Anda di halaman 1dari 22

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park.

ISBN: 0-13-611848-8
2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

Chapter 13 Real-Options Analysis


Financial Options
13.1
Define the option parameters for the call option.
S0

$80.38

$90

0.5

0.06

0.8

The value of the call option is $15.39 by Black-Scholes equation.


13.2
Define the option parameters for the put option.
S0

$136.08

$160

0.167

0.05

0.6

The value of the put option is $28.39 by Black-Scholes equation.


13.3
Long call and short call

Page | 1

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

Long put and short put

13.4
Define the option parameters for this option.
S0

$52

0.75

0.05

0.6

To get a value of call option of $4 by Black-Scholes equation, the current


stock price should be $37.5 by Goal seek function in Excel.

13.5
u = e t = e0.3 0.75 = 1.2967
1
1
d= =
= 0.7712
u 1.2967
Risk neutral probability
q=

e r t d e0.050.75 0.7712
=
= 0.5081
ud
1.2967 0.7712

Page | 2

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

Tree valuation
100.88
Max(0, (100.88-60)) = $40.88
q
60
$9.81

77.80
$20.02
60
Max(0, (60-60)) = $0

1-q
46.27
$0.00

35.68
Max(0, (35.68-60)) = $0

European call option value = $9.81


13.6
u = e

= e0.3 1 = 1.3499 , d =

1
1
=
= 0.7408
u 1.3499

Risk neutral probability


e r t d
e0.051 0.7408
q=
=
= 0.5097
ud
1.3499 0.7408

98.39
Max(0,45-98.39)
0
Do not exercise

Tree valuation
72.89
Max(0,45-72.89)
0
Do not exercise

53.99

40

Max(3.34,45-53.99)
3.34
Do not exercise

$8.79

53.99
Max(0,45-53.99)
0
Do not exercise

40
Max(7.17,45-40)
7.17
Do not exercise

29.63
Max(0,45-29.63)
15.37
Exercise

29.63
Max(14.24,45-29.63)
15.37
Do not exercise

21.95
Max(20.86,45-21.95)
23.05
Exercise

American option value = $8.79

16.26
Max(0,45-16.26)
28.74
Exercise

Page | 3

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

13.7
We may use the Goal Seek function in Excel to find the value of K by
inputting the known parameters into the Black-Scholes equation. Or we may
use a known result of put-call parity in financial option. The put-call parity
shows the relationship between the price of a European call option and the
price of a European put option when they have the same strike price and
maturity date.
r T

c+Ke f = p+S0
35.15+Ke0.06(1) =13.95+90
K=$73.05
If the equation above does not hold, there are arbitrage opportunities.

13.8
Portfolio
A long call with K = $40
A short put with K = $45
Two short calls with K = $35
Two stocks shorted at $40
Total

Premium
$3
$4
$5

Payoff at stock price $60


$17
$4
($40)
($40)
($59)

13.9
Intrinsic value = S0 K = $2
Time premium = option premium intrinsic value = $2

13.10
Invest $10,000 in the stocks

Stock Purchase
Price

Initial
Cost of
Stock 400
shares

Stock, Price
at Expiration

Value of Stock
at Expiration

Payoff

$25

$10,000

$27

$10,800

$800

$25

$10,000

$30

$12,000

$2,000

$25

$10,000

$40

$16,000

$6,000

Page | 4

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

Invest $10,000 in the call options


Option
Price
per
Contract
$4

Initial Cost of
Options (2500)

$4
$4

Profit Per
Option
at Expiration

Total Profit of
Options

Payoff

$0

$0

($10,000)

$3

$7,500

($2,500)

$13

$32,500

$22,500

$10,000
$10,000
$10,000

13.11
(a)

Discount rate per period

S0 =
K=
T=
r=
u=
d=
volatility =
q=
1-q =
w=

100
105
1.5
5%
1.354
0.739
35%
0.49
0.51
0.9632

183.35
135.41
36.74
100
17.23

78.35
100.00

73.85
0.00

0.00
54.54

17.23 = 0.9632*(0.49(36.74 )+ 0.51(0))


0.00
0= 0.9632(0.49(0) + 0.51(0))

Option value= $

17.23

Page | 5

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

(b)

Discount rate per period

S 0=
K=
T=
r=
u=
d=
volatility =
q=
1-q =
w=

100
100
1
5%
1.191
0.839
35%
0.49
0.51
0.9876

201.38

119.12
3.73
100
10.43
83.95
17.18

169.05

0.00

141.91

0.00

141.91

0.00

119.12

0.00

100.00

0.00

100.00

7.43

83.95

0.00

70.47

14.81

70.47

27.06

59.16

29.53

39.60

49.66

17.18= 0.9876(0.46(7.43) + 0.54(27.06))

50.34
Option value=

$ 10.43

MAX(0, 100 - 49.66)


= 50.34

Page | 6

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

(c)

Discount rate per period

S 0=
K=
T=
r=
u=
d=
volatility =
q=
1-q =
w=

100
100
1
5%
1.191
0.839
35%
0.49
0.51
0.9876

201.38
169.05

0.00

141.91

0.00

141.91

119.12

0.00

119.12

0.00

100

4.04

100.00

0.00

100.00

11.36

83.95

8.05

83.95

0.00

18.73

70.47

16.05

70.47

29.53

59.16

29.53

40.84

49.66

11.36 = 0.9876*(0.49(4.04 )+ 0.51(18.73))

MAX(18.73, 100 - 83.95)


= 18.73
Option value=

$ 11.36

50.34
MAX(39.20, 100 - 59.16)
= 40.84

MAX(0, 100 - 49.66)


= 50.34

13.12
(a)
Define the option parameters for this call option.
S0

$40

$40

1.167

0.06

0.4

The value of call option is $8.05 by Black-Scholes equation.

Page | 7

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

(b)
Define the option parameters for this put option.
S0

$50

$55

1.5

0.06

0.2

The value of put option is $5.02 by Black-Scholes equation.


(c)
Define the option parameters for this put option.
S0

$38

$40

0.25

0.06

0.6

The value of put option is $5.35 by Black-Scholes equation.


(d)
Define the option parameters for this call option.
S0

$100

$95

0.08

0.4

The value of call option is $38.27 by Black-Scholes equation.


13.13
The accumulated cost of the hedge at the end of year one is
($50,000 - $38,000)exp(0.06) = $12,742.
Let S be the market price:

If S < $1.25, the put option is in the money and the payoff is
$1,000,000(1.25 S) = $1,250,000 1,000,000S.
The sale of the coffee beans has a payoff of
1,000,000(S 1) - $12,742 + $1,250,000 1,000,000S = $237,258
Page | 8

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

From $1.25 to $1.40 neither option has a payoff and the profit is
1,000,000(S 1) - $12,742 = 1,000,000S -1,012,742

If S > $1.40, the call option is in the money and the payoff is
-$1,000,000(S 1.40) = $1,400,000 1,000,000S.
The profit is
1,000,000(S -1) - $12,742 +$1,400,000 1,000,000S = $387,258

Therefore, the range is $237,258 to $387,258.

Real-Options Analysis
13.14
Define the real option parameters for delaying option.
V0

$1.9 Million

$2 Million

0.08

0.4

The value of delaying is $0.32 Million by Black-Scholes equation. If the choice is


to defer or cancel, the value of delaying is $0.32M as calculated. If the choice is
to defer or upgrade now, then we have to subtract the conventional NPW and the
answer is $0.32M (-$0.1M) = $0.42M.

13.15
Define the real option parameters for license option.
V0

$30 Million

$40 Million

0.06

0.2

The value of license is $2.86 Million by Black-Scholes equation. Here we


assume that the option will be exercised in three years when exclusive mining
rights expire.

Page | 9

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

Growth Options
13.16
Define the real option parameters for this option.

V0

$1 Million

0.06

The best cutting policy:


It is most profitable when we cut the trees at year 2.
Keeping option open/waiting is better than cutting trees from year 0 to
year 1.
Option Value of the investment opportunity: $0.62M
0

1
1.6

2
1.5

0.4

0.4

unit: $M

Growth rate
Rent Cost

r
T=
dT
u=
d=
v=
q=
1-q =

0.06
2
1
1.25
0.8
0
0.58
0.42

3.75=2(1.25)(1.5)
2= 1(1.25)1.6
3.75

1
1.62
1

wait
Cutting

1.62=EXP(-0.06*1)*(2.6*0.58+1.52*0.42)-0.4: Wait
1: Cutting

2
2.60
2.00

wait
Cutting

1.28
1.52
1.28

wait
Cutting

3.75
2.40
2.40

Cutting

1.54
1.54

1.52=EXP(-0.06*1)*(2.4*0.58+1.54*0.42)-0.4: Wait
1.28: Cutting

Option value = $

Cutting

0.62

Page | 10

Cutting

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

13.17
Define the real option parameters for deferral option.

V0

I1

I2

$60,000

$38,588

$60,638

0.06

0.2

The value of postponing the construction decision for two years: $349,743
0
I1 =
I2 =
volatility
r
T=
dT =
u=
d=
q=
1-q =

60,000
349,743

2
38,588
60,638
0.2
0.06
2
2
1.33
0.75
0.65
0.35

38,588=35,000(1.05)(1.05)
60,638=55,000(1.05)(1.05)

410,263=MAX(79,614-38,588,0)*10
569,289=MAX(79,614-60,638,0)*30

79,614
410,263 10 stores mall open
569,289 30 stores mall open
45,218
66,308 10 stores mall open
0 30 stores mall open

349,743=EXP(-0.06*2)*(569, 289*0.65+ 66,308*0.35)

Page | 11

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

Switching Options
13.18
The NPW of project B:
PW (12%) B = $2 + $1( P / A,12%,10) = $3.65M
Define the real option parameters for switching option.
V0

$4 Million

$3.65 Million

0.06

0.5

The value of switching is $0.85 Million by Black-Scholes equation for put


option.
Therefore, the total value is:
SNPW = Value of project A + Option to switch to project B

SNPW = $4 + $0.85 = $4.85M

R&D Options
13.19
Assuming MARR = 12%, the cash flow diagram transforms to:

$73.42

0
$14.18

R&D Expenses

10

Manufacturing and Distribution


$80

Define the real option parameters for R&D option.

Page | 12

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

V0

$46.66 Million

$80 Million

0.06

0.5

The value of option today is $13.70 Million by Black-Scholes equation


for a call option.
Therefore, the total value is:
Option value = SNPW - Cost for R&D
= $13.7 $14.18 = $0.48M < 0
The firm should not embark on the project as the required R&D
expenditure already exceeds by $0.48M.

Abandonment Options
13.20
Standard NPW approach

0.35 0.35 0.35 0.35

0.35

...
0

$3
$0.35
= $0.08M
0.12
1
e0.06 d
= 1.6487, d = = 0.6065, and q =
= 0.4369
u
ud

PW (12%) = $3 +

u = e0.5

Abandon Option value through the binomial tree - Option parameters


V0
$2.92 Million

I
$2.2 Million

T
5

r
0.06

0.5

Page | 13

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

- Option valuations
Time

0
2.92

1
4.81
1.77

2
7.94
2.92
1.07

3
13.09
4.81
1.77
0.65

4
21.58
7.94
2.92
1.07
0.40

0.50

0.23
0.77

0.06
0.42
1.13

0.00
0.12
0.69
1.55

0.00
0.00
0.23
1.13
1.80

Monetary Value

Option value

5
35.57
13.09
4.81
1.77
0.65
0.24
0.00
0.00
0.00
0.43
1.55
1.96

* It is optimal to exercise early at the shaded positions.


Option premium = $0.50 (-0.08) = $0.58M

Scale-Down Options
13.21
Scale down option parameters
V0
$10 Million

I
$4 Million

T
3

r
0.06

0.3

Decision tree for a scale-down option through one-year time increment.


o
o
o

u = e t = e0.3 1 = 1.35
1
1
d= =
= 0.74
u 1.35
e r t d e0.061 0.74
q=
=
= 0.53
ud
1.35 0.74

Page | 14

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

K=
volatility
r
u=
d=
q=

4
0.3
0.06
1.35
0.74
0.53

1.35
10
11.7671

=max(18.22*0.8+4,EXP(-0.06)*(24.6*0.53+14.8*(1-0.53))) =18.8

13.50
14.7989
scale down

0.74
7.41
9.9265
scale down

24.60
max(24.6*0.8+4,24.6)
1.35
24.60
=24.6
18.22
Do not scale down
1.35
18.8003
0.74
Do not scale down
13.50
max(13.5*0.8+4,13.5)
0.74
1.35
14.80
=14.8
10
scale down
1.35
12.0000
0.74
scale down
7.41
0.74
1.35
9.93
5.49
scale down
8.3905
0.74
scale down
4.07
7.25
scale down

From the result of the tree we can get the SNPW:


SNPW = NPV + Option value = $11.77M
Option value = $11.77M - $10M = $1.77M

Expansion-Contraction Options
13.22
(a) Binomial lattice tree
u = e t = e0.15 1 = 1.1618
1
1
= 0.8607
d= =
u 1.1618
Tree with incremental period one year
134.99

116.18
100
100
86.07
74.08

Page | 15

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

(b) Option valuation


Risk neutral probability
q=

e0.051 0.8607
ert d
=
= 0.6329 , 1 q = 0.3671
ud
1.1618 0.8607

134.99
Max(134.990.9+25,134.991.3-20,134.99)
155.48
Expand

116.8

Max(116.80.9+25,116.81.3-20,133.76)
133.76
Keep option open

100

Max(1000.9+25,1001.3-20,100)
115
Contract

100
116.31

86.07
Max(86.070.9+25,86.071.3-20,101.24)
102.46
Contract

74.08
Max(74.080.9+25,74.081.3-20,74.08)
91.67
Contract

Option value = SNPW NPV = $116.31 - $100 = $16.31M

Compound Options
13.23
Compound option parameters
V0
I1
I2
$32.43

$10

$30

T1

T2

r
0.06

0.5

Decision tree for a scale-down option through one-year time increment.


- u = e t = e0.5 1 = 1.6487
1
1
-d= =
= 0.6065
u 1.6487
e r t d
e0.061 0.6065
- q=
=
= 0.4369
ud
1.6487 0.6065

Page | 16

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

145.34
Max(145.34 - 30, 0)
115.34
Invest $30

88.15
59.90
Keep option open

53.47
Max(53.47 - 30, 0)
23.47
Invest $30

53.47
Max(29.77 - 10, 0)
19.77
Invest $10

32.43
9.66
Keep option open

32.43
8.13

Max(19.67 - 30, 0)
0
Do not invest

19.67
Max(3.97 - 10, 0)
0
Do not invest

19.67

11.93
0
Do not invest

7.24
Max(7.24 -30, 0)
0
Do not invest

First Option

Second Option

SNPW is $8.13 and this exceeds the initial cost $5. Initiate the phase I.

Page | 17

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

13.24

Option parameters
V0

I1

I2

$19.5M

$3M

$12M

T
3

r
0.05

Phase 1
1

0
I=

0.25
Phase 2
2

3,000,000

12,000,000

12,000,000
29,281,500=MAX(41,281,500-12,000,000, 0)
2,700,000: Abandon (Selling price of the land)

volatility=
r
T=
dT
u=
d=
v=
q=
1-q=

0.25
0.05
3.00
1.00
1.28
0.78
0.00
0.54
0.46

20,735,312=EXP(-0.05*1)*(29,281, 500*0.54+13,038,496*0.46)
20,150,065=MAX(32,150,065-12,000,000, 0)
2,700,000: Abandon (Selling price of the land)

41,281,500

25,038,496
14,180,447
22,038,496
2,700,000
15,186,615
5,382,658
12,186,615
2,700,000

19,500,000
16,646,312

Keep Option
Invest 3M
Abandon
Keep Option
Invest 3M
Abandon

5,382,658=EXP(-0.05*1)*(8,085,247*0.54+2,817,955*0. 46)
12,186,615=MAX(15,186,615-3, 000,000, 0)
2,700,000: Abandon (Selling price of the land)

Option value=

32,150,065
20,735,312
20,150,065
2,700,000
19,500,000
8,085,247
7,500,000
2,700,000
11,827,348
2,817,955
2,700,000

Keep Option
Invest 12M
Abandon
Keep Option
Invest 12M
Abandon
Keep Option
Invest 12M
Abandon

29,281,500 Invest 12M


2,700,000 Abandon
25,038,496
13,038,496 Invest 12M
2,700,000 Abandon
15,186,615
3,186,615 Invest 12M
2,700,000 Abandon
9,211,148
Invest 12M
2,700,000 Abandon

16,646,312

Page | 18

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

Short Case Studies


ST 13.1
(a) American put option value
Option parameters
V0
$150
u = e

K
$100
t

= e0.3 1 = 1.3499 , d =

Risk neutral probability


q=

t
1 year

T
2

r
0.05

0.3

1
1
=
= 0.7408
u 1.3499

e r t d
e0.051 0.7408
=
= 0.5097 , 1 q = 0.4903
ud
1.3499 0.7408

0
K=
volatility
r =
u=
d=
q=

100
0.3
0.05
1.35
0.74
0.51
1.35
1.35

150
3.84

202.48
0.00

0.74

0.74
1.35

111.12
8.24

273.32
0.00

150.00
0.00

0.74

82.32
17.68

American put option value = $3.84

Page | 19

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

(b) Expansion Option value


Option parameters

t
T
2
1 year
1
1
u = e t = e0.35 1 = 1.42 , d = =
= 0.70
u 1.42
Risk neutral probability
er t d
q=
= 0.51, 1 q = 0.49
ud
K

V0
$400

volatility
r=
u=
d=
q=

1.42

400
593.17

567.63
658.20
902.16

0.70

0.35

805.50
1361.00

0.70
1.42

281.88
201.00
353.89

0.35
0.07
1.42
0.70
0.51

1.42

r
0.07

400.00
550.00

0.70

198.63
198.63

Total option value = $593.18


Real option premium = $598.13 - $400 = $198.13

Page | 20

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

ST 13.2
(a) Since $4 M is lower than the option price, it is a good investment for Merck
Co.
To give a range for the option value, first using one period lattice.
V0
K
$36M
$72M
($301.2M) ($601.2M)

t
3 years

T
3

r
0.06

0.5

u = e t = e0.5 3 = 2.3774
1
1
d= =
= 0.4206
u 2.3774
Risk neutral probability

q=

e r t d
e0.063 0.4206
=
= 0.3969 , 1 q = 0.6031
ud
2.3774 0.4206

One period lattice and option price: 4.50M


85.59
Max(85.59 - 72, 0)
13.59
Buy the stock
36
4.50
15.14
Max(15.14 - 72, 0)
0
Do not buy the stock
Through the B-S model, the option price should be $6.54M.

Page | 21

Contemporary Engineering Economics, Fifth Edition, by Chan S. Park. ISBN: 0-13-611848-8


2011 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
This material is protected by Copyright and written permission should be obtained from the publisher prior to any prohibited reproduction,
storage in a retrieval system, or transmission in any form or by any means, electronic, mechanical, photocopying, recording, or likewise.
For information regarding permission(s), write to: Rights and Permissions Department, Pearson Education, Inc., Upper Saddle River, NJ 07458.

Note: We can think that the price from the one step binomial tree is the lower bound
and B-S being the upper bound. So the option price is definitely higher than
the suggested price.
(b) With the agreement, Merck has a chance to buy Genetics with a lower price
than the prevailing market price when the project is successful. Otherwise
they just lose $4M. To make this concept simple, a basic example is
demonstrated below:
Profit/loss analysis

Success
Fail

Buy stock
Gain $37.59M
Loss $32.86M

Aforesaid agreement
Gain $9.59M
Loss $4M

The Buy stock option has a higher risk than the option.