S.No.
Description of Work
Hours
Reqd
Start
Date
MAJOR ACTIVITIES
1
126
17.09.16
72
17.09.16
20
12
27.09.16
17.09.16
Boiler cooling
36
16.09.16
40
19.09.16
222
18.09.16
24
18.09.16
12
19.09.16
5.3
10
21.09.16
48
26.09.16
56
8
10
12
12
27.09.16
29.09.16
30.09.16
30.09.16
30.09.16
1
2
3
Service air line Tapping in RHS & LHS 16 mtr for maintenance
6
7
8
9
19
11
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Windbox Inspection
U#2 Mill-2B LOP-B seal leak arresting
19
27
28
30
31
32
33
34
35
36
37
38
40
41
42
1
2
3
4
5
24
1
2
9
10
11
12
4
5
6
7
8
9
10
1
2
3
ELECTRICAL ACTIVITIES
GT-2 Y PH Bushings Moose connectors inspection
UT-2A & 2B tap changer oil changing & overhauling
ID Fan-2B ,Coolinfg fan-2B Vibration
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
ELEC
ELEC
ELEC
ELEC
ELEC
ELEC
29
30
31
32
33
34
35
36
37
38
39
40
41
42
1
2
3
4
5
6
7
8
9
10
12
13
14
15
1
2
PM
PM
PM
PM
PM
PM
FOR
FOR
FOR
FOR
FOR
FOR
1
2
3
4
5
6
7
8
9
Modifications
Power supply of HP/LP bypass drives
EH Oil Trip Logic - Low Level Switch-2/3 to be added
TOP- Hardwire Start Logic-1/2 Pressure Switch
BCP auto start permissive
Generator seal oil pump discharge header pressure transmitter
should be provided in seal oil skid
ETS- trip logic on HP & LP condensor vaccum switches - arming
coondition from pressure switch to be changed to turbine
speed > 80 rpm
MFT for MS pressure > 17mpa and temperature >600 with 300
sec delay
MFT for reheat temperature > 630 with 300 sec delay
Alarm for coal mill; 1. feeder running with roller lifted for 3 min,
2. bowl dp > 5.5 kpa
10
Operation of mill reject hopper outlet gate from dcs and alarm
on gate open > 3 min
11
12
Mill inerting SOV auto open when flow less than 20 TPH
13
Mill inerting SOV auto open when outlet temperature (3/6) >
90 for 3 sec
14
Mill inerting SOV open feedback for start permissive. feed > 25
TPH for 60 sec as closing permissive
15
Currently mill trip condition exists on 3/6 MDV close. the logic
to be implemented only for start up and alarm but not trip
16
17
18
19
20
21
24
25
26
27
22
28
29
30
Finish
Date
Time
20:00 23.09.16
2:00
8:00
8:00
21.09.16
0:00
12:00 27.09.16
6:00
0:00
20:00 22.09.16
6:00
0:00
28.09.16
0:00
8:00
16:00
0:00
10:00
22:00
29.09.16
30.09.16
30.09.16
30.09.16
01.10.16
16:00
0:00
10:00
22:00
10:00
Completed
Burners inspection under progress
Waterwall tube panel welding under progress
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Pass C&D Inspection done and A pass inspection under
progress
E2,E4,E5 BOX UP DONE. G4 & G5 DPT done.Box-up under
progress
completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Seal Trough Cleaning Completed. Manual cleaning under
progress
A& C Completed
Completed
Completed
Competed
Competed
Competed
Completed
Completed
Completed
Mill Motors 2A to 2H,ID-2B,FD,PAN FAN,CEP,MDBFP,MDBFP
AOP,ACW,CCCW,AC JOP,Stator water,MSP completed.
under observation
Completed
Completed
Completed
Completed (39114548)
We found tranduscer(BR-ph) I/P terminal got damaged
same has been made
ready . Found ok
Trail taken and found motor tripping n Over load(3.26A in
all
phases),Checked motor parameters found normal(60 ohms
balanced & B/W
winding-Gnd=Open)
Completed
completed
Completed. Tightness & TB's cleaning done
and observed temperatures found normal.
completed
Under Progress
completed
Completed
completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Work under progress
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Under progress, 2A & 2D Completed
Completed
Completed
Completed
Completed
Under progress
Completed
Completed
Completed
Completed
Under Progress
Under Progress
Completed
Under Progress
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Mechanical team has to remove insulation and thermowell
has to be welded.
Completed
Completed
Completed
Completed
Completed
Completed
Notification/Order Number
39114535
39114541
39114534
39114542
39114543
39114544
39114545 & 39114546
39627177
39114549
39114551
39114542
39114531
39114532
39114545, 39114550
39114546, 39114554
39114556
351031424
351028177
39114533
39627253
39627254
39627255
39627256
39627257
39627258
39114689
39114692
39114688
351022164
351033905
351034179
351022132
39627190
39627189
351027803
39114530
39114462
39627166
39627167
39627168
39114537
39627126
39114445
39114577
351010375
351014204, 351031000, 351032226
351027409
351030305
351030666, 351030794, 351031558
351032033, 351032401
351032147
351032636
351033343
351033497
351033439
351034050
351034125
351034126
351034122
351034133
39104581
39105218
39105419
39108841
39109608
39109796
39112936
check the feasability of circuit and
found not required for BTG
39114553
39114536 & MOC-192
39114569
39114568
39114569
39114568
MOC-149
MOC-143
MOC-192
MOC-247
351033020
351033760
351030306
351022847
351023426
351024244
351024310
39627179
39114573
TPCIL/OPN/102
TPCIL/OPN/145
TPCIL/OPN/146
TPCIL/OPN/153
TPCIL/OPN/169
TPCIL/MOC/209
TPCIL-MOC-198
TPCIL-MOC-199
TPCIL-MOC-215
TPCIL-MOC-219
TPCIL-MOC-220
TPCIL-MOC-228
TPCIL-MOC-229
TPCIL-MOC-230
TPCIL-MOC-232
TPCIL-MOC-248
TPCIL-MOC-249
TPCIL-MOC-251
TPCIL-MOC-255
TPCIL-MOC-257
TPCIL-MOC-260
TPCIL-MOC-284