Dakhni Gas Processing Plant

Activity ID

ATA Plan 2016

Activity Name

Original Planned Start Planned Finish


g 07
Duration

ATA-16 ActivitiesAc
Electrical Section
Motor Maintenance
Ma

29-Aug-16

29-Aug-16, Motor Maintenanc

1d 15-Aug-16

16-Aug-16

1d 15-Aug-16

16-Aug-16

A030

Servicing/ Bearing replacement of De-butanizer Condenser fan motor (EC-602), 11KW, 380V

1d 16-Aug-16

17-Aug-16

A040

Servicing/ Bearing replacement of NGL fractionator pump motor (GA-601 A/B), 2.2KW, 380V

1d 16-Aug-16

17-Aug-16

A050

Servicing/ Bearing replacement of crude transfer pump motor (100-GA-01A/B), 45KW, 380V

1d 17-Aug-16

18-Aug-16

A060

Servicing/ Bearing replacement of Flare K.O. drum pump motor (902-GA-01A/B), 4KW, 380V

1d 17-Aug-16

18-Aug-16

A070

Servicing/ Bearing replacement of Effluent pump motor A/B , 37KW, 380V

1d 17-Aug-16

18-Aug-16

A080

Servicing/ Bearing replacement of Steam condenser fan motor (E-01A/B), 11KW, 380V

1d 18-Aug-16

19-Aug-16

A090

Servicing/ Bearing replacement of Boiler feed water pump motor (P-01A/B), 37KW, 380V

1d 19-Aug-16

20-Aug-16

A100

Servicing/ Bearing replacement of Aux. boiler blower motor (700-PA-3), 5.5KW, 380V

1d 19-Aug-16

20-Aug-16

A110

Servicing/ Bearing replacement of Aux. lube oil pump motor (GA-403 AX/BX), 1.5KW, 380V

1d 19-Aug-16

20-Aug-16

A120

Servicing/ Bearing replacement of Amine reg. reflux pump motor (GA-401 A/B), 6KW, 380V

1d 20-Aug-16

21-Aug-16

A130

Servicing/ Bearing replacement of Amine transfer pump motor (GA-404), 3KW, 380V

1d 20-Aug-16

21-Aug-16

A140

Servicing/ Bearing replacement of Amine regen. condenser Fam motor (EC-402 A/B), 28KW, 380

1d 21-Aug-16

22-Aug-16

A150

Servicing/ Bearing replacement of Hot oil cir. pump motor (830-GA-02 A/B), 112KW, 380V

1d 22-Aug-16

23-Aug-16

A160

Servicing/ Bearing replacement of Hot oil makeup pump motor (830-GA-03), 112KW, 380V

1d 22-Aug-16

23-Aug-16

A170

Servicing/ Bearing replacement of Cooling water pump motor (830-GA-01 A/B), 112KW, 380V

1d 22-Aug-16

23-Aug-16

A180

Servicing/ Bearing replacement of Cooling tower fan motor (801-CT-01 A/B/C/D/E/F), 9.5KW, 380

1d 23-Aug-16

24-Aug-16

A190

Servicing/ Bearing replacement of Raw water pump motor (802-GA-01 A/B), 19KW, 380V

1d 23-Aug-16

24-Aug-16

A200

Servicing/ Bearing replacement of Potable water pump motor (802-GA-02 A/B), 3KW, 380V

1d 24-Aug-16

25-Aug-16

A210

Servicing/ Bearing replacement of Demin water pump motor (912-GA-01 A/B), 2.5KW, 380V

1d 24-Aug-16

25-Aug-16

A220

Servicing/ Bearing replacement of LPG loading pump motor (911-GA-01 A/B), 11.9KW, 380V

1d 24-Aug-16

25-Aug-16

A230

Servicing/ Bearing replacement of Crude loading pump motor (910-GA-01 A/B), 11.9KW, 380V

1d 25-Aug-16

26-Aug-16

A240

Servicing/ Cleaning of SRU-II Blower motor (C-1901 A/B), 250KW, 6KV

1d 25-Aug-16

26-Aug-16

A250

Servicing/ Cleaning of Lean Amine feed pump motor (GA-403 A/B), 755KW, 6KV

1d 26-Aug-16

27-Aug-16

A260

Servicing/ Cleaning of Air blower motor (GB-701 A/B), 187KW, 6KV

1d 26-Aug-16

27-Aug-16

A270

Servicing/ Cleaning of Fire water pump motor (901-GA-01 A), 220KW, 6KV

1d 26-Aug-16

27-Aug-16

A280

Servicing/ Bearing replacement of RGT A/B vent fan motor (A/B), 22KW, 380V

1d 27-Aug-16

28-Aug-16

A290

Servicing/ Bearing replacement of RGT Gen. cooling fan motor (A/B), 2.2KW, 380V

1d 27-Aug-16

28-Aug-16

Critical Remaining Work

Prepared By: Bilal Khurshid(J.E Mech)

Sep 11 18

14d 15-Aug-16

Servicing/ Bearing replacement of Reco Condenser fan motor (PA-501X-A/B), 11KW, 380V

Summary

Sep 04

08-Sep-16, ATA

Servicing of Reco Compressor motor (PA-501), 336KW, 6KV

Milestone

2016
Aug 28

08-Sep-16

A020

Remaining Work

Aug 21

24d 15-Aug-16

A010

Actual Work

Aug 14

Chec ked By: Ahmad Zia ( I/C Electrical )

Dakhni Gas Processing Plant


Activity ID

ATA Plan 2016

Activity Name

Original Planned Start Planned Finish


g 07
Duration

A300

Servicing/ Bearing replacement of Boiler Feed Water Pump Motor SRU-II (A/B), 37KW, 380V

1d 27-Aug-16

28-Aug-16

A310

Servicing/ Bearing replacement of Sulfur Feed Pump Motor SRU-II (A/B), 14.92KW, 380V

1d 28-Aug-16

29-Aug-16

A320

Servicing/ Bearing replacement of Sulfur Loading Pump Motor SRU-II (A/B), 14.92KW, 380V

1d 28-Aug-16

29-Aug-16

A330

Servicing/ Bearing replacement of Condensate Transfer Pump Motor SRU-II (A/B), 2.2KW, 380V

1d 28-Aug-16

29-Aug-16

A131

Servicing/ Bearing replacement of Amine cooler fan motor (EC-401 A/B/C/D), 28KW, 380V

1d 21-Aug-16

22-Aug-16

A231

Servicing/ Cleaning of Hot oil cir.pump motor (830-GA-01 A/B/C), 187KW, 6KV

Electric Heat
H
Tracing

1d 25-Aug-16

26-Aug-16

23d 16-Aug-16

08-Sep-16

B010

Removing of Heat Tracing From different LICs,LCVs,LGs and LCVs' manifolds.

4d 16-Aug-16

20-Aug-16

B020

Re-installation of Heat Tracing back at different LICs,LCVs,LGs and LCVs' manifolds.

5d 03-Sep-16

08-Sep-16

4d 16-Aug-16

20-Aug-16

Plant Lightenng
Lig
Circuit
C040

Cleaning / servicing of all lighting pole DBs.

1d 16-Aug-16

17-Aug-16

C050

Cleaning / servicing of all Road Lights (250W) & Replacement of parts if required.

1d 17-Aug-16

18-Aug-16

C060

Cleaning / servicing of all Flood Lights ( 400W ) & Replacement of parts if required.

1d 18-Aug-16

19-Aug-16

C080

Cleaning/servicing of all Plant Lights ( 2x20W) & Replacement of parts if required.

1d 19-Aug-16

20-Aug-16

6d 15-Aug-16

21-Aug-16

Plant Earthing
Ear
D010

Cleaning/ Tightening of earth pit contacts

3d 15-Aug-16

18-Aug-16

D020

Cleaning/ Tightening of earth terminals contacts

3d 18-Aug-16

21-Aug-16

7d 22-Aug-16

29-Aug-16

Cable Laying
La
E010

Power cable for 100 GA 01 A 16 sqmm

1d 22-Aug-16

23-Aug-16

E020

Power cable for 902 GA 02 B 10 sqmm

1d 23-Aug-16

24-Aug-16

E030

Control cable for 902 GA 02 B 2.5 sqmm

1d 24-Aug-16

25-Aug-16

E040

Power cable for Old SRU Air Blower motor 25 sqmm HT Cable (Req . 1.5'X3.5' running 150 mete

4d 25-Aug-16

29-Aug-16

6d 16-Aug-16

22-Aug-16

Installation/Modification
Installatio
F010

Dismanteling of existing Diesel Genset Panel.

1d 16-Aug-16

17-Aug-16

F020

Installation of 3200 Amp Air Circuit Breakers

1d 17-Aug-16

18-Aug-16

F030

Modification job of LV Busbar and coupller Drop downs for 3200 Amp Air Circuit Breakers

1d 18-Aug-16

19-Aug-16

F040

Inst of AMF panel ,Sync of EDG circuit breaker with transformer breaker,

1d 19-Aug-16

20-Aug-16

F050

Synchronization of LV switchgear with new synch system.

1d 20-Aug-16

21-Aug-16

F060

Housekeeping and removal of unwanted material

1d 21-Aug-16

22-Aug-16

5d 21-Aug-16

26-Aug-16

5d 21-Aug-16

26-Aug-16

Relay Testing
Tes
G010

Relay testing of all relay installed with( MV )medium voltage sytem.CTM 09 NOS ,CDG 04 NOS

Actual Work

Milestone

Remaining Work

Summary

Critical Remaining Work

Prepared By: Bilal Khurshid(J.E Mech)

Aug 14

Aug 21

2016
Aug 28

Sep 04

Sep 11 18

08-Sep-16, Elec

20-Aug-16, Plant Lightenng Circuit

21-Aug-16, Plant Earthing

29-Aug-16, Cable Laying

22-Aug-16, Installation/Modification

26-Aug-16, Relay Testing

Chec ked By: Ahmad Zia ( I/C Electrical )