By
Superintending Engineer,
TVCC,
BBMP
1
Quality Control
Tests Necessary to Control a Product
Determine Quality of Product being
Produced
Performed by Contractor
Quality Assurance
Tests Necessary to Make a Decision on
Acceptance
Ensure Product being Evaluated is What
the owner Specified
Performed by Owner
QC + QA =
High Quality
Finished Road
A PR
MA Y
JUN
JUL
A UG
S EP
OCT
NOV
Cl e a r a n d G r u b
Ex c a v a t Io n
S u b - b a s e
B a s e P r e p.
Preparatory
Phase
Start-up
Phase
Production
Phase
7
Start-up Phase
Establish quality required
Resolve conflicts
Ensure testing is performed
Establish detailed testing schedule based
on production schedule
Review Safety
Production Phase
Ensure Contract Compliance
Conduct intermittent or continuous inspections to identify and correct
deficiencies
Inspect completed phases before scheduled Government acceptance
Ensure Testing reports are submitted
Ensure rework is completed
8
Requirements
Ensure Quality
Create Durable National Assets
Grossly Inadequate for Present day Needs
10
Advantages
Improved Quality
Uniformity
Economic Utilisation of Materials
Reduction in User Cost
Extra Cost Fraction of Resulting Benefits
to 1% of Construction Cost
Economic Return 5 10% of Total Construction Cost
11
Pre
Pre--requisites
Provision for Quality Control in Construction,
Specification and Estimates
Adequately Trained Staff
Adequate Equipment
Periodic Appraisal of the QC Data
Updating of Knowledge by On-job Training
12
Mixes
Gradation of Aggregates, Mix Proportion, Mixed Design
Properties
14
Finished Surface
Longitudinal Profile
Transverse Profile
Cross Slope
Texture
15
Plasticity Index
CBR on a set of 3
Specimens
Deleterious Constituents
As Required
16
17
Relative Compaction as %
of MDD
Not less than 97
Not less than 95
Expansive Clays:
Subgrade and 500 mm
portion just below the
subgrade
Remaining Portion of
Embankment
Not Allowed
Frequency (min)
Thickness of layer
Regularly
Degree of compaction
(a) Body of embankment
19
20
Acceptance Criteria
Control should be based on the mean value of a
set of 55-10 density measurement.
The criteria for acceptance shall be subject to
the condition that the MEAN DENSITY is not
less than the specified density plus:
plus:
1.65
1.65 (No. of samples)0.5 times the standard deviation
21
Granular SubSub-base
Gradation
Atternberg limits
As Required
22
Lime/Cement Content
Degree of Pulverisation
CBR or UCC
As Required
Density
Test
Requirements
40 percent (Max.)
or Aggregate Impact
Value
30 percent (Max.)
Combined Flakiness
and Elongation Indices
30 percent (Max.)
24
25
Grading
27
Surface Dressing
Quality of Binder
- do -
Stripping Value of
Aggregates
Water Absorption of
Aggregates
Grading of Aggregates
- do -
28
Aggregate Impact
Value
FI and EI of
Aggregates
Stripping value
Water Absorption of
- do Aggregates
Grading of Aggregates One Test per 25 m3 of Aggregates
29
Requirement
40 % Max.
30 % Max.
12 % Max.
Water Absorption
2 % Max.
30 % Max.
30
Bituminous Macadam
Quality of Binder
Aggregate Impact
Value
FI and EI of
Aggregates
Stripping Value
Grading of
Aggregates
Aggregate Grading
Temp. of Binder at
Application
32
Marshall Flow
2-4
3-5
1313-15
6565-75
33
900 kg Min.
Marshall Flow
2-4
3- 5
3.0 - 10-14 %
4.0 - 11-15%
5.0 - 12-16 %
65 - 75
5- 6 (50
(50--65 mm thick)
5 - 7 (30(30-45 mm thick)
Water Sensitivity
Swell Test
35
Aggregate gradation
Asphalt content
Temperature
Theoretical maximum density
In
In--place density
Smoothness
Visual inspection
36
Aggregate Gradation
SAMPLING
STOCK PILE
COLD FEEDER BELT
HOT BINS
EXTRACTED ASPHALT MIXTURE (END
PRODUCT)
37
Trouble Shooting
38
Asphalt Content
39
Temperature
40
Temperature
Grade
Bitumen
Agg.
Mix
Rolling Laying
65
90
41
Compaction
Compaction
43
Rock
Frequency
(CPM)
Amplitude
(mm)
Thickness of
Compaction,
mm
1800
1800--2500
1.2 1.5
750
0.8 1.2
500
Sandy/clay
/clayey
1600--2000
1600
0.8 1.2
600
Clay
2000
2000--2500
0.8 1.0
400
Asphalt
25002500-3500
0.4 0.6
50 75
44
ROUGH
SMOOTH
FINISH
FINISH
HIGHER SPEED
LOW DENSITY
LOWER SPEED
HIGH DENSITY
OPERATION
SPEED
45
46
47
48
49
50
51
52
53
54
55
56
Depressed Carriageway
57
58
59
60
61
62
63
64
Benkelmen Beam
65
66
67
68
69
70
71
72
73