For
Alfanar Labor Camp Project
Al Kharj Road Riyadh
APD70
Presented to
ALFANAR Co.
September 2012
APD70
Table of contents
INTRODUCTION.............................................................................................................15
EMS Comments and Recommendations.................................................................................. 16
1.0
Electrical Systems.................................................................................................17
1.1
Electrical Codes......................................................................................................17
1.2 Connected Load.......................................................................................................17
1.3 Labor Type 1 & 2 / Technician Type 1 & 2 Lighting .............................................18
1.4 Rest House lighting .................................................................................................20
1.5 Recreation lighting ..................................................................................................21
1.6 Restaurant/Guard House/Visitor Lounge Lighting .................................................21
1.7 Additional points on Lighting ..................................................................................22
1.8 LV Panel Construction ............................................................................................23
1.9 Capacitor Banks.......................................................................................................23
1.10
Metering & Energy Management ........................................................................24
2.0 Mechanical Systems...................................................................................................24
2.1
Mechanical Codes ..................................................................................................24
2.2 Air-Conditioning System.............................................................................................24
2.2.1 Designer Calculations...............................................................................................24
2.2.1 Suggested Cooling Load Calculations......................................................................26
2.2.1.1 Recommended Cooling Load Calculations Based on ASHRAE ..........................26
2.2.1.2 Based on Evaporative Cooling Design Guidelines Manual. .................................28
2.3 Supply Duct Sizing......................................................................................................30
2.4 Exhaust Air System. ....................................................................................................31
2.5 Steam System. .............................................................................................................31
2.5.1 Steam Boiler Sizing..................................................................................................31
2.5.2 Steam Network. ........................................................................................................31
2.6 Compressed Air System ..............................................................................................32
2.6.1 Air Compressor Sizing. ............................................................................................32
2.6.2 Compressed Air Network. ........................................................................................32
3.0 Plumbing System .......................................................................................................33
3.1 Tanks Capacity ...........................................................................................................33
3.1.1 Potable Water Storage Tank Capacity......................................................................33
3.1.2 Grey Water Collection Tank Capacity.................................................................33
3.1.2 Treated Grey Water Storage Tank Capacity ............................................................34
3.1.3 Soft Water Tank Capacity ........................................................................................35
3.1.4 Septic Tanks Capacity ..............................................................................................35
3.1.5 Fire Fighting Water and Pump. ................................................................................35
3.1.6 Electric Water Heaters..............................................................................................35
3.1.7 Solar Water Heaters..................................................................................................36
4.0 The Feasibility of Introducing Renewable Energy Solutions ...............................36
4.1 Solar Water Heating ...................................................................................................38
Energy Management Services Int.
Page 2 of 45
APD70
Page 3 of 45
APD70
The below table show Dar Engineering comments on EMS final report and EMS clarifications and
reply to Dar Engineering comments.
Please consider this complete document as the final report of EPD 70 as it includes EMS
recommendations on preliminary design drawings; designer comments on EMS recommendations
and EMS justifications, comments and reply on the designer comments and final design drawings
and tender documents.
Point
No
1.0
1.2
1.2.1
1.2.2
Comments
ELECTRICAL SYSTEMS
The following observations
are noted in the review of
available information on
lighting layouts and power
layouts of Labor Type 1(LT1),
Technician Type1 (TT1) and
Technician Type2 (TT2)
blocks;
The lights point of 2x26W
CFL down lights has been
reduced to 18W CFL down
lights keeping the number of
light points same. This will
effectively reduce the
lighting power density.
DAR Technical
Clarification
EMS
Justifications/Reply
Noted
Noted
Noted.
EMS comment is related to
the number of socket points
and not on the load
calculation.
Page 4 of 45
APD70
1.3.1
1.3.2
1.3.3
recommended to provide
one single socket per bed
with a minimum of two
sockets per bedroom. This
will reduce the socket
density by over 50%.
It is recommended to revisit
the number/type of sockets
considered in the bedrooms
in line with the design
occupancy and bedroom
layouts.
EMS recommendation was
not implemented in the
detail design.
T5 fluorescent with sensors
has been considered for
most hallways except that
the wattage shown in light
fixture schedule is 4x4 Watts
and conventional control
gear. The wattage should be
4x14W and with electronic
control gear.
Rooms
Refer to sec.1.2 above
Common Toilets
The common toilets of LT1
are provided with 2x26W
compact fluorescent down
light for the general areas
and
WC areas. The mirror lighting
is with 1x26W compact
fluorescent wall mount globe
light. Occupancy sensors
control the lighting in LT1
only.
The WC areas to have either
1x26W or 2x13W compact
fluorescent down light in
Already complied.
Refer to drawing NO. E002,
Legend, General notes & List
of
abbreviations dated
September, 2012
Noted.
Noted
Noted in the Sep12
drawings issue.
Page 5 of 45
APD70
1.4
1.4.1
1.4.2
1.5
1.5.1
Gym/Tennis/Library/Prayer
Hall areas are not designed
with 4x26W
T5 Fixture instead these are
designed with 3x35W T5 For
Gym/Tennis/Prayer Hall &
2x35W for Library.
Toilets are designed with
1x32W CFL and not with
2x26W. Refer
Page 6 of 45
APD70
1.5.3
1.5.4
1.5.5
Page 7 of 45
APD70
1.6
1.6.1
1.6.2
abbreviations
Page 8 of 45
APD70
with
4x4W T5 which should be
4x14WT5.
1.6.3
1.6.4
1.7
1.8
Noted.
It is clear in our
specifications. We are using
NFPA system for our
Panel boards and not IEC
system using Forms for
Noted.
Page 9 of 45
APD70
of Form 2 construction.
The form and type of panel
construction in not clear
from the specifications.
1.9
2.0
2.2.1
protection. Please
refer to our LV Switchgear
specifications. Form4, Type
LV panels
and Form2 are expensive
due to additional materials
required
inside the panel boards or
SMDB
Capacitor Banks
The size of the capacitor
The three transformers
bank is calculated as per the
(MDBs) are provided with
code, taking
into consideration the
450
various loads connected to
KVAR, 450 KVAR and 500
each transformer
KVAR power factor
and to achieve target power
correction capacitor banks
factor of 0.93.
respectively. Since the
demand load on
The proposed initial power
this transformers is less than factor differs according to
the load type.
1000 kW, and considering
the system load power factor The capacitor bank is steps
will be >0.85, the to achieve detuned type, and the
a target power factor of 0.93, controller will add
the Capacitor banks required the required value according
to the actual load power
is around 225 KVAR. A 330
factor.
KVAR will maintain a power
factor > 0.95. It is suggested
to Optimize the capacitor
bank size accordingly.
MECHANICAL SYSTEMS
The designer considered a
According to Alfanar
unified factor of 1000 Btu/
management requirements
m2
and site survey for the
for sizing the different
existing Labor camp the new
evaporative cooling units
HVAC design Matching with
without
the existing Camp and as per
any consideration to the
ASHRAE code the
different application as
evaporating
following:
Cooling depend on zone
Also the designer provided
area, and the application
another calculation sheet
type not effect here,
APD70
based
on ASHRAE 2007 handbook
shows that the CFM/m2 is a
bout 94 which is almost the
same result that has been
gotten form the first
assumption.
2.2.1.1 using the Hourly Analysis
Program (HAP 3.34) that was
developed by Carrier; EMS
conducted a detailed load
calculations for the Library
and the Internet hall .
- As mentioned above
ASHRAE handbook 2007
mentioned at 51.9 that
coolers capacity might be
determined from standard
heat gain calculations.
The evaporation process
will act as the cooling coil to
remove the sensible heat
from the space.
Page 11 of 45
APD70
75.05
Air Flow= Sensible heat load
/ (1.08 * (84.5 75.05) CFM
= 22,900 CFM
The designer calculations for
the same area show that the
required air flow of the
evaporative cooling unit is
29,500 CFM..
CFM / m2 = 22,900/364.7 =
62.8
From the above; it is clear
that the CFM requirements
based on actual cooling load
calculations are 36 % less
than
that considered by the
designer
2.2.1.1 In detailed calculations of
heat load are not
economically
justified; one method of
several estimates gives
satisfactory results. In this
method, the difference
between
dry bulb design temperature
and coincident wetbulb
temperature multiplied by
10 is equal to the number of
seconds needed for each air
change.
Applying this on the same
Library and Internet hall:
2.3
the main duct sizing based
on the designer calculations
for
the library and Internet hall
(29,500 CFM) is (1900 * 750
mm) and the air velocity is
12.3 m/sec; while the main
Page 12 of 45
APD70
2.5
2.5.2
(A)
2.5.2
(B)
duct
sizing based on the
suggested air flow (22,900
CFM) will be
(1500 * 750 mm) with air
velocity of 9.6 m/sec.
EMS recommends the
designer revisiting the duct
sizing
area to recalculate the duct
dimensions for each area
based on the new
evaporative coolers adjusted
air flow.
STEAM SYSTEM
EMS desagrees with pipe
sizing as it was considered
based on pressure drop of
150
Pa/m; while ASHRAE
Fundamentals handbook
recommends a pressure drop
of 450 to1100 Pa/m for such
boiler pressure, applying
this; then the main pipe
diameter from the boiler
should be
maximum 40 mm instead of
50 mm
the steam boiler which is
considered as correct action;
but the layouts didnt show
any collections for the
condensate
return line from the main
steam line or from the steam
end users to the tank, taking
into consideration that this
condensate water is 100%
pure hot water; collecting it
and returning it to the feed
Ashrea
recommendation to prevent
the noise , but in Residential
buildings
( LT1,LT2) there are some
HVAC risers has high velocity
because
available Architecture shaft
in the building not sufficient
for
HVAC work, this assumption
regarding to Alfanar
management agreement.
Un Scientific and
unconvinced justification.
Page 13 of 45
APD70
2.6
2.6.1
3.0
3.1.7
noted
Page 14 of 45
APD70
INTRODUCTION
Page 15 of 45
APD70
Page 16 of 45
APD70
1.0
Electrical Systems
1.1
Electrical Codes
Preliminary Recommendation
The Designer has referenced electrical/lighting codes and standards, such as IESNA, NEC
and Saudi Arabian Std. Organization.
The following are some of the additional standards/codes that are recommended to be
referenced;
ASHRAE 90.1
The major areas of the building are addressed in this section as to the specific standards
requirement, Consultants design considerations and EMS comments/recommended
technologies and control strategies;
Detail Phase Comment
The above standards are preferred to be referenced in the specification document.
1.2
Connected Load
The following observations are noted in the review of available information on lighting layouts
and power layouts of Labor Type 1(LT1), Technician Type1 (TT1) and Technician Type2 (TT2)
blocks;
1. Lighting densities
Preliminary Recommendation
Page 17 of 45
APD70
The lighting points of 2x26W compact fluorescent downlights provided in rooms results
in lighting density of approx 10 watts/sqm. Each typical room is provided with 4
downlights in the bedroom.
It is recommended to reduce the number of light point in the bedroom from 4Nos. to
2Nos for LT1 and the same for TT1 & TT2 but with addition of 1No. Downlight in the
entrance area. This will reduce the number of fixtures and hence the connected load.
Detail Phase Comment
The light points of 2x26W CFL downlights has been reduced to 18W CFL downlights
keeping the number of light points same. This will effectively reduce the lighting power
density.
2. Power density
Preliminary Recommendation
There are 4 Nos of twin sockets provided for each bedroom. This results in a socket density of 78
Watts (VA)/m2. Considering that the rooms are provided with multiple beds, it is recommended
to provide one single socket per bed with a minimum of two sockets per bedroom. This will reduce
the socket density by over 50%.
It is recommended to re-visit the number/type of sockets considered in the bedrooms in line with
the design occupancy and bedroom layouts.
Detail Phase Comment
EMS recommendation was not implemented in the detail design.
1.3
The current lighting for the areas within the accommodation blocks is as follows;
1. Hallways
Page 18 of 45
APD70
Preliminary Recommendation
The lighting provided is of 4 ft. linear fittings spaced approx 5m apart. The specifications
of the fixtures are not available. While LT1 hallway lighting is provided with occupancy
sensors, no sensors are shown in the TT1, and TT2.
The following strategies are recommended for all hallways;
T5 fluorescent with sensors has been considered for most hallways except that the
wattage shown in light fixture schedule is 4x4 Watts and conventional control gear. The
wattage should be 4x14W and with electronic control gear.
2. Rooms
Preliminary Recommendation
Refer to section 1.2 above
Detail Phase Comment
Refer to section 1.2 above.
3. Common Toilets
Preliminary Recommendation
The common toilets of LT1 are provided with 2x26W compact fluorescent downlight for
the general areas and WC areas. The mirror lighting is with 1x26W compact fluorescent
wall mount globe light. Occupancy sensors control the lighting in LT1 only.
The following is recommended for toilets;
Page 19 of 45
APD70
1.4
Preliminary Recommendation
Since lighting is not designed yet for the Rest house, the following design considerations are
recommended for the various areas within the Rest house;
Page 20 of 45
APD70
1.5
Recreation lighting
Preliminary Recommendation
The Gym/Tennis/Library/Prayer Hall areas of the Recreation building is designed with
4x26W T5 fixtures with a power density of 5.8W/m2, which seems to be optimum. The
toilets are with 2x26W compact fluorescent downlights.
The following are the recommendations;
Consider sensors and/or time schedule for all above mentioned areas within the
recreation building including the lockers, toilets and stairs.
The WC areas to have either 1x26W or 2x13W compact fluorescent downlight in place
of the current 2x26W
The artificial lighting in sports areas like the gym, table tennis and waiting areas could be
complemented with day lighting elements such as sun pipes/skylights. This will not only
yield lighting savings during daytime but also improve the indoor ambience.
1.6
Preliminary Recommendation
Since lighting is not designed yet for the Restaurant/Guard House/Visitor Lounge, the
following design considerations are recommended;
Page 21 of 45
APD70
Security Area T5
1.7
Preliminary Recommendation
All non-emergency interior lighting has to be automatically controlled to turn off during
non-operational hours.
Page 22 of 45
APD70
1.8
LV Panel Construction
Preliminary Recommendation
All main LV Panels are recommended to be of Form 4, Type2 while SMDBs could be of Form
2 construction.
Detail Phase Comment.
The form and type of panel construction in not clear from the specifications.
1.9
Capacitor Banks
Preliminary Recommendation
Capacitor banks to be sized to meet the power factor requirement of the Saudi code.
However, it is recommended not to consider a low value for the initial (reference) power
factor in the capacitor bank sizing calculations to avoid oversized capacitor banks.
Detail Phase Comment
The three transformers (MDBs) are provided with 450 KVAR, 450 KVAR and 500 KVAR
power factor correction capacitor banks respectively. Since the demand load on this
transformers is less than 1000 kW, and considering the system load power factor will be
>0.85, the to achieve a target power factor of 0.93, the Capacitor banks required is around
225 KVAR. A 330 KVAR will maintain a power factor > 0.95. It is suggested to optimize the
capacitor bank size accordingly.
Page 23 of 45
APD70
Mechanical Codes
The following are some of the standards that are recommended to be referenced for the
HVAC designs;
ASHRAE 62.1
ASHRAE 90.1
Page 24 of 45
APD70
Area (m )
2
One Room
Recreation Building
Restaurant
17
2190
2090
1,000
17,000
1,666
1,000
2,190,000
214,580
1,000
2,090,000
204,782
98
98
98
Also the designer provided another calculation sheet based on ASHRAE 2007 handbook
shows that the CFM/m2 is about 94 which is almost the same result that has been gotten
form the first assumption.
EMS disagree completely with both calculation results provided by the designer as the first
example was built on an exaggerated heat load figure (1000 Btu/m2) and the second
example which is based on ASHRAE 2007 handbook which is applicable for greenhouse
cooling load calculations where the solar radiation represents the major heat gain.
Based on the above results; the below table summarizing the evaporative cooling desert
cooling capacities as provided by the designer:
Building Type
Labor Type 1
Labor Type 2
Recreation Center
Resturant
Utility Building
Visitors Building
Model
DC-1-LT1
DC-2-LT1
DC-1-LT2
DC-2-LT2
DC-1-REC
DC-1-LAU
DC-2-KIT
DC-3-LAU
DC-4-LAU
DC-5-KIT
DC-5-RES
DC-5-LAU
DC-6-KIT
DC-1-UB
DC-2-UB
DC-1-VL
DC-2-VL
CFM
30,400
19,200
32,000
33,600
29,500
9,000
13,500
16,000
21,000
29,500
29,500
29,500
32,000
8,000
1,600
10,000
6,000
QTY
1
1
1
1
5
1
1
1
1
1
6
1
1
1
1
1
1
kW
13
5.6
13
13
13
13
2.2
3.7
5.6
13
13
13
13
1.3
0.6
1.5
0.75
Page 25 of 45
APD70
ASHRAE recommends using one of the 2 mentioned below methods to calculate the
evaporative cooling units capacities:
1- Detailed Cooling Load Calculations
Using the Hourly Analysis Program (HAP 3.34) that was developed by Carrier; EMS
conducted a detailed load calculations for the Library and the Internet hall; the following table
summarizing the results:
Page 26 of 45
APD70
From the above table; the area of Library and Internet hall is 364.7 m2 and its sensible
cooling load is 68.5 kW and coil load is 86.9 kW,
Leaving Air Temp (LAT) = DB ((DB WB) * Efficiency)
= 115- (115 68) * 0.85
= 75.05
Air Flow
The designer calculations for the same area show that the required air flow of the
evaporative cooling unit is 29,500 CFM..
CFM / m2
= 22,900/364.7 = 62.8
From the above; it is clear that the CFM requirements based on actual cooling load
calculations are 36 % less than that considered by the designer.
The above cooling load is calculated based on the below design parameters:
Wall U value = 0.475 W/m2 oC
Roof U value = 0.425 W/ m2 oC
Windows U value = 1.72 W/ m2 oC
Windows shading Coefficient = 0.29.
Lighting load density = 16.14 W/m2
Electrical Equipments = 30 W/m2
Number of occupants = 102 person seated at rest
(67.4 & 35.2 W/person for sensible and latent heat loads per person).
Fresh air requirements 100%
Page 27 of 45
APD70
Page 28 of 45
APD70
Page 29 of 45
APD70
Building Type
Labor Type 1
Labor Type 2
Recreation Center
Resturant
Utility Building
Visitors Building
Model
DC-1-LT1
DC-2-LT1
DC-1-LT2
DC-2-LT2
DC-1-REC
DC-1-LAU
DC-2-KIT
DC-3-LAU
DC-4-LAU
DC-5-KIT
DC-5-RES
DC-5-LAU
DC-6-KIT
DC-1-UB
DC-2-UB
DC-1-VL
DC-2-VL
CFM
19,600
12,400
20,600
21,600
19,000
5,800
8,700
10,300
13,500
19,000
19,000
19,000
20,600
5,200
1,100
6,500
3,900
QTY
1
1
1
1
5
1
1
1
1
1
6
1
1
1
1
1
1
The main duct sizing based on the designer calculations for the library and Internet hall
(29,500 CFM) is (1900 * 750 mm) and the air velocity is 12.3 m/sec; while the main duct
sizing based on the suggested air flow (22,900 CFM) will be (1500 * 750 mm) with air
velocity of 9.6 m/sec.
EMS recommends the designer revisiting the duct sizing area to re-calculate the duct
dimensions for each area based on the new evaporative coolers adjusted air flow.
Another point that should be raised here that the provided design drawings doesnt show the
engineering solution for exhausting the supplied air quantities from each evaporative cooler, It
is clear that exhaust from toilets will only remove very small fraction of the supply air while
the remaining air will be ex-filtrated though doors and windows.
Page 30 of 45
APD70
The designer considered an exhaust air fan of 1200 CFM and an exhaust air duct of (500 *
250 mm) for the toilet, lockers room and changing room next to the Library and Internet Hall.
EMS checked the exhaust air quantities and found it according to ASHRAE 62.1-2007, and
agrees with the suggested fan sizing and exhaust duct dimensions.
The designer equipments schedule shows the need for installing 2 steam boilers 626 kg
each, one operational while the other is stand-by, while his calculations according to laundry
equipments requirements shows that the steam requirements is 564 kg after considering
10% as safety factor.
EMS agrees with the designer selection.
The steam layouts show that the main the steam from the boiler is distributed by a 2 inch
pipe diameter at 150 PSIG,
EMS dis-agrees with pipe sizing as it was considered based on pressure drop of 150 Pa/m;
while ASHRAE Fundamentals handbook recommends a pressure drop of 450 to 1100
Pa/m for such boiler pressure, applying this; then the main pipe diameter from the boiler
should be maximum 40 mm instead of 50 mm.
EMS agrees with 150 PSIG operational pressure as the required steam pressure at the
utility press is 115 PSIG.
Page 31 of 45
APD70
Also steam layouts shows that the water in feed water tank is pre-heated with live steam
before introduced to the steam boiler which is considered as correct action; but the layouts
didnt show any collections for the condensate return line from the main steam line or from
the steam end users to the tank, taking into consideration that this condensate water is
100% pure hot water; collecting it and returning it to the feed water tank will reduce the preheating costs, the water treatment costs and the water costs.
EMS recommends the designer to re-visit this area to collect and direct the condensed water
from all possible points and return it back to the boiler feed water tank.
The designer equipments schedule shows the need for installing 2 air compressors 18 CFM
each
at 115 PSIG, one operational while the other is stand-by, while his calculations
according to laundry equipments shows that the compressed air requirements is 18 CFM by
considering 5% only as safety factor and part of that requirements is at 115 PSIG.
EMS recommends increasing the installed air-compressors capacity by at least 20% to cater
for future expansions and any compressed air leaks, also the operating pressure should be
increased to about 120 PSIG to cater for pressure drop through pipes, fittings and valves.
The compressed air layouts show that the main the compressed air from the air
compressors is distributed by a 1 inch pipe diameter at 115 PSIG,
EMS agrees with pipe size and as mentioned above; recommends increasing the operational
pressure to 120 PSIG as the required steam pressure at the utility press is 115 PSIG.
Page 32 of 45
APD70
Page 33 of 45
APD70
The first source was based on considering 4,860 persons, 185 lit/day/person, 60%
waste water discharge factor, and 10% evaporation factor which could secure 486
m3/day.
EMS agrees with designer calculations.
The second source was based on 190 m3/day from kitchen with 80% collection
factor which could secure 152 m3/day.
Although the designer didnt provide any calculations for the water needs of the
restaurant; the considered figure is almost equivalent to the standard international
restaurants figure (35 gallons per seat per day).
Total waste water collection 638 m3/day.
EMS agrees with designer calculations.
Flushing system: which was calculated based on 4860 persons, 185 lit/day/person
and 40% flushing of total daily demand, which could consume (360 m3/day).
EMS agrees with designer calculations.
Irrigation system: which was calculated based on considering 10 liters per day for
each square meter of covered area and also for each palm tree, which could
consume (115.6 m3/day).
Page 34 of 45
APD70
= 60 oC
Tin
= 12 oC
Page 35 of 45
APD70
= 0.95
Although; EMS agrees with designer calculations of the electric water heaters, we
recommend utilizing the steam to generate the required domestic hot water especially for
the restaurant and for any other close building.
Page 36 of 45
APD70
Many types and systems of renewable energy are available in the world, the applicability and
the feasibility of these systems depends on many variables that affect the installation and/or
the operation of the renewable energy systems.
In Saudi Arabia, there are some renewable energy systems that could be utilized to reduce
depending on the fossil fuel energy sources. The following systems are applicable in the:
1- Solar thermal water heating system
2- Wind energy systems
3- Solar photovoltaic systems
This report will investigate the feasibility and applicability of the above mentioned systems for
Al-Fanar Head Quarter Building.
It is well known that solar energy is the main renewable energy source especially in the
Middle East area due to high solar radiation in comparison to other areas in the world as
shown in the below figure:
World Solar Radiation
According to RETScreen software; the average daily solar radiation, wind speed and
temperature data for Riyadh region which are based on ground monthly measured data are
shown in the below table:
Page 37 of 45
APD70
Table (1)
. Riyadh ground weather data
The designer didnt provide any calculations, sizing or selection for the recommended solar
water heaters that are mentioned in the drawings on several buildings roofs
EMS calculations based on Wagner selections for the APD 32 show that:
Domestic water heating cost = 19,980 * 0.26
= 5,195 SAR/yr.
Solar Water Heaters cost
= 35,000 SAR
Page 38 of 45
APD70
Page 39 of 45
APD70
Page 40 of 45
APD70
Page 41 of 45
APD70
Page 42 of 45
APD70
can significantly reduce the power output, and of course no power is produced at night. PV
systems work best during summer months since the day is longer and the sun intensity is
higher. Due to these variations between summer and winter, day and night, it is difficult for
PV systems to cover all the needed power, therefore it is advised to be used in conjunction
with utility-supplied electricity.
The generating capacity depends on the PV modules efficiency in converting sunlight to
electricity.
For Al-Fanar Head quarter project, electrical analysis of installing a PV system to supply part
of the buildings load was evaluated by using special PV software
It was assumed that the proposed area for installing the PV panels is on the roof empty
areas away from the equipments shading. All PV modules should be oriented to the south in
order to absorb maximum solar energy with efficient way. The available empty surface area
was not determined yet, therefore, the following estimation is referred to kWh per squared
meters. The following assumptions were considered in the study:
1) The PV panel tilted angle is 20 degree and facing to the south.
2) PV SYST version 4.0 software package was selected in this study.
3) PV module is Si- poly crystalline type with maximum efficiency of 13.4%.
4) Electric Tariff = 0.26 SAR/kWh
5) Standalone (Off-Grid) project cost = 15.0 SAR / W
Page 43 of 45
APD70
PVSYST is a PC software package for the study, sizing, simulation and data analysis of
complete PV systems. It is suitable for grid-connected, stand-alone and DC-grid (public
transport) systems, and offers an extensive meteorological and PV-components database.
The total electrical generation capacity depends on the PV modules efficiency in converting
sunlight to electricity.
It was shown that for off grid project the annual energy supply is 163 kWh / m2 of module,
with electric power of 133.6 Watt /m2 for each module. In other word, the annual delivered
electrical energy from PV modules of total area 100 m2, for example, is about 16.22 MWh.
The proposed above PV arrays produce total electrical power capacity of about 19.73 kWp.
The annual saved in electrical energy = 0.26 SAR/kWh * 163 kWh = SAR 42.4 / m2
The PV cost was estimated and summarized as follows:
The above mentioned systems prices includes solar panels, batteries, inverters and charge
controller.
The capital cost of PV module = SAR 2,000 / m2.
The payback Period = 47.2 years
Page 44 of 45
APD70
Wind speed and wind speed fluctuations are mainly dictated by physical geography and
vegetation. The ideal site for wind energy generation should offer wind resources with the
following characteristics:
Table (1) above shows that the average winds speed for Riyadh is less than 7 m/sec.
Moreover, the minimum distance between the wind mill and the surrounding residents
building shall be not less than 10 times the height of the wind mill to avoid the windmill noises.
Since trees and surrounding building are usually considered as major wind obstacles,
therefore, height of the wind turbine should be increased in order to compensate the effect of
these obstacles. It is expected that the height of the wind mill not less than 30 meter to run
with acceptable low air resistance. Then the building should be far from the mill with at least
300 meter. Moreover, the voltage drop and cost of the electric cables will be increase the
wind turbine is installed far from the electricity local network.
Other environmental issue that limits the installation of the wind turbines is its negative
impact on the birds and other native animals on the surrounding environment which cause
the native animals and bird to leave.
Therefore, it is not recommended to install wind turbine at AlFanar Head Quarter project due
to the above obstacles.
Page 45 of 45