Anda di halaman 1dari 3

Re: PO n61246X-1000-PO-0234-0005-0046 - ALFA LAVAL - DRAIN

WATER TREATMENT PACKAGE - TEPN comments on 480021


Lukas Dobrowolski to: Bhuvanesh PiskalaSankaran

09.09.2015 08:57

Expediting-MARTIN-LINGE 61246X, Fabian Krause,


Cc:
Senthilkumar Jeevanandham, Arun Prasath Moorthy

1 attachment
CPY_COMMENTS_NO-HLD-10-T046-480021_rev03-RS.PDF

Dear Bhuvanesh,
kindly note that the document is stamped in code 3 and issued as built.
Note that no further revision of this document is foreseen.
Nevertheless please find below some explanation:
" Maximum horizontal displacement at the in/outlet connections during operation 15mm" refers to all
three connections.
We state how much the connections will move, be displaced during operation. Thats why the
connections must be installed non-loaded and flexible according to our basic size drawing.
The idea is about minimizing the loads, std procedure with a bellow, compensator or flexible hose so it`s
flexible and not static/tense.
ALfa Laval centrifuges are designed with the prerequisite that all piping, such as inlet, outlet and drain,
as well as other service media are flexible attached to the machine. Alfa laval`s experience is that this
is good and widely known engineering practise for rotating machines that has critical speeds during
the start and stop phase.
It is essential that all pipes are flexibly connected to the separator. The main reason is that this is the
best known way to avoid flange fatigue problems due to vibrations. Under the condition that the
connection flanges are flexibly connected to the surrounding piping, the dynamic forces on the flanges
will be almost neglible. Furthermore, an Alfa laval separator with flexible connections has critical
speeds that are well separated from the operating speed in order to avoid resonance. A hard piping
connection with an unknown stiffness may change the critical speeds in an unfavourable way.
Other reasons for using flexible connections are that the separator will be less sensitive to vibrations
that originate from the surrounding piping system and also reversly that vibrations from the
separatorwill not be transferred to the environment through the piping.
A separator in operation will produce forces acting on its foundation. In normal operation, the main
force is the static machine weight load. the dynamic forces on the foundation are mainly due to
unbalances in the separator bowl. These forces are low thanks to the vibration isolation of the
separator`s vibration feet dampers.
Hope that clarifies.
Best Regards
Lukas Dobrowolski

Lukas Dobrowolski, Dipl.-Ing.


Engineering & Supply
Tel direct: +49 40 7274 26 11 - Fax: +49 40 7274 4 2611
lukas.dobrowolski@alfalaval.com
Contact me on MS Lync/Communicator: sip:lukas.dobrowolski@alfalaval.com
Alfa Laval Mid Europe GmbH
Postfach 1114 - DE-21503 Glinde - Germany
Visit: Wilhelm-Bergner-Strasse 7 - DE-21509 Glinde
Registered office: Reg.-Gericht Amtsgericht Lbeck: HRB 1679 RE, GF: Jens Pulczynski, St. Nr,:30 293 00 333 (Alfa Laval
Holding GmbH); U.St.-Id. Nr.: DE211435775
Tel switchboard: +49 40 72 74 03 - Fax switchboard: +49 40 72 74 25 15
www.alfalaval.com/mideurope - info.mideurope@alfalaval.com

This e-mail is intended solely for the use of the individual or entity to whom it is addressed and its
content shall be regarded as confidential unless explicitly stated otherwise. If you have received this e-mail
by mistake, please notify the sender immediately by e-mail and delete this e-mail from your system.

From:
To:
Cc:

Bhuvanesh PiskalaSankaran <SBhuvanesh@technip.com>


Lukas Dobrowolski <lukas.dobrowolski@alfalaval.com>
Fabian Krause <fabian.krause@alfalaval.com>, Senthilkumar Jeevanandham <JeSenthilkumar@technip.com>,

Expediting-MARTIN-LINGE 61246X <exp61246x@technip.com>, Arun Prasath Moorthy <MArunprasath@technip.com>


Date:
02.09.2015 08:31
Subject:
PO n61246X-1000-PO-0234-0005-0046 - ALFA LAVAL - DRAIN WATER TREATMENT PACKAGE - TEPN
comments on 480021

Dear Lukas,
Please find the TEPN comments on 480021. Please provide your response to these
comments, before the document is revised.
Thanks in advance for your response.
Regards,
P.S.Bhuvanesh
Sr.Engineer - Package Design
Technip - Chennai
____________________________________________________
____________
______________
Technip India Limited - Technip Centre - 19 Velachery Main Road
Chennai - 600 032 India, www.technip.com
Tel (Direct): +91 44 22 30 32 85 Switchboard: +91 44 22 30 31 00
Fax: + 91 44 22 30 00 17
This email and any attached files ("Message") may contain

confidential and/or privileged information. It is intended


solely for the addressee(s). If you receive this Message in
error, inform the sender by reply email, delete the Message
and destroy any printed copy.
Any unauthorized use, distribution, or copying of this Message
or any part thereof is prohibited. Emails are susceptible to
alteration. Neither Technip nor any of its affiliates shall be
liable for the Message if altered or falsified nor shall they
be liable for any damage caused by any virus that might be
transmitted with this Message.

Anda mungkin juga menyukai