May 2008
Prepared by WG4
MAY 2008
May 2008
INDEX
Introduction
Overview
Flow Charts
1. Contract Strategy Decision
2. Inventory Checking
3. Resale / Reuse Decision
4. Define Cleanliness Standard
5. Topsides Cleaning Issues
6. Onshore Dismantle / Disposal
7. Pipeline Cleaning
8. Topsides Cleaning Techniques
9. Safety Management System
10.Safety Case Adjustments
11.Workforce Management
Appendices
Decommissioning Technology Forum (DTF) Report
Extract (Jul-06)
Session 1
Session 2
Session 3
Session 4
Session 5
May 2008
Introduction
Part of OGUK/PILOT decommissioning initiative is to actively raise awareness about
decommissioning issues; improve supply chain engagement and capture learning and
experience where available as part of continuous improvement agenda.
This document is the first in what is hopefully a series offering guidance based on
recent experience from operators, consultants and contractors on topside and pipeline
conditioning or cleaning as part of the decommissioning process. This area was
selected as several major projects have completed this activity phase.
It builds on an earlier document prepared by the Decommissioning Technology
Forum based on Ekofisk; Frigg and NW Hutton experience.
The input was gathered by five workshop sessions as below:
1.
2.
3.
4.
5.
9 May 2006
4 Oct 2007
31 Jan 2008
12 Feb 2008
27 Feb 2008
More details on participants and detail output are contained in the appendices.
The document is intended to provide guidance on some of the issues faced, options to
be considered and opportunities for improvement that could be realised. It is not
intended as a prescriptive series of requirements or a comprehensive guideline on how
to execute the activities.
To make the output accessible, usable and understandable the various areas covered
have been discretely identified in the form of simple flowcharts. These charts are not
exhaustive or necessarily complete but are intended to provide a rational flow in the
preparation process to stimulate early thought and minimise late surprises.
It is hoped that the document provides a base to expand on as further experience
materialises but any project will need to consider their own circumstances as different
execution options maybe dictated by the overarching Project Execution Strategy
rather than optimisation of a single activity.
INVENTORY
CHECKING
CONTRACT
STRATEGY
DECISION
3
RESALE
REUSE
DECISION
9
5
TOPSIDES
CLEANING
ISSUES
DEFINE
CLEANLINESS
STANDARD
SAFETY
MANAGEMENT
SYSTEM
10
6
SAFETY
CASE
ADJUSTMENTS
ONSHORE
DISMANTLE/
DISPOSAL
11
WORKFORCE
MANAGEMENT
PIPELINE
CLEANING
TOPSIDE
CLEANING
TECHNIQUES
Notes
The above tries to simplistically represent how each of the detailed flowcharts are generally
related and also highlights the key overlaps, however, in practice many other interlinks exist.
Each of the Detailed Flowcharts have identified which workshop sessions contributed to that
Specific area of the process, as indicated by workshop sessions numbers on previous page.
Session details and contributors can been found in Appendices.
1
CONTRACT STRATEGY DECISION
BLOCKERS
OPERATOR RELUCTANCE
UNPROVEN TECHNOLOGY
LIMITED OFFLOADING SITES
UNPROVEN COST
REVERSE
MODULAR
PIECE SMALL
Workshop Session 2 3 4
SINGLE LIFT
WEIGHT
UNCERTAINTY
OPPORTUNITY
THE STANDARDS FOR SHUTDOWNS & TURNAROUNDS MAY
BE EXCESSIVE FOR OFFSHORE PREPARATION NOT
SEEKING FLOW ASSURANCE, EQUIPMENT RELIABILITY &
PERFORMANCE, INSPECTIONS REQUIREMENTS
OPPORTUNITY
JUST IDENTIFYING THAT CONTAMINANT IS PRESENT MAY BE
SUFFICIENT. UNLIKELY THAT QUANTITIES WILL BE
PREDICTED WITH GREATER ACCURACY OR CLEANED
WITHOUT LEAVING TRACES
IDENTIFY
CONTAMINENTS &
MINIMISE HAZARDS
ALLOW
HOT CUTTING
OPPORTUNITY
NEED TO MAINTAIN PERSONNEL CONTINUITY BUT NEED
TRAINING IN CHANGING MINDSET OF OPERATIONS TO
DECOMMISSIONING
OPPORTUNITY
MINIMISE REQUIREMENTS FOR ACCESS CAN BE BIGGEST
OFFSHORE MANPOWER REQUIREMENT
OPPORTUNITY
IS FLUSH SUFFICIENT? WHERE IS IT OK.
OPPORTUNITY
SUPPLY CHAIN CONSOLIDATION IF OFFSHORE / ONSHORE
CLEANING / CONDITIONING IS A SINGLE SUPPLIER. THE
SELECTION OF EFFICIENCY OF LOCATION WOULD BE MORE
STRAIGHTFORWARD
REMOVE H-C
SOURCES IMPACT ON
HAZARD AND SAFETY
CASE
OPPORTUNITY
GREATER CO-OPERATION & DOCUMENT INTERFACE
BETWEEN OFFSHORE & ONSHORE EARLY IN THE PROCESS
Key
Green Opportunities
Pink Observation / Consideration
(Based on Current Experience)
Do you have an
Accurate Asset
Register ?
Yes
2
Do you know
What chemicals are
onboard
No
Develop an up to
date Register
Execute a
Chemicals
Inventory Study
No
INVENTORY CHECKING
Yes
Yes
Workshop Sessions 1 2 3
No
Execute a detailed
Inventory Study
Do you
Know if there is
LSA Scale in the
wellbores ?
Yes
Can it be re-injected
down the wells?
Or left in the well
None Present
None Present
Is there LSA
in the production
pipework ?
No
Not Sure
Execute a radiological
contamination Survey
Yes
None Present
Is there LSA
in the Production
separation Systems
?
Not Sure
Execute a radiological
contamination Survey
Update Surveys
as required or as
access improves
Yes
Naturally Occurring
Uranium
contamination has
been found in some
WI pipework
None Present
Is there Uranium
in the WI pipework
systems ?
Execute a Uranium
contamination Survey
Consolidated
Inventory Report
Yes
None Present
Not Sure
Info
Naturally Occurring
Radon is produced which
degrades via Polonium to
Lead 210
Is there
radiological
contamination of the gas
handling pipework
?
May be missed as
Pollonium not usually
checked for - check
assumptions
Not Sure
Info
Develop Waste Management Plan
Cleaning Strategy based
on inventories expected
Execute a radiological
contamination Survey
Yes
Mercury may leech into
rust scale / metal of
pipework
None Present
Is there Mercury
in the produced
gas pipework
systems ?
Not Sure
Info
Execute a mercury
contamination Survey
OPPORTUNITY
USE OPERATIONS EXPERIENCE & SHUTDOWN
RECORDS
Yes
May be missed as Mercury
not usually checked for check assumptions
OPPORTUNITY
DEVELOP IMPROVED NON INTRUSIVE MAPPING
TECHNIQUES
Yes
Is there asbestos
on the platform ?
Yes
Not Sure
Execute an Asbestos
Survey
Not Sure
Info
Execute a Paint
Type Survey
Key
Green Opportunities
Pink Observation / Consideration
(Based on Current Experience)
Info
Workshop Session 1
Can Firm dates for
supply of items for sale to
Beach be given
Reconsider Resale
Strategy
No
No
No
Yes
Internal Resources
Does
Decommissioning
Strategy Involve NUI
Operations
Is it intended to
remove items early from
facilities for Sale
Yes
Yes
Decide How to
Market Goods
External Contractors
Is
(Cost x Effort) <
Perceived
Resale Value
No
Considerable
No
Evaluate amount of
Effort required to locate
paperwork
Info
Yes
Minimal
Yes
Establish Ownership
of perceived Resale
Value and how it will
be shown on the
Bottom Line
Info
Key
Green Opportunities
Proceed with Cleaning
Process
Info
Consider Unexpected
Hazards
Yes
Info
Info
Info
Info
Info
Workshop Sessions 1 2 3 4 5
No
Yes
Develop appropriate
Draining / Venting / Cold
Phase Strategy
Select appropriate
Cleaning technologies
BE AWARE
RESIDUAL WASTE SURVEYS HAVE IDENTIFIED
MATERIALS SUCH AS.
OPPORTUNITY
INTERROGATE SHIP CLEANING EXPERTISE
RESIDUAL HYDROCARBONS
SLUDGES
LSA
RESIDUAL CHEMICALS
MERCURY
ASBESTOS
PCBs
WAXES RECHARGING UNFLOODED
SYSTEMS. - CONSIDER MONITORING OR
INERT GAS IF PRESENT
Key
Green Opportunities
Pink Observation / Consideration
(Based on Current Experience)
5
i.e. When is the work to be
carried out in relation to
Cessation of Production
Workshop Session 1
Is there a
Decommissioning
Strategy
Yes
CONSIDER
DEVELOPING / AGREEING CLEANLINESS AND
PRESSURE HANDOVER CERTIFICATE
REQUIREMENTS WITH OPERATIONS,
WHAT HAPPENS TO OPERATIONAL CONSENTS IN
NUI MODE, LENGTH OF TIME PLATFORM WILL BE
COLD i.e. MAINTENANCE OF F&G SYSTEMS,
SCE ELEMENTS, ACCOMMODATION.
No
Develop a
Decommissioning
Phasing Strategy
Will Equipment be
Sold/ReUsed
Or
Scrapped
Sale / Reuse
Scrapped
Develop Cleaning /
Preservation Strategy
on this assumption
Key
Green Opportunities
Pink Observation / Consideration
(Based on Current Experience)
Contract Strategy
Decision
Taken for Onshore / Offshore
Workscope and Re-Use
/ Disposal
6
ONSHORE DISMANTLE / DISPOSAL
Info
Workshop Sessions 3 4
CONSIDER
LONG LEAD FOR TRAILERS Vs
SCHEDULE FLEXIBILITY
Establish Weight,
Delivery Window
Custody Transfer
Info
Dismantle
Re-Use
CONSIDER
EARLY DIALOGUE WITH
REGULATOR
ACCURATE P&IDs
MAINTENANCE RECORDS
ASSIST IN PREDICTING
CONTAMINATED AREAS
CAPTURE OFFSHORE
DOCUMENTATION OF STATUS
FROM RECORDS
OFFSHORE VISIT & EARLY
LIAISON WITH OFFSHORE STAFF
Info
CONSIDER
NATURE OF COATINGS IF HOT
WORK PLANNED
ARE CDM (Construction, Design
and Management Regulations 2007)
RELEVANT
KEEP WALKWAYS / STAIRS AS
FAR AS POSSIBLE TO MAINTAIN
ONSHORE ACCESS
Recycle
Blockers
Blockers
Limited Market
Demand
Limited Specialist
Waste Routes
OPPORTUNITY
PARTNERSHIP / JV WITH OFFSHORE CLEANING
AND ONSHORE DISMANTLING
OPPORTUNITY
SPECIALIST EQUIPMENT TO IMPROVE
EFFICIENCY & SAFETY FOR PIECE SMALL
REMOVAL
OPPORTUNITY
ESTABLISH COMMON PROTOCOL AT HANDOVER
INTERFACES
OPPORTUNITY
MARKET DEMAND FOR SPECIALIST / HAZARDOUS
WASTE ROUTES
OPPORTUNITY
DISMANTLING FACILITIES CAPABLE OF
RECEIVING > 10,000t STRUCTURES
OPPORTUNITY
IF NOT ESSENTIAL LEAVE TO ONSHORE
DO NOT DUPLICATE EFFORT
Key
Green Opportunities
OPPORTUNITY
CENTRAL DATABASE FOR PLANT & EQUIPMENT
AVAILABLE FOR RE-USE
OPPORTUNITY
OFFSHORE PREPARATION SHOULD BE TERMED
CONDITIONING NOT CLEANING
7
PIPELINE CLEANING
Preparation &
Engineering Phase
Operations Input
Documentation &
History
Workshop Session 4
CONSIDER
ACCESS REQUIREMENTS OFTEN
REDUCED BY MODIFICATIONS
LAYDOWN AREA REQUIREMENTS
HISTORY OF PIGGING / STATUS OF
PIPELINE
WASTE DISPOSAL ROUTES
ESTABLISH CLEANLINESS
REQUIREMENTS
Establish
Likely Condition
Remnants Requiring
Treatment
Criteria to be met
Procedures to interface
with existing operational
practices
Execute
LEAKING VALVES
OTHER PLATFORM ACTIVITIES
IMPACT
BE AWARE OF CORROSION
PRODUCTS eg. BLACK POWDER
Dispose of Waste
OPPORTUNITY
MAKE BEST USE OF OPERATIONAL PIGGING IN
LATE LIFE STAGES
OPPORTUNITY
PIG AT EARLIEST OPPORTUNITY PRODUCTION TO
AVOID CHANGES TO REMNANTS AND REDUCED
SERVICES
Key
Green Opportunities
Pink Observation / Consideration
(Based on Current Experience)
CONSIDER
VOLUMES OF WASTE AND
IMPACT ON DISPOSAL ROUTES
CAN THEY BE ACCOMMODATED.
CLEANING LOCATION DRIVERS
SPILL RISK
HEALTH RISK HAZARD
SAFETY RISK
LIFTING UNCERTAINTIES
EFFORT
ACCESS ISSUES
USE OF OPERATIONAL
DISCHARGE CONSENTS
No
No
8
TOPSIDE CLEANING TECHNIQUES
Yes
Workshop Sessions 1 2 3 4
Info
Does each system have
an agreed cleanliness
standard
MINIMISE OCCUPATIONAL
HEALTH HAZARDS
Cleaning
Techniques
Assessment
Yes
Onshore
Info
Onshore Contractor to
advise ensure
contract reflects this.
Draining / Venting
Methodology Study
Info
Offshore
Is It appropriate to use
Operational Flushing
Techniques
Yes
Do Operational Flushing
Techniques Ensure
Complete Flushing.
If no release envisaged
consider using new /
different technologies to cut
drain holes/vents in piping to
avoid breaking flanges/
removing spools
Develop specific
Decommissioning
flushing Procedures
No
No
Selecting an inappropriate
flushing methodology may
result in increased
execution manhours and
may not attain required
cleanliness levels
Consider chemicals
& Mechanical
Techniques
Consider Waste
product Disposal
Info
Traditional workpacks
have been shown to be
unnecessarily large &
Complex for
Decommissioning works.
Ensure sequence of
cleaning systems
considers risk introduced
Consider abseiling vs
scaffolding, comparison
dependent upon draining
methodology.
(Cutting vs Valves)
No
Piece small
approach to flushing
should be avoided
as it increases
access / isolation
issues
Do Operational
Flushing Techniques
ensure complete
flushing?
No
Modify Procedures
Info
Challenge Operational
Flushing Techniques are
appropriate for
Decommissioning
Corroded Flanges /
Bolts increase
chances of hand
injuries (Flogging
spanners slipping)
Proceed with
Flushing
Yes
OPPORTUNITY
CHALLENGE EXISTING OPERATIONAL PRACTICES
TO ENSURE FIT FOR PURPOSE
Key
Green Opportunities
Pink Observation / Consideration
(Based on Current Experience)
Decision made to
Commence
Decommissioning
9
SAFETY MANAGEMENT SYSTEM
Workshop Session 1
Review Proposed
Decommissioning
Strategy
Info
Assess Operational
Work Control Systems
Vs Expected Work
Types
Assess Operational
Work Control Systems
Vs Expected Work
Types
Info
Info
During Decommissioning
there may be more
SIMOPS/Hot Work/Lifting
activites than usual during
production operations
Yes
Consider developing a
strategy to electrically
isolate as close to the
energy source as possible
(Generators, Batteries etc)
No
Key
Green Opportunities
Continue using Controls
until Milestone point is
reached
10
Decision made to
Commence
Decommissioning
Info
Workshop Session 1
Review Proposed
Decommissioning
Strategy
Info
Info
SimOps Well
P&A and
Operations
SimOps Well
P&A and HC
Freeing
Reservoir
Isolated,
Conductor
Removal,
HC Freeing
Reservoir
Isolated,
Conductor
Removed,
HC Freeing
Reservoir
Isolated,
Conductor
Removed,
HC Free
Develop Management of
Change procedure for
Safety Case transitions
Can SCEs be
reduced / deleted
Reservoir
Isolated,
Conductor
Removed,
Unattended.
Key
Green Opportunities
Pink Observation / Consideration
(Based on Current Experience)
Decision to Commence
Decommissioning Studies
Info
11
WORKFORCE MANAGEMENT
Workshop Session 1
Commence regular
communications
program
Develop the
Decommissioning
Workscope
Communications Plan
Identify
Decommissioning
Competencies needs
Develop
Decommissioning
Training Program
Liaise with
Drilling
Contractor HR
Liaise with
Brownfield
Engineering
Contractor HR
Info
Liaise with
Operator HR
Develop Skill /
Experience Retention
Plan
Ensure Decommissioning
Strategy needs are
identified for duration of the
work eg. Tartan Cables
may reduce EA Demand
Info
Info
Decommissioning Safety
Management System
No
Consider Retention
Incentives
Info
Info
Yes
Commence Re-Training of
Key Personnel for
Decommissioning Culture
Key
Green Opportunities
Develop Managaement of
Change Program to change
experienced personnel out
APPENDICES
Session 1
Decommissioning Technology Forum (DTF)
Report Extract (Jul-06)
Session 1
REVISION
Issued for Comment
Issued for Use
DATE
7th June2006
18th July 2006
ORIGINATOR
P Brindley
P Brindley
APPROVED
B Hemmings
B Hemmings
Page 3
Page 3
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
2 of 12
Company
BP
BP
BP
Shell
Shell
ConocoPhillips
Total Norge
Decommissioning Project
North West Hutton (Project Manager)
North West Hutton (Environmental)
North West Hutton (HSE)
Decommissioning Advisor
Brent Decommissioning (Projects)
Ekofisk (Projects)
Frigg
3. MINDMAP/FLOWCHARTS
A mindmap and series of flowcharts have been developed that summarise the information produced during the workshop.
Actual experience input to the flowcharts is provided by the series of pink coloured boxes. These diagrams follow:MINDMAP
The following mindmap is provided to give guidance as to the interactions between the various issues, such as equipment
resale strategy, waste disposal issues, resource constraints, demolition/removal startegies etc.
As can be seen there are numerous interactions that influence the cleaning strategy, especially when trying to define the
level of cleanliness sought. Clearly there will be trade offs between these interacting issues however there are one or two
key decisions that will provide significant guidance to the cleaning strategy.
Resale or Scrap? this decision is a prime driver on determining how to clean and what level to clean to. If the equipment is
to be scrapped then clearly it may not necessarily require a high level of cleanliness to be achieved offshore. If resale is
considered viable identify what value you want/expect to get and think about how you are going to get it. Often aspirations of
value fail to materialise (e.g. Maureen and Froy resale)
Removal Strategy If the facilities are to remain offshore in a Care and Maintenance mode for a period of time, then the
cleaning strategy has to ensure that recharge of the hazard or new hazards is not an issue (e.g. vapour build up from
degrading hydrocarbons, mercury sweating etc.). If the facilities are to be removed to shore within a short time frame then
the opportunity exists to reduce the level of cleaning to the minimum, and perform more cleaning onshore although onshopre
waste disposal may then become an issue/concern.
Waste Disposal Routes (Onshore) the lack of acceptable disposal routes (e.g. LSA disposal capacity shortfalls) may
dictate the cleaning strategy to be adopted. Consider carefully the use/release of existing offshore operational discharge
consents. Develop a strategy that provides the best value in terms of the offshore vs onshore disposal of wastes. This
strategy should consider the cost and spaces issues of cleaning offshore or onshore. Remember that a duty of care may
exist from cradle to grave for all wastes.
Onshore Dismantle/Disposal - Decide early what the drivers are (HSE/Cost/Schedule etc.) and decide how to influence
these activities to get best value.
Overarching all of the above is Risk Management the cleaning strategy, especially draining and venting issues, can
introduce significant offshore works that raise risk levels. There clearly is a need to balance risks between level of cleaning
activities, perceived value of equipment, and location of cleaning activities.
3 of 12
Name
Company
Phone
Name
Company
Phone
Session 2
Offshore Workshop Notes / Participants (Oct-07)
Access/Support
o The cleaning aspect is relatively small compared to all the preparation required.
This is particularly evident in terms of scaffolding required for access.
o Offshore surveys are critical to ensure planning can be efficient.
o Are there different access techniques? Scaffolding is labour intensive and slow.
o Cranes play an important role. Often required to be refurbished. Decks may not
be designed to take the loads for alternative cranes.
o Laydown areas are critical in the planning.
Key Opportunities
Create a Guideline on Cleaning
o No plans at present but can be added to the list of possible future guidelines?
o Standards of Cleanliness
What do we do offshore
What can we do onshore
Quantification of disposal quantities and keeping records is a key part of the workflow
from offshore to onshore.
Downhole disposal.
o
LSA Management
o Still the major uncertainty in cleaning estimates where present.
o Regulation
o (Check with environmental committee)
o Managing LSA Scale
Disposal Routes for LSA
Onshore Disposal
o Yard availability and capability
o Types of access
Vessel draft
o LSA handling
Pipeline Cleaning
Removal
o If we use Single Lift then what are the implications for disposal
o How do we handle the facility near shore to onshore
Tank Cleaning
o Hydrocarbon Storage Tanks
o Engage regulators
Health Issues
o New guidelines coming out next year?
Timing of Removals
o This is still an issue not resolved but we need to keep an eye on this one.
o There have to be upcoming opportunities on cooperation
Session 3
Onshore Workshop Notes/ Participants (Jan-08)
Answers
Deliver as Big as possible, avoid piece small
Engineering details a critical must
Detailed client documentation.
Reuse potential, minimise offshore dismantling. Linked to documentation.
Detailed waste inventory required
Good onshore/offshore interface.
Pro-active agency management
TFS not a show stopper
Less work offshore achieves more efficiency onshore, ALARP
Resource utilisation, balanced schedule to maximise safety and efficiency
2,200 employees
Revenue $1billion.
ISO 9001 approved
ISO14001 certified
Onshore disposal services at AF Vats
LSA Scanner
Contracting Strategy
Risk Management and Mitigation
Hazardous Waste. Transhipment issues
Use of CDM regulations and interpretation thereof.
Session 4
Npf Break Out session Notes
Cleaning Guidelines
There is a need for some cleaning guidelines
o These will give guidance on what to consider
o Key to cleaning is to understand the deconstruction
method
Are you Cleaning only to make hotwork safe?
Are you cleaning for Safety at Lift separation
no free hydrocarbons
o Only do it once flow of data offshore to on; create
database, define handover documents
o How clean is clean provide guidance for different
stages incl transportation
o Standards for cleaning why needed and how much
acceptable
o Link onshore and offshore cleaning activities
o Perhaps the DTF Guidelines could be expanded for
this purpose?
Technology
Can we improve cleaning products?
o Is there value in investing in new or improved
cleaning products?
Scale
NORM (LSA Scale) onshore or offshore?
o General consensus is that the cleaning work should
be done onshore
o However the product should be injected into the
wells offshore as potentially the best environmental
option.
New Techniques?
Injection into reservoir
o Ideally injection of contents of facilities, cleaning
products and scale?
o Time
IS
an
issue
injection
potential/
knowledge/documentation. Need to know in early
planning whether to have wells available for this
purpose.
Other Opportunities
Contracting Strategy
o There is some value in ensuring that the onshore
dismantling contractors are involved in the offshore
cleaning somehow.
o Are there different ways of organising the
contracting arrangements to ensure these potential
efficiencies actually happen?
Deal with trans boundary issues early
o This is to ensure that any approvals are started
early enough to ensure they do not become the
critical path.
Standards for grillage if spillage
o This is a detail where we need to consider
standards for grillage to ensure we do not have
Session 5
Pipeline Workshop Notes (Feb-08)
Major Challenges
o Access. This is an issue due to limited space on many facilities. Access may have
been reduced through later platform modifications.
o Key Issues at Engineering Phase
Status of pipelines
Historical data
Access to temporary pipe work
o Lay-down areas. As above these are important for cleaning operations.
o Waste disposal. Products generated from the cleaning have to be disposed off and a
viable, environmentally acceptable route must be established.
o Communications and Modifications. Need to have more discussion with the host
Operations group.
o Pig at the earliest opportunity. If your sole objective is cleaning then performing the
job as early as possible is preferable.
o Passing valves. This is a risk which can add a significant cost to rectify.
o Cleanliness standards, how clean is clean. What objective are we working to?
o Confirmation of cleanliness being achieved. How do we know when we have done
enough.
Discussion Session
Note some of these discussions occurred during each presentation and
have been rolled into this section.
The key issue remains how much cleaning do we need to perform for decommissioning
purposes.
o Pipelines need to be flushed to 30ppm
o Is this a valid assumption?
o How clean is clean?
o Is there a need for a guideline?
Waste Management
o Waste routes on and offshore.
Questionable whether we have got the best routes for this.
o Issue of removing/cleaning mercury contamination from pipeline.
o We can re-inject scale into well formation providing the scale remains offshore and is
directly connected through intra field lines.
o If chemical solutions are brought on shore, it is possible to concentrate the solution
and make blocks of concrete (to minimise leaching)
o LSA Scale will always need to be dealt with, in solution or as a solid.
o Disposal of corrosion products such as black powder.