J~ina ) sraisa
>e i'. iinriIeI: roc
o';
~asec on 5l,'i
insI:ruriIen:et
si
ei:esi:s
Q4,F
Mazurkiewicz (1972), Fuller & Hoy (1977) and others, have proposed
methods based on mathematical or graphical approaches. A comprehensive comparative study of the nine methods most commonly used
in practice has been carried out by Fellenius (1980).
Because ultimate resistance Q remains the key value in most piling
problems, it is worthwhile to recall that various definitions of this
concept are given by different authors and codes. For example:
Qplunging failure, observed sometimes insitu and corresponding to a rapid increase of settlement without an increase in
load (Figure 1)
Q asymptotic ultimate load derived mathematically or graphically (Figure 2) from the measured load settlement curve
Q, conventional ultimate load defined by many codes as the load
causing a gross settlement equal to 10% of the equivalent pile
diameter D (Figure 2), or the load at which the penetration
creep rate reaches a given value.
The failure derived by the Chin method falls into the mathematicalasymptotic category and has been defined further as Qc,N.
This paper examines the performance of Chin's recommendations
on load tests with limited settlement and the ability of his method in
predicting the proportion of shaft load.
s/Q =C+ ms
(I]
[I] becomes:
(2]
where for both equations:
the applied load on the pile head
Q
s
the pile head gross settlement
m
the slope of the linear plot corresponding to the inverse of the
asymptotic value of the ultimate resistance Q
C
a constant corresponding to the initial slope (ds '] of the load
settlement curve plotted in linear coordinates dQ /g p.
In a system of hyperbolic coordinates s versus s/Q, a given
typical relationship s-Q obtained from a routine pile test (Figure 3a)
system becomes generally:
~ in most cases and according to the evidence presented by Chin (1970)
a single straight line as shown on Figure 3b.
~ for other cases, two straight lines plot with an A and B part as illustrated on Figure 3c.
Chin's final proposal (1978) allowing the detection of broken piles
from a particular plot will not be addressed here.
The graph in Figure 3b is supposed to model the behaviour of a pile
supporting the load mainly through shaft friction or purely in end
bearing. Because the linearity is not always explicit for the first points
of the relationship, Chin (1972) recommended that these are rejected
when determining C and m.
The bilinear plot with its two straight lines which intersect (Figure
3c) is supposed to correspond to piles supported by combined shaft fric-
Load (kN)
Load, Q
22
2004
PAPER
Load,
Settlement/load,
s/0
Settlement/load,
0 (kN)
Load,
s/0
0
500
1000
1500
Settlement/load,
s/0
0.02
(mm/kN)
0.06
0 04
10
20
30
40
50
60
70
tion and end bearing. Because toe resistance needs higher settlement
to be mobilised than shaft resistance, it has been suggested that the
first part (A) would represent shaft resistance while the second part (B)
would represent total load. The validity of these assumptions will be
shown later.
The advantages presented a priori by the method are undeniable for
common practice:
~ the method is not linked with any soil parameters;
~ it gives the possibility to analyse the results of either CRP or ML
tests and for piles subject to compression or tension loading;
~ it allows a continuous check while the test is being carried out;
~ the interpretation can be carried out quite simply using at most a
pocket calculator;
~ the definition of characteristic loads Q, QQ is based on mathematical rules;
~ because of the linearity of the s vs s/Q plot, it is easy to determine
any load associated to any given gross settlement. At a settlement equal
to 10% of the pile diameter one can obtain QctttN lp which is an estimate of Q,according to the 10% criteria.
However, Fellenius (1980), Fleming (1992) and England (1999) have
shown that considerable drawbacks can complicate the interpretation
and distort the performance of the method. They are:
~ the necessity to collect data at sufficiently large gross movements, s,
to avoid deducing false ultimate resistance;
~ a marked sensitivity to the chosen test procedure demanding constant time increments as well as a sufficient number of load steps;
~ the validity of the method is jeopardised by the fact that the
real response of the pile/soil system is not exactly a hyperbolic
form. In particular, elastic shortening of the pile is a major cause
of erroneous analysis, especially in the first part (A) of the curve,
where elastic shortening can be a large proportion of the pile head
movement.
Before commencing a more comprehensive study, a strict application
of the Chin method has been made on one pile tested by the authors at
a site in Mittersheim (France) in 2001.
The pile was a 480mm diameter CFA pile, 7m long and bored through
marly clay (26% of CaCO,). At the pile toe level, the soil is characterised by a CPT cone resistance q, = 5MPa and a PMT limit pressure
p, = 1.8MPa. The water table is located at 4m depth.
with two strings of removable
The pile was instrumented
extensometers, which made it possible to measure the mobilisation
of shaft and toe resistance during the loading stages. It was
loaded according to a maintained load test (MLT) procedure, with 13
Pressure limit
(MPa)
0.1
( 'ro,3(IIo";.
10
Settlement/load,
0.002
0
0
E
E
10
0.006
s/0
(mm/kN)
0.01
0.008
10
Q,=
kdQ1
36 0 mm k
ctttN
Q,
Qa
3 5 MN
lp:
Module pressuremeter
(MPa)
1
0.004
100
10
20
30
40
resistance
0 f1
O
3
10
12
10
2004
50
100
150
200
Fnctlon (kN)
23
PAPER
compare the shaft resistance determined according to Chin's criterion
on the first part of the curve Q, GUIN Ipn: 715kN with the measured
value Q,
860kN. For the considered case history the agreement
can be considered as quite good in geotechnical terms, as the difference
between the calculated and measured values is only 17 'o.
Following these first encouraging results the performance of the
method has been investigated for a greater number of pile tests carried
out by the authors. The following items were investigated:
~ sensitivity of the method as a function of the available field readings
when determining the ultimate capacity;
~ performance of the method when estimating shaft and toe resistance.
resistances.
The 50 tests have included various pile techniques and covered an
extensive range of soils. Four piles were loaded in tension. The loads
applied on piles ranged from 675kN to 10,000kN, the pile lengths from
5m to 45m, and the pile diameters from 200mm to 1,000mm. Note that
due to substantial elastic shortening, micropiles with free (ungrouted)
length have not been considered in this study.
The following piles have been examined: CFA (12 tests), bored (six
tests), impact driven steel and concrete (17 tests), vibratory driven (five
tests) and screwed displacement auger (10 tests). The piles were
installed in clay (20 tests), sand (15 tests), calcareous soils (eight tests)
and mixed soils (seven cases).
1500
1000
500
s/Q (mm/kN)
0.02
0.04
0.06
)
E
10
E
2O
30
4o
Settlement/load,
Load, Q (kN)
ip,:
50
s =
1202
1
s+ 1.70 x 10 I
125
Qu,oian 10%/Qu,conv = 97%d
s/D 6 6%
100
8
go75
8
v =
50
=
s/D =
92%
81'8
1.4%
25
15
10
as
20
(s/D, %)
200
150
100
s.~'~ 4.'s(n,
'~A eW
~.e
d
d
50
10
15
20
(s/D, %)
method.
20
16
12
0.97
0.98 0.99
1.00 1.01
1.02
1.03 1.04
) L25
24
2004
PAPER
Chin method.
The results
are
shown on Figure 9. Note that to
reduce the effects of human errors
and contrary to Chin's recommendation, the first points of the load settlement curve were not rejected in a first
stage.
This procedure has been repeated
for all of the 50 loading tests (Figure
10). The main conclusions to be drawn
from this figure are the following:
~ the reliability of the Chin prediction improves when the last measured
gross settlement approaches lpio of
the pile diameter;
~ the majority of the data (in black
circles) lie inside a clearly defined
envelope. The only cases falling outside, a total of seven out of 50, correspond to:
plunging failure (five cases in
red
a case
not
squares),
anticipated
Chin
the
by
200
3%
ot
0 C
+25%o
150
5%o
o:) +17%
ae
10% D
100
]
50
g~o~iti
SSt Sir oo
Ioo
4 conventional
~Jo
od'
cntena
10
15
20
Settlement/load,
0
vo
0.0015
(s/D, %)
s/Q (mm/kN)
0.006
0.0045
0.003
method;
25
5.0
75
10.0
12.5
15
Settlement/load,
0.008
0.006
0.004
0,002
s/Q (mm/kN)
2.5
10.0
12.5
15
20
'S
16
16
12
Determining
0
0.2 0.4
06 08 1.0
~ ~ ~
1.2
1.4
GROUND ENGlNEERlNG
')
1+ (0' 35~0 4x Io ( head settlement s)
( pile diameter D / J[3]
[
JANUARY
2004
PAPER
3.5
'I
Scardon
30
CTRL
310 Esch
2.5
20
I
otr
15
1.0
0.5
40
20
f,
oo(
60
100
80
%o)
Figure 15.
Figure 16 shows that the increase of the number of loading steps
does not improve significantly the accuracy of the shaft resistance prediction.
60
)4
Esch
50
Conclusions
Scardon
40
fo
3O
CTRL
310
~ ~
20
41
~ -o
10
6
I
0
0
40
20
~--V'
~ ~~~ ~ ~
60
100
80
ill
%%uo)
3.5
Scardon
3.O
Esch
2.5
CTRL
310
2.0
'5
1.5
1,0
0.5
0
I I~ ~ e I ~
~ ~
~ ~
~
References
0
10
15
20
i.e. 86% of the total. The histogram of predicted versus measured shaft
resistance using the 10%o criteria is shown on Figure 13. Due to the
cases for which the predicted value greatly exceeds the measured ones,
the average is 1.07 and the standard deviation is 0.55, even though most
of the predictions are in the range of 60% to 120'/o.
Figure 14 shows the ratio of the predicted/measured shaft friction
versus the percentage of the load carried by shaft to allow better identification of the cases for which the Chin method gives poor results.
The main conclusions are as follows:
~ the predicted shaft friction is in the range of 60% to 120% of the
measured value when the shaft resistance is greater than 55%;
~ on the contrary, the Chin method significantly overpredicts the shaft
26
pages.
Fellenius BH (1980) The analysis of results from routine pile load tests, Ground
Engineering, vol13, no 6, pp 19-31.
Fleming WGK (1992) A new method for single pile settlement prediction and analysis,
Georechnique no 42, vol3, pp411-425.
Kaniraj Shenbaga R (1998) Interpretation of pile acceptance criteria from deficient data,
Engineering, vol. 124, no10, pp
ASCE Journal of Geotechnical and Geoenvironmental
1035-1040.
2004