Project Manager
Project Deliverable
Product Release
Alex B.
Start Date
End Date
Overall Progress
Tasks
2-Sep
9-Oct
20%
Responsible
Start
End
Alex B.
9/2
9/2
Agree on objectives
Frank C.
3-Sep
7-Sep
Detailed Reqs.
Jacob S.
7-Sep
9-Sep
Hardward Reqs.
Jacob S.
9-Sep
11-Sep
Jacob S.
11-Sep
15-Sep
Staffing
Alex B.
15-Sep
17-Sep
Techincal Reqs.
Frank C.
17-Sep
21-Sep
DB Development
Shari W.
21-Sep
23-Sep
API Development
Shari W.
23-Sep
25-Sep
UI Client
Alex B.
25-Sep
29-Sep
Testing
Kennedy K.
29-Sep
2-Oct
Dev. Complete
Jacob S.
2-Oct
5-Oct
Hardware Config.
Alex B.
5-Oct
7-Oct
System Testing
Kennedy K.
7-Oct
9-Oct
9-Oct
9-Oct
3/16/2016
Initiation
Development
Operations
Launch
Days
Status
Complete
Complete
Complete
Overdue
In progress
In progress
Not started
Not started
Not started
Not started
Not started
Not started
Not started
Not started
9/2
9/3
9/4
9/5
9/6
9/7
9/8
9/9 9/10
9/11 9/12 9/13 9/14 9/15 9/16 9/17 9/18 9/19 9/20 9/21 9/22 9/23 9/24
9/25 9/26 9/27 9/28 9/29 9/30 10/1 10/2 10/3 10/4 10/5 10/6 10/7 10/8
10/9