primary intent of showing the system meets the
users needs
B. Testing has the primary intent of finding faults
C. All above
D. None above

Question 14 of 20

5.0/ 5.0 Points

Defects are found by which of the following activities?


A.Reviewing
B.Designing
C.Testing
D.Inspection

Question 15 of 20

5.0/ 5.0 Points

Where defects come from?


A. Change requests
B. Misunderstanding
C. Software products
D. All of above

Question 16 of 20

0.0/ 5.0 Points

In which software development phase, the cost of defects is highest?


A. System testing
B. Analysing
C. Designing
D. Coding

Question 17 of 20

5.0/ 5.0 Points

Please chose correct order of below four steps during Defect lifecycle?
(1)Log defects
(2)Fix defects
(3)Analyze defects
(4)Re-test
A. 1-2-3-4
B. 3-1-2-4

C. 3-1-4-2
D. 1-3-2-4

Question 18 of 20

5.0/ 5.0 Points

Test cases are designed based on


A. Software requirement specification.
B. Detail Design document.
C. A & B and test plan document.
D. A & B.

Question 19 of 20

5.0/ 5.0 Points

In formal review, Rework: fixing defects found typically done by _________


A. Reviewer
B. Author
C. Conductor
D. Secretary

Question 20 of 20

Testing is done to prove, that


- The software works
- The software doesnt work

5.0/ 5.0 Points

True
False

Question 1 of 20

5.0/ 5.0 Points

How many main steps are there during Verification process?

A. 2

B. 4

C. 5

D. 3

Question 2 of 20

What don't you do during review preparing?

A. Preparing agenda and reviewing facilities

B. Identifying reviewers

C. Logging and sending to conductor all defects found

D. Gathering all comments and questions from reviewers

5.0/ 5.0 Points

Question 3 of 20

0.0/ 5.0 Points

Which is a Validation product in Fsoft software process?

A. Test plan

B. Delivery schedule

C. Test cases

D. Review schedule

Question 4 of 20

Which is not a step during "Perform Peer Reviews" process?

A. Perform Verification

B. Prepare for Peer Reviews

C. Conduct Peer Reviews

5.0/ 5.0 Points

D. Analyze Peer Review Data

Question 5 of 20

5.0/ 5.0 Points

The purpose of Validation is to assure that selected work products meet their
specified requirements

True

False

Question 6 of 20

Please chose correct order of below four activities?


(1)Conduct Peer Reviews
(2)Analyze Peer Review Data
(3)Perform Verification
(4)Analyze Verification Results

A. 3-4-1-2

B. 1-3-2-4

C. 3-1-4-2

D. 1-2-3-4

0.0/ 5.0 Points

Question 7 of 20

5.0/ 5.0 Points

Please chose the type of review which is to make sure all objectives of the current
stage are met, all its work products have been approved as planned, and project is
able to proceed to the next stage

A. Contract review

B. Post-mortem review

C. Code review

D. Quality gate review

Question 8 of 20

5.0/ 5.0 Points

The project team can find defects, omissions, and educate team members by
which of the following peer-review techniques?

A. Technical review

B. Walkthrough

C. Formal inspection

D. Audit

Question 9 of 20

5.0/ 5.0 Points

Peer review is one of the step during the Veririfcation process?

True

False

Question 10 of 20

5.0/ 5.0 Points

Which is not a type of review?

A. Walkthrough

B. Management approval

C. Technical review

D. Inspection

Part 2 of 2 - Extra_Quiz_Lession2

40.0/ 50.0 Points

0.0/ 5.0 Points


Question 11 of 20

Which is not considered as a defect?

A. Error

B. Bug

C. Issues

D. Leakage

Question 12 of 20

5.0/ 5.0 Points

Testing is done to prove, that


- The software works
- The software doesnt work

True

False

Question 13 of 20

Which of the following will be the best definition for Testing:

5.0/ 5.0 Points

A. The purpose of testing is to demonstrate that the program is defect free.

B. The goal / purpose of testing is to demonstrate that the program works.

C. The purpose of testing is to demonstrate t hat the program does what it is


supposed to do
D. Testing is executing Software for the purpose of finding defects to verify
that it satisfies specified requirements

Question 14 of 20

5.0/ 5.0 Points

Which of the following should NOT normally do in Test Execution process?

A. Execute test follow test case document

B. Study SRS

C. Create test report

D. Create defect list

Question 15 of 20

5.0/ 5.0 Points

A test case includes

A. Action

B. Input data

C. Expected result

D. All above

Question 16 of 20

5.0/ 5.0 Points

Regression testing always involves

A. Using a test automation tool

B. Executing a large number of different tests.

C. Testing whether modifications have introduced adverse side effects.

D. Testing whether a known software defect been fixed.

5.0/ 5.0 Points


Question 17 of 20

Is it necessary to create separete testing environment from develop environment?

A. No

B. Yes

Question 18 of 20

5.0/ 5.0 Points

V-Model is:

A. A testing life cycle model including unit, integration, system and


acceptance phases
B. A software development model that illustrates how testing activities
integrate with software development phases
C. The official software development and testing life-cycle model of ISTQB

D. A software life-cycle model that is not relevant for testing

Question 19 of 20

5.0/ 5.0 Points

Please chose correct order of below four steps during Defect lifecycle?
(1)Log defects
(2)Fix defects
(3)Analyze defects

(4)Re-test

A. 1-3-2-4

B. 3-1-4-2

C. 3-1-2-4

D. 1-2-3-4

Question 20 of 20

0.0/ 5.0 Points

How do you normally rate the severity for a defect which can not be worked
around?

A. Serious

B. Cosmetic

C. Fatal

D. Medium

Anda mungkin juga menyukai