Link boxes
technicalstandard
ETS-53-01-01 Rev. 0
REVISION VIEW
Document no.:
Version
Author
13/94559-1
Document status/change
Reviewer
USG
First draft
USG
Second draft
USG
Final draft
SRO
USG
Approved
Approver
Date
12-08-2013
13-08-2013
SDO
30-08-2013
2/7
Table of contents
Table of contents
1.
Introduction
2.
3.
Functional requirements
4.
Technical requirements
5.
Design requirements
6.
Documentation
3/7
1. Introduction
This standard specifies how Energinet.dk chooses to install and place link boxes for HV
cable systems. The standard is for all 132 400 kV cable projects using link boxes with
direct grounding, single point bonding or crossbonding.
In case of a single point bonding, an Earth Continuity Conductor (ECC) must be installed
with the HV cable.
3. Functional requirements
There are different types of link boxes; Crossbonding link boxes, Connection link boxes
(screens connected but not grounded), grounding link boxes and even combinations hereof.
Crossbonding and connection link boxes shall be equipped with Surge Voltage Limiters
(SVL) for protection of cable outer jacket. Each link box shall be equipped with 6
connection points, for the metal sheaths of the HV cables.
A connection link box is used for connecting three cable screens, without grounding, see
Figure 1 a). A crossbonding link box is used for phase shifting of the cable metal sheaths,
see Figure 1 b). A grounding link box is used for direct grounding of the HV cable metal
sheaths, see Figure 1 c).
Figure 1 A schematic of a) A connection link box for three phase connection point, b) A link
box with crossbonding, and c) A link box with direct grounding.
There can be different variations and combinations of the link boxes shown in Figure 1;
single phase open end (with an SVL), single phase grounding, three phase grounding in one
4/7
side and open on other side (with SVL) or three phase open end without connection (SVL
on each phase).
4. Technical requirements
The link box components must be:
The SVL shall connect the metal sheath to ground in case of over voltages due to switching
and lightning transients. The Transient Overvoltage Capability (TOC, 1s) must be high
enough to allow for the 50 Hz voltage induced from the maximum fault current in the
system. If SVL will conduct during fault, it can become defect. The size of the SVL shall
therefore be designed with a minimum and maximum size.
Minimum size of SVL
The minimum size of the SVL shall be able to withstand the induced AC voltage on the
metal sheath, during steady state and short circuit plus a margin of 20% and a simplified
safety margin level of 25%.
Furthermore, the voltage rating of the SVL shall be high enough to allow periodic testing of
the cable jacket, normally 5 kV DC or as specified.
I.e. in some cases it is required that the Jacket can be tested to the voltage of the after
installation test of up to 10 kV due to limited accessibility of the Link boxes just after
installation.
Maximum size of SVL
The maximum size of the SVL is limited to the residual voltage [Ures] due to a traveling
wave from a lightning. The most harmful transient shall be used for maximum size design,
which normally is due to a lightning to the entrance of the cable line. The lightning impulse
withstand voltage (1.2/50 s) is 1425 kV and the switching impulse withstand voltage
(250/2500 s) is 1050 kV. Both shall be considered when the worst case is defined.
5/7
5. Design requirements
In order to reduce probability of failure, Energinet.dk wants to minimize the number of link
boxes. The length of minor sections can be maximized with straight joints, according to the
expected maximum short circuit current during the life time of the cable and withstand
level of the jacket.
Whenever possible, SVLs should be avoided.
Following two possibilities should therefore be considered:
Installation of link boxes without SVLs. This does not include link boxes on the first
major section from each cable end.
Use of cable lines with direct crossbondings. These crossbondings do not include
link boxes and cannot be used on the first major section from each cable end, due
to switching and lightning over voltages.
Station B
Figure 3 Setup for reduction of grounding link boxes, by using a combination of grounding
and connection link boxes.
According to CIGRE recommendations [LECTRA 47, p75-76], the link cables between the
cable joint and link box, may not exceed 10 m. This limit is to avoid the creation of voltage
multiplication of the induced pulse voltages of the metal sheath, which can occur due to the
link cables different inductance compared to the metal sheath of the HV cable. If the length
6/7
of the link cables exceed 10 m, the limits for over voltages on the grounding system are no
longer valid, and there are thus no guidelines for how the cable jacket and the link cable
can be tested [LEKTRA 47, Taple II on P83 / IEC/EN 60 229].
When link boxes are used, their location shall follow the definition:
In urban areas, the link boxes shall be placed easily accessible in the surface or
elevated where possible, depending on the local conditions.
Outside of urban areas, the crossbonding link boxes may be buried, to avoid
interference with the farmers normal work in the field.
Grounding boxes, every third or every sixth link box, shall be located so that they
can be accessed easily. These must be accessible for fault locating activities and for
periodical jacket testing. Consideration must be given to local conditions when
selecting the location of the link boxes.
It is important that link cables are not longer than 10 m. This limit is set to avoid
the creation of voltage multiplication of the induced pulse voltages of the metal
sheath.
A link box shall be watertight, and filled with a compound that covers the link cables to seal
the cable glands and the exposed ends of the link cable. This compound may not overflow
the SVLs or coupling bars.
The link box shall include a well defined and accessible grounding point, which can be
connected to a jointing pit grounding.
6. Documentation
The size of the SVL shall be designed by the cable manufacturer. The size and background
for the minimum and maximum voltage choices shall be documented in the tender and as
built documentation.
A drawing of the link box shall be given in tender and as built documentation.
A maintenance manual shall be given, including:
Specification of all materials used for the box and its accessories.
Test reports
o Voltage
o Water tightness of link cable and link box
o Corrosion tests
o Short circuit current tests
o Mechanical strength
Safety instructions for maintenance, and replacement of the box and its
accessories, taking induced and transferred voltages into account.
Maintenance plan.
Definition of size, material, filling compound and water tightness (minimum IP68) must be
given in tender material as well as in as built documentation.
7/7