Phase-II:
Phase - I
Preparation of Detailed Project Report for Phase-I entrusted to
the Consultants was completed by Dec 2005. The Consent for
Establishment was received from APPCB. The clearances from
MOEF are also received. Since the work is of specialized nature it
was decided by the Government to follow the International
Competitive
Bidding
procurement
for
process,
Phase-I
is
for
award
completed
of
and
contracts. The
the
status
of
implementation is as under.
(a). Supervision Consultancy Contract:
The High Level Committee constituted by the Government
decided that the bid of M/s BCEOM-Aarvee (JV) is the best value bid
received on ICB mode and the Contract is being awarded to them.
(b). Civil Works Contracts:
The High level Committee constituted by the Government
approved the lowest evaluated bids offered by the Contractors as
under.
(i). Contract Package I from Km 0.000 to 11.000
( Gachibowli to Shamshabad )
Agency: M/S CORPORATION TRANSSTROY OSJC ,Russia
(ii). Contract Package II from Km 11.000 to 24.380
( APPA to Shamshabad )
Agency: M/S CONTINENTAL ENGINEERING
CORPORATION, Taiwan
The works are scheduled to be completed in 30 Months while four
lane connectivity shall be given between Gachibowli and Shamshabad by
December 2007.
PHASE II
The preparation of Detailed Project Report is entrusted to the
M/s BCEOM-Aarvee (JV) Consultants.
Time Lines:
Preparation of DPR
Obtaining Clearances
: by April, 2007.
Project Funding
The Phase-I of ORR Project cost is being met from the borrowed
funds from the consortium of Banks to a tune of Rs.500 crores.
The above loan is proposed to be liquidated in a period of ten years by
way of developing Integrated townships and Cluster Development alongside
the ORR and also through a mechanism of Regulations and Impact fees and
Charges in the 1Km Corridor on either side of the ORR.
2. Hyderabad Knowledge Corridor Project:
The Hyderabad Knowledge Corridor Project is proposed to be
implemented in about 34 villages in R.R. and Medak Districts. This project
envisages creation of world class infrastructure for IT & IT Enabled Sector,
integrated with Clusters of housing and commercial infrastructure and it is at
preliminary stage of conception. A committee has been constituted by the
Government to go into the modalities for forming a Special Authority for the
Hyderabad Knowledge Corridor Project.
(Bhadrachalam-Rajahmundry),
river
Krishna
(Wazirabad-
The State
The above TEF study has been entrusted to M/s. RITES Ltd., A
Govt. of India Enterprise and it is expected to complete the study by
August/September, 2007.
Chairman has been constituted for proper guidance on the project execution.
Recently Government of India have suggested to GoAP to consider using the
Pataudi House land adjacent to A.P. Bhavan for setting up of a five star
Hotel. The proposal was examined by INCAP.
Milestones achieved:
1) Government have issued Orders constituting the Special Empowered
Committee in G.O.Ms.No.423, General Administration (GH-1) Dept., dated
14.09.2005 read with GO Ms.No.436 General Administration (GH-I)
Department dated 23.09.2005.
2) International competitive Bids were called for and EOI-cum-RFQ was
issued 18 developers have responded to the EOI-cum-RFQ 8 developers
were short listed.
3) Government have issued Orders constituting Technical Advisory
Committee vide GO Ms.No.6 Infrastructure & Investment (IID-I) Dept.,
dt.12.07.2006. The Technical Advisory Group has met twice on 14.07.06
and 26.07.06 to advice on critical issues.
4) Government have issued orders for engaging Independent Engineering
Agency vide GO Ms.No.7 Infrastructure & Investment (IID-I) Dept., dated
12.07.2006.
5) Government have issued Orders appointing liaison team vide GO
Ms.No.8 Infrastructure & Investment (IID-I) Dept., dt.12.07.2006.
6) Govt., has issued orders permitting VC & MD for appointment of
additional personnel in his office vide G.O.Ms.No.10, Dt.27.07.06.
Development of Nizampatnam Industrial Port City Complex
A Memorandum of Understanding was entered into between M/s
Skoda Export Company Ltd., belonging to the Czech Republic and INCAP
convened to look into the project specifics. Government have approved the
Memorandum and Articles of Association of the Special Purpose Vehicle.
Milestones achieved:
1. Developer has prepared the Pre-feasibility report and initial Master
plan in pursuance of the MOU.
2. The Memorandum and Articles of Association of Nizampatnam
Industrial Port Complex Company Pvt. Ltd. (NIPCCO) has been
approved by the Government in G.O.Ms.No.1, I & I Dept., dated
2.2.2007.
3. Inter departmental coordination meeting at Government level
covering 8 departments for discussing the details contained in the Prefeasibility report was convened.
1) Ports Department
2) South Central Railways
3) Finance Department
4) Revenue Department
5) Environment, Forest, Science & Technology Department
6) Energy department
7) Industries & Commerce Dept.
The Council of
10
4. Ongole;
5. Nellore;
6. Kurnool;
7. Tadepallegudem;
The Airport Authority of India has also expressed their view
that new airports in the State can be undertaken through MoU route. The
State Govt. has, therefore, vide its letter dated 20.1.2007 requested the AAI
to take up Feasibility Studies at these locations for Greenfield airports.
Besides this, the AAI has been requested to enter into MoU similar to the
one entered into by the AAI with the Govt. of Karnataka, for revival of the
two existing Airports at Cuddapah and Warangal.