KPP227
KPP227
Antti Salonen
What is layout?
Layout decisions:
Require substantial investments
(money and effort)
Involve long-term commitments
Impact the cost and efficiency of
short-term operations
KPP227
Antti Salonen
Layout types
Layout requirements are determined by the type of operation.
Less customization and higher volume
Process
Characteristics
KPP227
(1)
Customized process,
with flexible and unique
sequence of tasks
(2)
Disconnected line flows,
moderately complex
work
(1)
Low-volume
products, made
to customer
order
(2)
Multiple products with low
to moderate volume
(3)
Few major
products,
higher
volume
(4)
High volume, high
standardization,
commodity
products
Job
process
Small batch
process
Batch processes
Large batch
process
(3)
Connected line, highly
repetitive work
Line
process
(4)
Continuous flows
Continuous
process
Antti Salonen
Layout strategy
KPP227
Continuous flow
Extremely high volumes, standard products, e.g. paper, milk.
Hybrid layouts
Warehouses
Service layout
Antti Salonen
Assemble-to-Order Strategy
Used by manufacturers that produce a wide
variety of products from relatively few
subassemblies and components after the
customer orders are received.
DD
Consume
PD
DD
Consume
OP
PD
DD
OP
KPP227
PD
OP
MTO:
Make-to-Order Strategy
Demand
Antti Salonen
Consume
Layout strategy
Job shop process
A process with the flexibility to produce a wide variety of products in
significant quantities, with considerable complexity and divergence in the
steps performed => Resources allocated around the process
Line Process
A process with high volumes and standardized products => Resources
organized around the product
Hybrid layout
Create flow lines in parts of the workshop to increase efficiency, e.g. One
worker multiple machines, Cell/Group technology.
KPP227
Antti Salonen
KPP227
Antti Salonen
KPP227
Antti Salonen
KPP227
Antti Salonen
KPP227
Antti Salonen
10
Closeness Factors
Department
1. Administration
10
2. Social services
3. Institutions
4. Accounting
5. Education
6. Internal audit
KPP227
Antti Salonen
11
EXAMPLE
KPP227
Antti Salonen
12
Salonen machining is a machine shop that produces a variety of small metal products on general-purpose equipment. A
full shift of 26 workers and a second shift of 6 workers operate its 32 machines. Three types of information are needed
to begin designing a revised layout for Salonen machining: Space requirements for each center, available space and
closeness factors. Departments 3 and 4 can not be moved because of constraints in the building design.
Space requirements for each center: Salonen machining has grouped its processes into six different departments: burr
and grind, NC equipment, shipping and receiving, lathes and drills, tool crib, and inspection. The exact space
requirements of each department, in square meters, are listed below.
Department
Area needed m2
100
2. NC equipment
95
75
120
5. Tool crib
80
6. Inspection
70
TOTAL:
540
The layout designer must tie space requirements to capacity plans, calculate the specific equipment and space needs
for each center, and allow circulation space such as aisles and the like.
KPP227
Antti Salonen
13
Available space:
A block plan allocates space and indicates placement of each department. When
describing a new facility layout, the plan need only provide the facilitys dimensions and
space allocations. When an existing facility layout is being modified, the current block
plan also is needed. Salonen machinings available space is 36 meters by 15 meters,
or 540 square meters. The designer could begin the design by dividing the total
amount of space into six equal blocks (90 square meters each), even though
inspection needs only 70 square meters. The equal space approximation shown in the
figure below is good enough until the detailed layout stage, when larger departments
(such as lathes and drills) are assigned more block space than smaller departments.
3
15m
36m
KPP227
Antti Salonen
14
Closeness factors:
The layout designer must also know which centers need to be located close to one
another. Location is based on the number of trips between centers and qualitative
factors.
Below is Salonen machinings trip matrix, which gives the number of trips (or some
other measure of materials movement) between each pair of departments per day.
20
2. NC equipment
3 Shipping and receiving
4 Lathes and drills
20
10
-
80
75
15
-
90
70
5 Tool crib
6 Inspection
KPP227
Antti Salonen
15
Develop an acceptable block plan for Salonen machining, using trial and error. The
goal is to minimize materials handling costs.
Solution:
A good place to start is with the largest closeness ratings in the trip matrix (say, 70 and
above). Beginning with the largest number of trips and working down the list, you might
plan to locate the departments as follows:
3
15m
Departments 3 and 4 should remain at their current locations because of the other
considerations.
If after several attempts you cannot meet all five requirements, drop one or more and
try again. If you can meet all five easily, add more (such as for interactions below 70).
The block plan in the figure shows a trial-and-error solutoion that satisfies all five
requirements. We started by keeping departments 3 and 4 at their current locaitons. As
the first requirement is to locate departments 3 and 6 close to each other, we put 6 in
the southeast corner of the layout. The second requirement is to have departments 1
and 6 close together, so we place 1 in the space just to the left of 6, and so on.
KPP227
Antti Salonen
36m
16
Improvement analysis:
The table below includes all department pairs that have some load in between them. The Distance figures are
based on recti-linear movements.
Current plan
Proposed plan
Department
pair
Load
Distance
Load-Distance
Distance
Load-Distance
1-2
20
60
20
1-4
20
40
20
1-6
80
160
80
2-3
10
20
30
2-5
75
150
75
3-4
15
15
15
3-6
90
270
90
4-5
70
70
70
Tot:
785
3
15m
36m
400
3
15m
36m
KPP227
Antti Salonen
17
Technical considerations
Requirements of different tasks
If these are quite different, it may not be feasible to place the tasks in the
same workstation.
If these are incompatible, it may not even be feasible to put the work
stations near each other.
Human factors
When humans are involved, tasks may take different amount of time to
complete.
Equipment limitations
Space limitations
KPP227
Antti Salonen
18
KPP227
Antti Salonen
19
Description
Time
(sec)
4.
40
None
30
Attach axle
50
Attach agitator
40
25
15
Attach controls
20
D, E
Mount nameplate
18
F, G
D
B
30
40
Antti Salonen
20
40
25
50
KPP227
Immediate
Predecessor(s)
Total 244
3.
5.
Work
Element
I
G
18
15
20
EXAMPLE
KPP227
Antti Salonen
21
EXAMPLE X.4
Green Grass, Inc., a manufacturer of lawn and garden equipment, is designing
an assembly line to produce a new fertilizer spreader, the Big Broadcaster.
Using the following information on the production process, construct a
precedence diagram for the Big Broadcaster.
Work
Element
Description
Time
(sec)
Immediate
Predecessor(s)
40
None
30
Attach axle
50
Attach agitator
40
25
15
Attach controls
20
D, E
Mount nameplate
18
F, G
Total 244
KPP227
Antti Salonen
22
SOLUTION
The figure shows the complete diagram. We begin with work element A, which
has no immediate predecessors. Next, we add elements B and C, for which
element A is the only immediate predecessor. After entering time standards and
arrows showing precedence, we add elements D and E,
and so on. The diagram simplifies interpretation.
Work element F, for example, can be done
D
anywhere on the line after element C is completed.
H
40
B
However, element I must await completion of
20
E
elements F and G.
30
6
A
40
F
C
25
50
I
G
18
15
KPP227
Antti Salonen
23
[%]
[%]
Antti Salonen
24
EXAMPLE
KPP227
Antti Salonen
25
EXAMPLE X.5
Green Grasss plant manager just received marketings latest
forecasts of Big Broadcaster sales for the next year. She
wants its production line to be designed to make 2,400
spreaders per week for at least the next 3 months. The plant
will operate 40 hours per week.
a. What should be the lines cycle time?
b. What is the smallest number of workstations that she could
hope for in designing the line for this cycle time?
c. Suppose that she finds a solution that requires only five
stations. What would be the lines efficiency?
KPP227
Antti Salonen
26
SOLUTION
a. First convert the desired output rate (2,400 units per week) to an
hourly rate by dividing the weekly output rate by 40 hours per
week to get units per hour. Then the cycle time is
c = 1/r = 1/60 (hr/unit) = 1 minute/unit = 60 seconds/unit
b. Now calculate the theoretical minimum for the number of
stations by dividing the total time, t, by the cycle time,
c = 60 seconds. Assuming perfect balance, we have
t
244 seconds
TM =
=
= 4.067 or 5 stations
c
60 seconds
c. Now calculate the efficiency of a five-station solution, assuming
for now that one can be found:
t
244
= 81.3%
Efficiency =
(100) =
nc
5(60)
KPP227
Antti Salonen
27
KPP227
Etc
Antti Salonen
28
KPP227
All the tasks predecessors must be assign to the same or earlier work stations
Antti Salonen
29
KPP227
Antti Salonen
30
EXAMPLE
KPP227
Antti Salonen
31
Work
Element
Description
Time (sec)
Immediate
Predecessor(s)
D
40
40
None
30
Attach axle
50
Attach agitator
40
25
40
15
Attach controls
20
D, E
Mount nameplate
18
F, G
30
F
C
25
50
I
G
Antti Salonen
20
Total 244
KPP227
18
15
32
Description
Time (sec)
Immediate
Predecessor(s)
40
None
30
Attach axle
50
Attach agitator
40
25
15
Attach controls
20
D, E
Mount nameplate
18
F, G
Total 244
D
B
30
20
A
40
40
C
50
F
25
I
G
18
15
KPP227
Antti Salonen
33
KPP227
Antti Salonen
34
Solution:
Station
Candidates
Choice
Cumulative
time
Idle time
S1
40
20
S2
B,C
50
10
S3
B, F, G
30
30
E, F, G
55
D, E, G
40
20
E, G
55
E, I
18
42
24
36
44
16
S4
S5
When implementing this solution, we must observe precedence requirements within each station.
For example, the worker at station S5 can do element I at any time but cannot start element H until
element E is finnished.
KPP227
Antti Salonen
35
D
B
30
20
A
40
40
F
C
25
50
I
G
18
15
KPP227
Antti Salonen
36
KPP227
Antti Salonen
37
The manager of a computer assembly line plans to produce 100 assembled computers per 10-hour
workday. Work element data for the assembly is shown in the table below.
Work
element
Time
(minutes)
Immediate
predecessors
None
C, D
D, E
I, J
KPP227
Antti Salonen
38
C
A
E
D
KPP227
F
G
Antti Salonen
39
C
A
E
D
Work
element
Time
(minutes)
RPW
41
39
31
35
30
18
15
14
14
12
KPP227
WS
Candidates
CT
A, B, C
E, G
F, H
J, K
Antti Salonen
40
C
WS1
E
D
WS2
KPP227
WS6
WS4
F
G
WS3
Antti Salonen
WS7
I
WS5
41
KPP227
Antti Salonen
42
Parallel workstations
Bottlenecks may be the result of difficult or very long tasks and
may disrupt the flow of products down the line.
In these situations, parallel workstations increase the work flow
and provide flexibility.
KPP227
Antti Salonen
43
KPP227
Antti Salonen
44
Workers
Another approach to achieving a balanced line is to cross train
workers to be able to perform multiple tasks.
This implies that a worker with temporarily increased idle time can
assist other workers to maintain the flow of the line, so called
dynamic line balancing.
KPP227
Antti Salonen
45
KPP227
Antti Salonen
46
KPP227
Antti Salonen
47
Cell/Group technology
This manufacturing technique groups parts or products with similar
characteristics into families and sets aside groups of machines for
their production => A line within the job shop.
Based on shape, size, manufacturing requirements etc.
Goal: efficient production with minimal change-over and set-up times
KPP227
Antti Salonen
48
EXAMPLE
Cell/Group technology
KPP227
Antti Salonen
49
KPP227
Antti Salonen
50
Lathing
Milling
Drilling
M
Grinding
Receiving and
shipping
Assembly
A
Antti Salonen
51
Assembly
area
A
Cell 2
Cell 1
Receiving
Cell 3
L
Shipping
KPP227
Antti Salonen
52
After:
Before:
KPP227
Antti Salonen
53
Storage layouts
The design of storage facilities present a different set of factors
than the design of factory layouts.
Frequency of order is an important consideration:
Items that are ordered frequently should be placed near the entrance of
the facility
Items that are ordered infrequently should be placed in the rear of the
facility.
KPP227
Antti Salonen
54
Storage layouts
If items are ordered/sold together it is beneficial to store them
close to each other.
Other considerations:
Width and length of aisles
Height of storage racks
Need to periodically make a physical count of stored items
Modes of internal transport
Level of automation
KPP227
Antti Salonen
55
EXAMPLE
Storage Layout
KPP227
Antti Salonen
56
KPP227
Antti Salonen
57
KPP227
Antti Salonen
58
Office layouts
Office layouts are undergoing transformations
as the flow of paperwork is replaced by
electronic communications.
This implies that there is less need to place
office workers in a layout that optimizes a
physical flow.
However, providing efficient use of space and
possibilities for cooperation between
colleagues are of course important issues.
KPP227
Antti Salonen
59
KPP227
Antti Salonen
60
Questions?
antti.salonen@mdh.se
Aggregate planning
KPP227
Antti Salonen
61