MC # 80
June 1978
MC # 103
Aug 1978
MC # 14
Jan 1981
MC # 38
Nov 1981
MO # 28
Aug 1985
April 1987
mixes shall be done for every batch of delivery & that the
mixes meet the concrete strength requirements
5. Testing of steel bars by the DPWH- accredited
laboratories/private institutions shall be allowed provided
that the testing shall be witnessed by the authorized
government representatives. For small projects located in
remote areas where the quantity of steel bars is 10,000 kg
or less, mill certificates may be used as basis for acceptance
of the material
DO # 55
May 1989
DO # 80
April 1990
DO # 45
Feb 1991
DO # 83
June 1991
DO # 137
June 1991
MC # 97
Aug 1991
Jan 1992
DMC
Mar 1992
DO # 55
May 1992
DO # 57
May 1992
DO # 119
Aug 1992
DO # 202
Nov 1992
DO # 135
May 1993
DO # 229
July 1993
DO # 29
Jan 1994
DO # 53
March 1994
DO # 83
April 1994
DO # 82
May 1996
DO # 177
Nov 1996
MC # 48
May 1997
DO 127
July 1997
Jan 1999
DO # 3
Jan 1999
DO # 29
Feb 1999
Sept 1999
DO # 59
Feb 2000
DA/FTMR
2.0%
RUDIP
2.5%
c. Projects each costing P50,000 & below are not
subject to the above-mentioned retention
DO # 76
Mar 2000
DO # 216
Nov 2000
PROJECT RECORDS
All PE shall faithfully maintain the following aside from
the Contract Documents, Plans & Specifications
1. Progress of Work
2. Diary or Log
3. Tests of Materials
4. Minutes of all meetings
5. Correspondence
6. Construction Schedules
7. Change Order logs & records
8. Contractors requests for payment
9. Sureties & insurance certificates
10. Monthly Progress Reports