Handil Field: Three Years of Lean Gas Injection Into Waterflooded Reservoirs
Sugianto Gunawan, Total Indonsie; Didier Cai, SPE, Total Indonsie
Abstract
The giant Handil field comprises of more than 500
hydrocarbon accumulations, in structurally stacked and
compartmentalized fluvio-deltaic sands.
Most of the accumulations consist of a large column of
saturated oil underlying a gas-cap, trapped in reservoirs with
good rock properties, and have been produced by water
injection or strong natural water drive.
In 1995 five reservoirs, representing nearly 1/5 of the fields
total OOIP and which had reached their final stage of
waterflood development 58% of the total oil in place had
already been produced were submitted to a further
development with lean gas injection to increase the ultimate
oil recovery.
To date, after 3 years of gas injection, the recovery factor for
these 5 reservoirs has increased by 1.2% of the oil initially in
place and the project is considered both a technical and an
economical success.
The predominant drive mechanism with lean gas injection
have been confirmed by field data. The previous decline of oil
productionhas been stopped and the oil rate is now stabilizing.
The main monitoring challenge has been the control of gas
cycling for most of the producers, particularly during periods
of higher injection rates to compensate low injection periods
imposed by gas availability.
The very close monitoring of the wells and reservoirs
performance, the numerical simulation and material balance
studies, have helped to better understand the mechanisms
involved and have to led a revised and more efficient policy to
maximize oil production.
The experience gained and the analysis of this 3-year old
project gives the confidence to pursue the extension of the lean
gas injection development to others reservoirs of Handil field.
Introduction
Handil is a giant oil field located in the Mahakam Delta of the
island of Borneo, Indonesia (Fig. 1)
The structure of the field is a simple anticline, 4 km long
and 3 km wide, with a main east-west fault dividing a North
and a South areas (Fig. 2).
The geology is complex, the field comprises more than 500
hydrocarbon accumulations, stacked between 300 m to 4000 m
subsea, trapped in channel-sand and sand-bar reservoirs
deposited in a fluvio-deltaic environment of Miocene age (Fig.
2).
Vertically, the field has been sub-divided in a Shallow
Zone, grouping the accumulations from 300 to 1500 mSS. A
main Zone between 1500 and 3000 mSS. And a Deep Zone
with the accumulations below 3000 mSS. Around 300 oil
accumulations are found in the shallow and Main Zones, while
the 200 gas accumulations lie mostly in the Deep Zone.
The reservoirs are of excellent characteristics, with
permeabilities ranging from 10 to 2000 mD, porosities in the
vicinities of 25% and the connate water saturations around
22%. Within a given reservoir, the vertical permeability is of
the same order as the horizontal permeability.
Most of the oil accumulations consist of a large column
typically well in excess of 100 metre of saturated oil
underlying a gas-cap, the relative size of which is very
variable. The structural dip ranges from 5o to 12o , down to the
aquifers generally connected in the western and eastern
sectors. The aquifers are generally very strong in the Shallow
Zone, and rather weak in the Main and Deep Zones.
The initial pressure regime is hydrostatic, while the
temperature gradient is 0.03 oC/metre. The oil density varies
between 31o and 34o API from the Shallow to the main Zone.
Oil formation volume factor is 1.1 to 1.4 v/v, dissolved gas to
oil ratio is 50 to 100 v/v, oil viscosity 0.6 to 1.0 cp, and the gas
formation volume factor range from 5.E-3 to 10.E-3 v res/v
surface.
Production history
Oil production started in 1975 under natural depletion drive.
Shortly after the accumulations of the main Zone, which
benefited of a weak aquifer at best, were submitted to a
development by peripheric water injection.
Water injection has eventually become the depletion drive
mechanism for the equivalent of 65% of the fields OOIP.
3.
4.
SPE 57289
Initial project
Five reservoirs of the Handil field, representing a combined
303 Mmstbo, were selected for the initial phase of the project.
These reservoirs have porosity between 17 % to 25 %, connate
water saturation from 15 to 19 %, permeabilities between 100
md to 2000 md, and initial oil columns from 120 m to 185 m.
(Tab. 1)
SPE 57289
HANDIL FIELD: THREE YEARS OF LEAN GAS INJECTION INTO WATERFLOODED RESERVOIRS
SPE 57289
SPE 57289
HANDIL FIELD: THREE YEARS OF LEAN GAS INJECTION INTO WATERFLOODED RESERVOIRS
Project economics
Investment costs were limited to 18 M$ for the compressor
and its utilities and 5 M$ for the newly drilled gas injector
wells, the project will have no problem in yielding a
competitive rate of return.
With 1.6 Mmstbo of additional oil produced during the
first 3 years, the gas injection project has already yielded some
24 M$ (assuming 15 $/bbl).
The injected gas is considered free as it will all be reproduced during a 2 to 3 year blow-down period at the end of
the project. It is only stored while the gas sales are met by
other sources of gas.
There is however a cost linked to the accelerated
development drilling of nearby gas fields. This acceleration is
required to ensure the necessary production potential, since the
injection of the gas into the oil reservoirs mobilizes 67
MMscfd on average of the available total capacity. This cost
has been estimated at 5 M$ over the life of the project.
Project extension
At the feasibility stage of the project up to 30 reservoirs had
been identified as possible candidates for the gas injection.
The initial project was limited to the 5 most promising, mostly
for reasons related to the availability of the injection gas.
In light of the results obtained so far and of the improved
understanding and know-how gained during the first three
years, it has been decided to extent the current project to a
second phase. Taking advantage of the installed injection
capacity of 90 MMscfd and with now less constraints on gas
availability, 6 more reservoirs will be involved that represent a
combined 167 Mmstbo of OOIP. The extension phase calls
only for the drilling of a new gas well and some flow-line
work for injection of about 22 MMscfd in the 6 reservoirs.
This means that eventually 470 Mmstbo of the Handil field
OOIP, previously produced by water injection, will be
submitted to an innovative EOR development that has now
successfully proven its potential at the field scale.
Conclusion
Crestal injection of lean hydrocarbon gas into waterflooded,
light oil, reservoirs is a new EOR technique in the Asia-Pacific
region.
The first three years of its application on the Handil field
have proven that it can yield additional reserves from
reservoirs otherwise at near abandon, and in economical
conditions.
The response to the mechanisms described by the
fundamental studies carried out before start-up have been
confirmed and observed on the field.
The merits of the production philosophy derived from
numerical simulations have essentially bee confirmed, while
some amendments have been made to take into account the
specificities of the reservoirs involved and the constraints born
from the operational environment, in particular the irregular
availability of the injection gas.
Res.
OOIP
A
B
C
D
E
MMbbls
24.6
110.9
36.8
29.2
101.6
TOTAL
303.0
Por.
%
22
22
25
22
22
Sw
%
19
20
15
17
15
no.
Well Nam e
1
HJ424 SS
2 HSA222 SS
3
HD414 LS
4
H316 SS
5
HF530 LS
6
HJ520 SS
7
HS323 LS
8
HA327 LS
9
HS323 SS
10 HSA431 LS
Total
Reservoir
A
B
B
B
A
B
C
D
A
C
Duration, from
Duration, from
gas injection
gas breakthrough
start-up to gas
to oil rate
breakthrough,
increased,
month
15
12
5
5
6
19
10
21
13
8
After
Oil Gain
month
bopd
bopd
bopd
23
26
28
33
31
17
28
14
22
28
44
83
4
109
57
178
59
0
72
92
214
562
712
366
168
311
240
148
227
133
170
479
708
257
111
133
181
148
155
41
698
3081
2383
HANDIL FIELD
SSW - NNE STRUCTURAL CROSS SECTION
500
1000
1500
2000
2. WATER
2500
3000
3500
GAS
250 m
OIL
500 m
WATER
1400
1200
1000
Qo total field
150
GOR
800
BSW
100
Qo from reservoir
developed by water
injection
50
600
400
200
98
99
96
97
94
95
92
93
90
91
87
88
89
85
86
83
84
81
82
79
80
0
77
78
GOR (v/v)
200
75
76
250
figure 5 : Vertical cross section of the reservoirs under lean gas injection
5000
4000
3000
2000
1000
Date
actual
base line
9811
9809
9807
9805
9803
9801
9711
9709
9707
9705
9703
9701
9611
9609
9607
9605
9603
9601
9511
9509
9507
9505
9503
9501
9411
9409
9407
9405
9403
0
9401
6000
Date
BSW, %
Oct-98
Sep-98
Aug-98
Jul-98
Jun-98
May-98
Apr-98
Mar-98
Jan-98
Feb-98
Dec-97
Nov-97
Oct-97
Sep-97
Aug-97
Jun-97
Jul-97
May-97
Apr-97
Feb-97
Mar-97
Jan-97
Dec-96
100
Nov-96
100
800
95
700
90
600
85
500
80
400
75
300
70
65
60
0
55
BSW (%)
900
ingtion
perfora
Lower
200
Sep-96
Oct-96
Aug-96
Jul-96
Jun-96
May-96
Apr-96
Feb-96
Mar-96
Jan-96
Nov-95
Dec-95
Oct-95
Sep-95
Production history
well : HD414 LS
reservoir B
Date
Sep-98
Jul-98
May-98
Mar-98
Jan-98
Nov-97
Sep-97
Jul-97
May-97
Mar-97
Jan-97
Nov-96
Sep-96
Jul-96
May-96
Mar-96
Jan-96
Nov-95
90
80
70
60
50
40
30
20
10
1.4
1.2
1
0.8
0.6
0.4
0.2
Date
monthly cycling
cumulative cycling
9812
9811
9810
9809
9808
9807
9806
9805
9804
9803
9802
9801
9712
9711
9710
9709
9708
9707
9706
9705
9704
9703
9702
9701
9612
9611
9610
9609
9608
9607
9606
9605
9604
9603
9602
9601
9512
0
9511
Ratio (Qgas
produced/Qgasinjected)
1.6
EOR RESERVOIR B
status before gas injection started up
Isopach map
with 5 m interval
0
10
Ini
tia
lO
W
C
10
5
5
15
0
10
C
O
lG
a
iti
In
HSA326 GI
Gas zone
0
0
EOR RESERVOIR B
status after 3 years of gas injection
Isopach map
with 5 m interval
0
10
Ini
tia
lO
W
C
10
5
5
15
0
10
C
O
lG
a
iti
In
HSA326 GI
Gas zone
0
0