Cost-Time-Risk Diagram:
Project Planning and Management
Dr. Peerapong Aramvareekul, PSP EVP and Daniel J. Seider, PE
ABSTRACT: This article presents the integration of cost and time performance measurement with
project risk analysis into one diagram, called the Cost-Time-Risk diagram (CTR). The author
believes the presented CTR diagram is a revolution in earned value analysis. It plots the total
brainstorming of project cost-time planning versus actual production. It also integrates evaluation of internal risks, external risks, and project specific risks. The steps to prepare and to operate the CTR diagram are explained. The article also illustrates, with graphical movement, decision-making information that many project managers struggle in developing.
KEY WORDS: Costs, earned value, planning, and project risk analysis
12
performance?
13
When
preparing
performance
measurement baseline (PMB), risk analysis
should also be integrated into it. For
instance, project risks in general are
categorized into three groups: external risks,
Figure 5 Budgeted Cost of Work Scheduled (BCWS), Budgeted Cost of Work Performed (BCWP), Actual Cost of Worth Performed (ACWP)
15
performing at the period of project start and CT-4: CTR-S is increasing while CTR-C is
continuing until almost the last period of the stable. This indicates that project time
performance is increasing while effort is
project duration, as shown in figure 6.
stable. This can happen when a project
Reading and Analyzing Information From team is highly productive and/or successfully
uses value engineering.
A CTR Diagram
The goal of the project manager is to
keep the schedule performance line (CTR- CT-5: CTR-S is stable and CTR-C is also
S) and the CTR - cost performance line stable. This indicates that project time
(CTR-C) moving forward. To accomplish performance and cost performance are
this, areas of risk need to be avoided or stable. However, this can be positive or
mitigated. Both CTR-S and CTR-C,at the negative, depending upon where or at what
time of project start, can be experiencing risk percentage levels the two lines run
issues. If not, risk issues can develop during horizontally.
the project. To avoid these becoming a
problem, the team can use fast-tracking, CT-6: CTR-S is decreasing while CTR-C is
crashing, etc., to bring the CTR-S and the stable. This indicates that project time
CTR-C out of risk problems. The best performance is decreasing while effort is
solution is to have both lines of the CTR stable. This generally happens when a
project team performs at a low level of
diagram running within the healthy area.
productivity.
Normally, CTR-S and CTR-C should
be progressing in the same direction; for
example, if CTR-S is increasing, CTR-C
will be also increasing, which means that the
team puts out more effort to get more work
done. For the ideal case, if a project is
progressing exactly as planned, CTR-S and
CTR-C will be parallel, running at the at the
100 percent and 0 percent levels
respectively. In this article, there are nine
moving directions of the CTR diagram, as
presented in a matrix table in figure 7.
CT-1: CTR-S is increasing and CTR-C is
also increasing. This indicates that project
time performance is increasing by means of
increased effort. An example of this is
overtime, such as when a project manager
has the project team spend more time to
catch up a project time performance
baseline.
CT-2: CTR-S is stable while CTR-C is
increasing. This is an indication that project
time performance is stable while effort is
increasing. This can happen when a project
team performs low productivity and/or works
on tasks that are out of scope. It most likely
shows a low productivity performance.
CT-3: CTR-S is decreasing while CTR-C is
increasing. This indicates that project time
performance is decreasing despite the fact
that effort is increasing. This can happen
when a project team performs at a seriously
low level of productivity and/or works on
tasks that are out of scope. Generally it is
caused by working on tasks that are not listed
in the project scope of work.
17
18