PS.1290
Lessons Learned P6 Resource
Updating for the Beginner
Charlie Jackson, PSP and Hannah E. Schumacher, PSP
Abstract Many contract documents require the project schedule to be cost and/or resource
loaded. If the contract documents require the use of Primavera P6, it is important for the
scheduler to understand the myriad of options within the P6 resource management utility and
how these options affect the updating process.
Primavera P6 contains several features that assist in establishing a well-defined resource plan
while efficiently managing resource allocations. However, a new or in-experienced user may be
overwhelmed in the attempt to grasp these features defined at various levels of the project and
overall enterprise organization without proper instruction.
This session is a follow-up to the authors AACE 2012 paper titled PS-962 Lessons Learned
P6 Resource Planning for the Beginner[1] and will focus on the authors experiences and
their lessons learned regarding the use of P6 in the resource updating process. The scheduler
should be able to apply the lessons learned outlined in this paper to effectively and efficiently
update their cost and/or resource loaded schedules to meet their organizational requirements
and project contractual obligations.
PS.1290.1
PS.1290.2
1
3
4
5
5
9
11
11
12
14
16
16
17
17
19
24
25
PS.1290.3
6
6
7
8
8
9
10
10
11
12
13
14
15
16
17
17
18
19
20
21
21
22
22
23
24
PS.1290.5
The Resource Details tab settings (as shown in Figure 1) determine whether the actual units
for each resource will be actualized as the activity it is assigned to is progressed (Auto
Compute Actuals) and whether the actualized units will be used to calculate the associated
costs (Calculate costs from units). Costs can only be automatically calculated based on the
units (price per unit) or entered directly by the scheduler.
For those resources whose costs are based on units, the Resource Units & Prices tab (as
shown in Figure 2) can have up to five rates (dollars) per unit based on an effective date.
The five rate types allow for varying resource usage by contract type for a given period (i.e.
Time and Material contracts versus Fixed Price).
Project Details, Resources tab settings (as shown in Figure 3) determine which Rate Type for
any given resource will by used by default, and whether a resources calendar will directly
drive the activitys duration (Resource Dependent activity types); whether a resource can be
assigned more than once to a single activity (i.e. different Cost Accounts or for varying time
periods and/or with varying cost rates). These settings apply to new assignments of
resources, and changes to these settings will not affect existing assignments.
Project Details, Calculations tab settings (as shown in Figure 4) determine how resource
assignment actuals are updated and stored. The scheduler must decide whether Actual
units/costs are added to Remaining to equal the At Complete (i.e. T&M contracts) or
whether the actuals are subtracted from At Complete to equal Remaining (i.e. Fixed Price
contracts). The scheduler must also decide whether to use the activitys actual duration
percent complete to update the assignment actuals (Note: this option is only available for
Fixed Duration activities) or to manually input actuals regardless of percent complete. This
option allows the scheduler to override the resource level option of auto compute actuals
with project specific requirements. Without this option selected, actual data can only be
entered manually.
The link between costing changes and unit changes can also be turned off to allow for
variance between costs and units. The scheduler can enter the total budgeted cost for each
activity assignment and have the application calculate the total associated units.
PS.1290.7
Project Details, Defaults tab settings (shown in Figure 5) which affect resources include the
duration type and percent complete type. The Duration Type determines the use of
production rates and how they affect progressed durations.
PS.1290.8
PS.1290.9
Figure 10 Resources
The Cost resource is identified as XXXX (the unique project ID) Costs (to identify the unique
project resource) as discussed previously. The resource type is set to Nonlabor this allows the
scheduler the ability to analyze pure cost resources versus labor or material resources.
The Labor resource is identified as XXXX (the unique project ID) Labor (to identify the unique
project resource) as discussed previously. The resource type is set to Labor, as shown in Figure
10.
Auto-Calculated Update
When using Primavera, if an activitys Duration % complete can be used to calculate actual
resource units the scheduler may choose to have P6 compute actual units completed
regardless of physical work performed.
In selecting to use Primaveras resource Auto Calculate option, activity actual and remaining
units are calculated using the planned dates, budgeted units, and the activitys schedule
percent complete. According to Primavera help, this assumes that all work by the resource
proceeds according to plan.
The following settings (as shown below) must be selected at these three levels:
1. Resource level (Details tab) Auto Compute Actuals
2. Project level (Calculations tab) Update units when costs change on resource assignments
3. Activity level (Resources tab) Auto Compute Actuals
The first scenario also assumes that assignment actual cost will be calculated based on actual
units (Resources level, Details tab, Calculate costs from units) and that the scheduler will be
using Financial Periods to store actual work for each update period (Project level, Calculations
tab, Link Actual and Actual This Period Units and Cost).