w40
22
23
24
25
PM (Project
Manager)
Engineer-1
W41
29
30
W42
6
13
14
15
16
19
W44
21
22
12
W43
20
23
26
W45
27
28
29
30
W46
2
W47
9
10
11
12
Design of floor plates for Level level-1 Design of floor plates for Level level-2 + Report Design of floor plates for Level level-3
+ Report preperation + reinforcement
preperation + reinforcement intent.
+ Report preperation + reinforcement
intent.
intent.
15
W48
16
17
18
19
22
W49
23
24
25
26
29
W50
30
W51
7
10
13
14
15
16
17
Design of stair-1&2 +
reinforcement intent.
Hours to contribute for any revisions in the project either from RFI + architect or during constructrion phase.
Holiday
Engineer-2Trainee
28
Holiday - Deepawali
21
Project Introducion /
Inputs / Clarifications and
agreement on WO/ATR
Holiday - Dusherra
W39
Activity
GEC
RFI
GEC
TEKLA Modeling
BIM Modeler -1
Placing Column Reinforcement in TEKLA & Generation of Reinforcement Placing Pile Cap Reinforcement in TEKLA & Generation of Placing storage lift Wall Reinforcement in TEKLA & Generation
Drawings
Reinforcement Drawings
of Reinforcement Drawings
BIM Modeler -2
or CAD RC
BIM Modeler -3
or CAD RC
HOD
Review
HOD
Review
HOD
Review
Review of
Safe - slab at
level -0
HOD
Review
HOD
Review
HOD
Review
HOD
Review
HOD
Review
Review of pile cap design + review Review of lift and stair wall design review of beam
of Slab results at level - 3 & 4
design
HOD
Review
Stairacse
review- 1&2
HOD
Review
HOD
Review
Placing Staircase 4
Reinforcement in
TEKLA & Generation
of Reinf. Dwgs.
HOD
Review
Stairacse
review- 3&4
drawings review for slab and beam reinforcement drawings review for slab and beam review of draawings for slab and
at level 0 & 1 + walls
reinforcement at level 2 +
beams at level 3 & 4 + staircase 3
staircase 1 &2
&4
Activity
Receive scope document/ project
documents from RFI + coordination and
clearing doubts with RFI + Study of
Design Criteria and study of Euro codes
for application of wind, snow and earth
pressure loads.
Anyother loads to be discussed with Kirsi
Engineer
Acitivity
Project documentation
total nos
of hours
spend on
project
Asst.
Design
Engineer
-1
total nos
of hours
spend on
project
HOD
total nos
of hours
spend on
project
Total nos of hours spend on the project by whole staf
Conteng
encies
(10%) of
total
hours
spend to
cover
the
scope
due to
missund
erstood
of ATR.
Engineer
-3 ( to be
used if
consider
able
comment
s been
received
from
Finland
office
during
the
project
flow
week ) 5% of
total
hours
spend to
cover
the
scope
Acitivity
41
32
40
42
43
40
39
40
32
mentation
236
32
40
40
32
248
40
32
16
16
20
20
16
140
6
48
848
85
50
983
hrs
46
s per week
44
20
20
20
32
32
40
32
16
16
40
16
16
20
Keep Resource for incorporation of any design changes due to comments or architectural changes