The Pamban Bridge is a railway bridge on the Palk Strait which connects the town
of Rameswaram on Pamban Island to mainland India. The bridge refers to both the road
bridge and the cantilever railway bridge, though primarily it means the latter. Opened on 24
February 1914, it was India's first sea bridge, and was the longest sea bridge in India until the
opening of the Bandra-Worli Sea Linkin 2010. The rail bridge is, for the most part, a
conventional bridge resting on concrete piers, but has a double leaf bascule section midway,
which can be raised to let ships and barges pass through.
The railway bridge is 6,776ft (2,065m) and was opened to traffic in 1914. The railroad
bridge is a still-functioning double-leaf bascule bridge section that can be raised to let ships pass
under it. Until recently, workers opened the two leaves of the bridge manually using levers.
About 10 ships cargo carriers, coast guard ships, fishing vessels and oil tankers pass under
the bridge every month. According to Dr Narayanan, the bridge is located at the worlds second
highly corrosive environment, next to Miami, the US, making the construction challenging. The
location is also cyclone-prone and a high wind velocity zone. The 90-year-old railway bridge,
one of the countrys architectural marvels that carried meter-gauge trains over the Palk Strait was
pulled down and replaced with a new broad gauge bridge. This replacement project was
completed on 12 Aug. 2007. The new bridge is also a bascule bridge, which can open up in
the middle, in order to allow ships to pass through. The replacement was for two reasons. First,
the bridge had outlived its lifespan of about 60 years. Second, the Railways were converting all
the (British built) meter gauge tracks to broad gauge. The Pamban Bridge is a part of the
Madurai-Rameshwaran gauge conversion project in Tamil Nadu. "The bridge is superior in
construction and compared to similar structures abroad (of similar vintage)," said Dr G.
Narayanan, Chief Engineer, Construction, Southern Railway. In 1963, a huge tidal wave washed
away parts of Pamban Bridge that connected Rameshwaram to mainland Tamil Nadu. The
Railway set a target of six months for the bridge to be repaired while Sreedharans boss, under
whose jurisdiction the bridge came about, reduced it to three months. Sreedharan was put incharge of the execution and he restored the bridge in just 46 days.
The railway bridge is 6,776 ft (2,065 m) long. It was opened on 24 February 1914,
construction having begun in 1911. However, plans for a bridge had been suggested from as
early as 1870 as the British Administration sought ways to increase trade with Ceylon. The
bridge has a still-functioning double-leaf bascule section that can be raised to let ships pass.
The adjacent road bridge was opened in 1988.
The railway bridge historically carried metre gauge trains, but Indian
Railways upgraded the bridge to carry broad gauge trains as part of Project, work that was
completed on 12 August 2007. Until recently, the two leaves of the bridge were opened
manually using levers by workers. Around 10 ships cargo carriers, coast guard ships,
fishing vessels and oil tankers pass through the bridge every month. More work was
carried out on the bridge in 2009 to strengthen it to enable it to carry goods trains.
After completion of the bridge, metre-gauge lines were laid from Mandapam up to
Pamban station. From here the railway line bifurcated, one line towards Rameshwaram about
6.25 miles (10.06 km) up and another branch line of 15 miles (24 km) terminating
at Dhanushkodi. The section was opened to traffic in 1914. The Ministry of Indian Railways
sanctioned Rs. 25 crore to replace the existing 65.23-meter- long rolling type span, which
opened like a pair of scissors to allow the vessels to pass the bridge with 66-meter-long single
truss span which could be opened with the press of the button.
The noted Boat Mail ran on this track between 1915 and 1964 from Madras-Egmore
up to Dhanushkodi, from where the passengers were ferried to Talaimannar in Ceylon. The
metre-gauge branch line from Pamban Junction to Dhanushkodi was abandoned after it was
destroyed by the 1964 Dhanushkodi cyclone.
The bridge was subsequently restored to working conditions under Elattuvalapil
Sreedharan in just 46 days. On 13 January 2013 the bridge suffered minor damage when a
naval barge drifted into it. The tug towing a naval barge
from Kolkata to Karwar near Mumbai ran aground hitting rocks on 10 January during bad
weather. The 220 tone barge then drifted into the bridge causing part of it to tilt slightly and
requiring repair work to the piers. In 2013 it was reported that Indian Railways had applied
to UNESCO(United Nations Educational, Scientific and Cultural Organization) for the bridge to
be made a world heritage site.
Length 2.06 KM
The Pamban Bridge has a double-leaf bascule section, that can be raised to let tall
ships pass, that is still functional even though it was constructed a century ago. The section
was implemented so that the then established ferry service would not be disrupted by erection
of piers. On average, 10 to 15 boats and ships still make use of this cantilever facility every
month.
4. IT WITHSTOOD A CYCLONE
A severe cyclonic storm tested the limits of the bridges strength in December 1964.
Although many of the metal structures, girders and concrete elements were washed away, as
well as damage to two of the supporting piers, the rolling lift centre span, designed by the
German engineer Scherzer, in 1913 stayed strong. A true testament to quality engineering that
stood tall against Natures fury. The bridge was repaired and reopened for service in 46 days.
6. SURPRISING STRENGTH
The Pamban Bridge is located at an area of immense corrosive
potential, second only to the Gulf of Mexico in the world. Even so, it has
stayed strong throughout the years, with over a century of continuous
service. In 2013, a 220 ton barge crashed into the bridge when its tugboat
ran aground, causing the piers to tilt. Damages were only minor and it was
soon repaired.