Sequence of work

1. Mapping drawing
- Piping Engineer/Construction Engineer prepare isometric drawing and give
-

to subcon
Drafter prepare mapping drawing (Spool Drawing)
Drafter submit drawing to Document Control PT. JSE
Document Control PT. JSE give to Piping Engineer/Construction Engineer
Piping Engineer review and recheck mapping drawing (spool drawing)
After piping engineer/contruction engineer approve and stamp by PT.JSE
Engineering department, Document control PT. JSE submit to PT.IOT
within true transmital

2. Material Take off


- PT. JSE conduct to prepare MTO by subcon
- Material Control PT. JSE review and approve MTO
- After sign by Material Control PT. JSE, Document Control PT. JSE submit
to PT. IOT within true transmital

3. Material Loading and Unloading


- PT. JSE conduct subcon prepare lifting activity
- Material Control PT. JSE and Quality Control PT. JSE inspect material
-

before loading from PT. IOT


After Inspect and accept by PT. JSE, subcon can take material
Unloading material must coordination with QC Depart and Material Control

4. Fit-Up report
- Subcon PT. JSE prepare fit up report