QUANTITY ESTIMATES
April 2006
QUANTITY ESTIMATES
Table of Contents
Section
7.1
GENERAL.................................................................................................................7-1
7.1.1
7.1.2
7.1.3
7.2
Page
QUANTITIES............................................................................................................7-5
7.2.1
7.2.2
7.2.3
7.2.4
7.2.5
7.2.6
April 2006
General.....................................................................................................7-5
Reinforcing Steel .....................................................................................7-5
Structural Steel.........................................................................................7-5
Construction Stakes, Lines, and Grades ..................................................7-6
Construction Estimates and Final Plans (As-Built Plans) .......................7-6
On-The-Job Training (OJT).....................................................................7-6
7-i
7-ii
QUANTITY ESTIMATES
April 2006
QUANTITY ESTIMATES
CHAPTER 7
QUANTITY ESTIMATES
The designer must compile an accurate estimate of the project construction quantities. This
information leads directly to the Engineers Estimate, which combines the computed quantities
of work and the estimated unit bid prices. An accurate estimate of quantities is critical to
prospective contractors interested in submitting a bid on the project. This Chapter presents
information on estimating quantities for bridge projects.
7.1
GENERAL
7.1.1
Bridge quantities are generated and placed on the Summary of Estimated Quantities Sheet. For
information on the Summary of Estimated Quantities Sheet, see Section 6.3.
7.1.2
When preparing quantity estimates, the designer should consider the following guidelines:
1.
Units of Measurement. Report the quantity estimates for all contract bid items consistent
with the terms and units of measurement presented in the SCDOT Standard
Specifications. Figure 7.1-1 illustrates the units of measurements and rounding criteria
for typical bridge items that should be used on the Summary of Estimated Quantities
Sheet.
2.
SCDOT Standard Specifications. Cross check all items against the SCDOT Standard
Specifications and the SCDOT Supplemental Specifications to ensure that the appropriate
pay items, methods of measurement, and basis of payment are used. Structural items are
presented in Division 700 of the SCDOT Standard Specifications.
3.
Rounding. Prepare a computation for each item used on the project. Include all
computations in the project file. Round the output quantities from these computations
according to Figure 7.1-1, and place them on the Summary of Estimated Quantities Sheet
as discussed in Section 6.3.
4.
Final Bridge Cost Estimate. All items described in the bridge plans that are included in
the cost estimate must be shown in the Summary of Estimated Quantities Table. Chapter
8 provides the Department criteria for preparing construction cost estimates.
April 2006
7-1
QUANTITY ESTIMATES
Item
Unit
LF
LS
CY
CY
EA
SF
CY
SY
SF
SY
LB
LB
LB
LB
LF
LF
LF
LF
LS
LF
LF
LF
LF
EA
LF
MBF
LS
LF
LF
LF
LF
EA
EA
EA
EA
LS
EA
Rounding
Accuracy
5
5
1
1
5
0.1
0.1
1
1
1
1
1
1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
1
0.1
0.1
0.1
0.1
0.1
0.1
1
1
1
1
April 2006
QUANTITY ESTIMATES
Item
Unit
LF
EA
EA
LF
LF
LF
EA
LF
LF
EA
LF
LF
LF
LF
EA
LF
LF
EA
EA
LF
LF
LF
LF
LF
EA
LF
CY
CY
SF
LF
LF
EA
EA
EA
SY
SY
SY
Rounding
Accuracy
1 (for each pile)
1
1
1 (for each pile)
1
0.5
1
1
1
1
1
1
1
1
1
1
1
1
1
0.1
0.1
0.1
0.1
0.1
1
0.1
0.1
5
1
1
0.1
1
1
1
1
1
1
April 2006
7-3
QUANTITY ESTIMATES
Item
SY
SY
CY
SF
SY
LF
Rounding
Accuracy
1
1
0.1
1
1
0.1
TON
SY
SY
5
0.1
Unit
7.1.3
Each pay item has an official title and item number that is tied to the SCDOT Standard
Specifications. These items are listed in the SCDOT Standard Specifications and the pay item
spreadsheet on the Departments website. The Department uses these coded item numbers for
tracking and as a historic database. In most cases, the AASHTO TrnsPort Proposal and
Estimates System (PES) will already have the pay item number. See Section 36.2.2 of the
Highway Design Manual for additional information on computer tracking.
For some specialty or new items, the pay item number may not be in the database. Therefore, if
the designer is unable to locate a pay item, the designer will be required to conduct the
following:
1.
Check. The designer should ensure that there is not an actual number for the item within
the system by entering the item into PES.
2.
SCDOT Standard Specifications. The designer should review the SCDOT Standard
Specifications and SCDOT Supplemental Specifications to determine if there is a method
of payment for the item.
3.
New Pay Item. If an item does not exist in the PES, the designer may request a new pay
item through the Bridge Design Section.
7-4
April 2006
7.2
QUANTITY ESTIMATES
QUANTITIES
7.2.1
General
The following Sections discuss the procedures that should be used to determine the cost estimate
for some of the typical bridge items used on the project.
7.2.2
Reinforcing Steel
The quantity estimate for reinforcing steel is based on the weight of the reinforcing bar. The
typical sizes the Department uses are presented in Figure 7.2-1. When estimating the quantity
for reinforcing steel, use Figure 7.2-1 to obtain the weight in pounds for the appropriate design
size. Anchor bolts and tie-bar assemblies are included in the weight of reinforcing steel. The
weight of incidental items (e.g., reinforcing steel bolsters, couplers) are not included in this
quantity estimate.
7.2.3
Structural Steel
The quantity estimate for structural steel is based on the weight of the steel components in the
structure. Structural steel is bid as a lump sum, but the steel weight and grade is provided for
information only to assist the Contractor in preparing the bid. Include the weight of all beams,
plates, diaphragms, stiffeners, bearing plates, bolts, shear studs, etc., in the estimate.
Calculate the weight of the steel using the following guidelines:
1.
2.
3.
Calculate the weight on the rectangular dimensions for all plates and overall lengths for
all structural shapes with no deductions for copes, clips, sheared edges, punching, or
borings.
4.
Measure bolts, nuts, and washers for payment on the basis of computed weight as
presented in the AISC Manual of Steel Construction.
5.
April 2006
7-5
QUANTITY ESTIMATES
Diameter
Area
Weight
US Customary
Designation
Metric
Designation
in
in2
lb/ft
#3
#10
0.375
0.11
0.376
#4
#13
0.500
0.20
0.668
#5
#16
0.625
0.31
1.043
#6
#19
0.750
0.44
1.502
#7
#22
0.875
0.60
2.044
#8
#25
1.000
0.79
2.670
#9
#29
1.128
1.00
3.400
#10
#32
1.270
1.27
4.303
#11
#36
1.410
1.56
5.313
#14
#43
1.693
2.25
7.650
#18
#57
2.257
4.00
13.600
7.2.4
The Assistant State Bridge Design Engineer Specifications will request this information from
the Construction Office, which in turn will request the information from the District. This item
is included in the Bid Proposal Package, but is not included in the Summary of Estimated
Quantities Table in the bridge plans.
7.2.5
The Assistant State Bridge Design Engineer Specifications will request this information from
the Construction Office, which in turn will request the information from the District. This item
is included in the Bid Proposal Package, but is not included in the Summary of Estimated
Quantities Table in the bridge plans.
7.2.6
When applicable, the cost estimate information for OJT requirements is provided to the Bridge
Cost Estimate Coordinator by the Roadway Specifications and Estimate Group.
7-6
April 2006