You will find the personnel and time requirements for the manufacture of the concept car below:
Day
Persons
Time*
48**
0.1
6.5
Curing of the paste (PU: approx. 6-12 hours, epoxy: approx. 48-72 hours)***
10
5/6
20
--
12
Rough-cutting 4 tyres
Finish-cutting 4 tyres
0
1
Measure
Required manpower:
: 139 h
* The listed total production time is the rounded sum of the specific absolute time weighted by the required personnel. It
excludes the set-up times for the machine.
** The CAD/CAM works were time-consuming as the supplied data did not represent an ideal 3D surface model.
*** The curing time of the epoxy paste was shortened by heating up the workshop.
Used material
The size of the car (L x W x H) was 4.65 m x 1.90 m x 1.60 m.
Object
Material
Volume*
Net costs
Subconstruction:
2 m
160
Carrier material:
15 m
1,200
Glue:
20 bottles
170
Paste:
Approx. 300 l PU
2,700
Approx. 240 l EP
3,360
7,590
* Rounded values.
** One half of the car model was extruded with PU paste, the other half with EP paste. The tyres were extruded with PU.
051206
1/5
Used equipment:
Application
Equipment
For milling:
Cutters for rough-/finish-cutting paste: Bull end, 24 mm, r = 3 mm, 150 mm long
For extrusion:*
* A meter/mix and dispensing machine can either be used for PU or EP paste. Due to chemical incompatibility it is
impossible to use one meter/mix and dispensing machine for both pastes.
Process
051206
2/5
051206
3/5
051206
4/5
For further information about this project, please do not hesitate to get in touch with following contact