Project
Management
Activity
Coaching center
management
Organization Authority:
Project Members:
Name: 1. Abhishek Bakshi (Rno. 6)
Sign :
___________
INDEX
SR.NO
CONTENTS
PAGE NUMBER
About Organization
Scope
Estimation : Time
Estimation : Cost
Risk Management
11
15
Questionnaire
17
SCOPE MANAGEMENT
Project stackholders:
Project stakeholder is nothing but all
people related to project. It contains the following
people:
Project sponsor: In this report the owner
is project sponsor. Example the owner is
anita Sharma.
Project manager: it can be head of staff,
or he works with the project sponsor.
Example the project manager is sanjana
Sharma.
Staff team: it contains all teaching , nonteaching staff. In non-teaching staff it
contains the electricians, hardware
repairing person.
List of staff as:
Staff type
teachers
teachers
teachers
teachers
teacher assistants
project coordinator
Hardware supporter
Name
suraj
suman
reeta
geeta
shital
Jayprakash
Ranveer
B.C.A
Subject
Math
Computer(c,ds,java,c++,rdms
Statistic
Electronics
Computer(java, dot net,c++
Business communication
Business mathematics
Programming in visual basic
Software testing
concept
1.analysis/coll
ecting a rough
data like cost,
place, time
table.
Close-out
Development
Implementatio
1.making a
project
management
plan.
1.actually
started with
teaching the
subjects
2.desiding a
place.
2.making the
proper of time
table
3.make the
time table for
courses.
3.if not
completed with
syllabus
conduct extra
1.all syllabus
completed
successfully
2.take
feedback from
the student
TIME MANAGEMENT
RISK MANAGEMENT
ABOUT RISK AND RISK MANAGEMENT:
What is Risk?
A probability or threat of damage, injury, liability, loss, or any other
negative occurrence
that is caused by
external or
internal vulnerabilitites, and that may be avoided through
preemptive action.
Risks associated with our event and the measure to handle them:
1. Injuries: one of risk in coaching center is, if any one injured
or some kinds major accident like fire, car accident has occurs.
2. Ragging: ragging is also one of major risk. Ragging in the
sense any one student is hurt by any other student physically or
mentally.
ESTIMATION: COST
A cost estimate is the approximation of the cost of a program,
project, or operation. The cost estimate is the product of the cost
estimating process. The cost estimate has a single total value and
may have identifiable component values.
FIXED COST
10,000 Rs.
estimated cost
Suraj
= 5,000
Suman
5,000
Reeta
5,000
Geeta
5,000
Shital
3,000
Jayprakash
= 3,500
Ranveer
= 3,000
Total cost=5,000+5,000+5,000+5,000+3000+3500+3000
=29500 Rs.
4.Cost classes:
This the cost for room where the class is going to be conducted this
is also in monthly bases.
No of rooms
4
estimated cost
=
4,0000 Rs.
CHANGEABLE COST
1. electricity cost:
The cost for electricity used in classes on per unit bases .
For a electricity ,the estimate cost is as followes:
Electricity used
For 20kw to 40kw
estimated cost
= 190 Rs
estimated cost
=
20*40=800 Rs
estimated cost
Markers
100
Board
900
Chair
= 15000
Table
= 1000
Total cost=100+900+15000+1000
=17000
Hence the cost estimate for this organization is approx Rs. 97540 Rs.
The people involved in our Human Resource team for organizing this
trip are:
1. Manager: The manager is responsible for organizing and
managing the classes. He is also responsible for allotting
staff who will be teaching which subject to which class .
2. Staff: The staff is responsible for managing the students in
different batches. Each staff is allotted 30 students to
conduct a lecture. There is a 1CR allotted who is a student
himself/herself for each batch from amongst the group.
3. Teacher assistant: The teacher assistant is the one who will
assist the staff allotted for each group and keep a track of
the activities and whereabouts of the students.
4. Hardware supporter: The hardware supporter is need if
there is any hardware failure occurs then it needs to
managed.
5. Project coordinator : the project coordinator is the one
which help in any software related problems.
QUESTIONNAIRE
Did you visit the place where classes are arranged before
arranging the coaching classes?
How many students were admitted in organization?
How many staffs were appointed?
How did you make batches and manage students?
How was the medical assistance taken care of in case of
emergencies?
Which all courses available in arganization.?
What does the fee for different courses?
Is extra classes are arranged during exam times?
What instructions were given to the staff and teachers before the
course started?
What is your classes timings?
Did the time initially planned for the coaching class will extend?
What were the different costs involved in the coaching classes?
Were there any additional expenses?
How were the parents of students informed and assured about the
safety of their wards during the entire classes?
Did the students enjoy the coaching classes and was the class
worthwhile?
Are you going to adjust the time for student?