Agenda
NEC3 Forms of Contract
Recent Application in Hong Kong
Some basic principles (with focus on ECC)
Roles and Duties (with focus on ECC)
Observations in some pilot contracts
Looking forward
Recent Application of
NEC in HK
Public Sector
HK Government in trial use of NEC since 2009
DEVBs Directives in Sept 2013
Extended pilot on NEC in public works (incl. D&B)
contracts to be tendered in 2015 & 2016 as far as
possible
At least 1 consultancy agreement for trial by each
works department per annum starting from 2014
Public Sector
No. of Government pilot NEC as at end Dec 2015:
Works contracts
3 ECC target cost contracts completed
31 on-going contracts
ECC priced contracts x 11
ECC target cost contracts x 9
TSC priced contracts x 11
Consultancy agreements
4 on-going PSC contracts
ECC: Engineering & Construction Contract
TSC: Term Service Contract
PSC: Professional Services Contract
Public Sector
Private Sector
Use of NEC in:
CLP
MTRC
Hong Kong Jockey Club
Hong Kong Academy
Accepted Programme
Timescale for actions
No surprises: early warning
Sort it NOW for compensation events (CEs) and other issues
Main
Option
Priced
Target
Activity
Schedule (AS)
Bill of
Quantities (BQ)
A
C
B
D
No specified
pricing doc.
Cost
Reimbursable
E
F
Management
11
Option B
Re-measurement contract with priced BQ
Measured workdone payments priced by BQ rates / prices
CEs assessed by Defined Cost NOT BQ rates / prices
unless with prior agreement
12
Option D
Priced BQ ITC
Payments on Defined Cost + Fee subject to pain / gain share
Final target cost = ITC + adjustments for CEs, remeasurement of BQ & others
13
Gain Scenario
Final TOP
Final PWDD
Contractor
50%
Employer
50%
Final PWDD
Pain
Share
110%
Final TOP
Contractor
50%
Employer
50%
Final PWDD
Final TOP
Gain
Share
Pain Share
Pain Scenarios
Gain
Share Share
range: up
to 110% of final target cost (total of the Prices - TOP)
Example
Share % - Employer : Contractor = 50 : 50 within share range
PWDD Price for Work Done to Date
14
Contractors
Remaining pain
105%
Employers pain
capped
15
16
Defined Cost
Beware: Different definitions for Options A/B, C/D, E and F
In short:
Amount defined in contract as reimbursable to Contractor
including:
Contractors costs incurred / to be incurred and
Sums calculated using rates and % as stated in contract
Less: Disallowed Cost in Options C to E
17
Fee =
Contractors costs
People
Equipment
Plant & Materials
Others stated in
Schedule of Cost
Components
Payments to
Subcontractors
Defined Cost
18
19
PM notifies
max 8 wk
PM instructs quote
Contractor notifies
3 wks
1 wk
PM says no
yes
PM silent?
C notifies;
PM has further 2 wks;
otherwise deemed acceptance
PM to assess
Contractor quotes
2 wks
PM replies
Implement CE
20
CE Financial Assessment
Change to the Prices (ECC 63.1)
actual Defined Cost of the work already done,
forecast Defined Cost of the work not yet done and
resulting Fee
21
22
Employer
Supervisor /
Supervisors delegates**
Supporting Staff
Supporting Staff
Key Duties
**
Key Duties
23
24
25
26
Stock Management
ECC requirements:
Not specified but reflected from coverage of Disallowed Cost
27
QS as PMs delegate
With PMs power on delegated actions
28
29
30
31
32
More Observations..
Saving in construction costs in target cost contracts
Cost Savings Design
Shorter construction period saving in preliminaries
33
More Observations..
Challenges in Defined Cost assessment - e.g.
Reasonableness of staff salary, allowances and bonus
Purchase or hire option for Equipment
34
NEC Contracts
Looking Forward.
35
Looking Forward..
Expected more and more NEC contracts in public
sector
Extent of impact on private sector still unknown
Yet QS profession inevitably exposed to more and
more NEC contracts
Increasing demand for competent financial
administration and monitoring services in NEC
contracts
36
Co-operation
Our Project
37
38
Thank you
Any questions
hayman.choi@mottmac.com
39