This article was published in ASHRAE Journal, August 2014. Copyright 2014 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or
distributed electronically or in paper form without permission of ASHRAE. For more information about ASHRAE Journal, visit www.ashrae.org.
Measurement
And Verification
BY SCOTT GORDON, ASSOCIATE MEMBER ASHRAE; AND DAVE MCFARLANE, MEMBER ASHRAE
The purpose of this article series has been to present the technical commissioning
process for new building commissioning. We began by outlining the owners expectations in the Owners Project Requirements (OPR) document. Next, we described the
Basis of Design (BOD) document, which ensures that the project designers meet the
requirements spelled out in the OPR document.
If we were moving through an actual project in
sequence with these articles, by this point we would
also have created the commissioning plan (CP), which
outlines the commissioning-related tasks that everyone involved in the project must complete to make
sure the objectives set forth in the OPR document are
achieved. We also would have been carefully monitoring the construction process and overseeing all
prefunctional testing (PFT) to ensure that all equipment and systems have been properly installedand
can be properly started and run. By now, too, we
would have directed and verified the completion of
all functional performance testing (FPT), so we would
This is the eighth in a series of bimonthly articles that explain the technical commissioning process for
new buildings. Some of these articles content is based on ASHRAE Guideline 0-2005, The Commissioning
Process (published 2005) and the National Environmental Balancing Bureau (NEBB) publication Procedural Standards for Whole Building Systems Technical Commissioning for New Construction (revised April
2013). In addition, some of the information in this article series has been adapted from an unpublished
NEBB standard titled NEBB Standard Owners Project Requirements (OPR) Guideline (draft dated June 20,
2011); and from NEBBs Procedural Standards for Building Enclosure Testing (March 2013).
Scott Gordon is a technical manager and Dave McFarlane is a senior technical director in the Building Performance Group at Atkins in Fort Myers, Fla.
32
TECHNICAL FEATURE
TABLE 1
Four M&V plan options. (The information in Table 1 is based on International Performance Measurement and Verification Protocol: Concepts and Options for Determining Energy and
Water Savings, Volume 1 (September 2010; Efficiency Valuation Organization, Washington, D.C.); pp. 2122.
M&V PLAN OPTION
COMMON APPLICATIONS
D CALIBRATED SIMULATION
33
TECHNICAL FEATURE
Adjusted
Baseline
Energy Use
Energy Use
Increased
Production
Baseline
Energy
Use
ECM
Installation
Baseline
Period
Savings, or Avoided
Energy Use
Energy Measured
During Reporting
Period
Reporting
Period
Time
TECHNICAL FEATURE
data would have been much less, thus effectively undervaluing the benefit of the ECM.1
While this particular example involves a retrofit to an
existing facility, the same type of analysis must be completed when comparing predicted the energy use of a
new building to its actual use.
Measurement Plan
Verify Implementation
Collect Data
Analyze Data
Make Changes
Report Results
Compare Results
Normalize Data
Usage Baseline
35
TECHNICAL FEATURE
TECHNICAL FEATURE
role in your M&V process. Of course, if energy performance is clearly on the decline (or already down the
tubes) it will take a much deeper analysis to identify and
alleviate the problems.
many years have passed since construction was completed; hence the need for OCx.
The good news is that OCx offers solid performance
and efficiency benefits, including a potential three-point
boost toward LEED certification. According to the
website of the U.S. Green Building Council, the purpose
of OCx is to proactively use the building commissioning process to improve building operations, energy, and
resource efficiency on a continuing basis over the buildings life, including planning, point monitoring, system testing, performance verification, corrective action
response, ongoing measurement, and documentation.4
So join us here in October for the conclusion to our
overview of the technical commissioning process.
References
1. U.S. Department of Energy. International Performance Measurement and
Verification Protocol: Concepts and Options for Determining Energy and Water Savings,
Volume 1, p. 12.
2. ASHRAE Guideline 14-2002, Measurement of Energy and Demand Savings, p. 4.
3. ASHRAE. 2013. Performance Measurement Protocols for Commercial Buildings:
Best Practices Guide, p. xv-xvi.
4. USGBC. 2013. LEED O+M: Existing Buildings v4, Ongoing commissioning,
http://tinyurl.com/ml43gx8.