Department of Chemical and Biomolecular Engineering, Yonsei University, 50 Yonsei-ro, Seodaemun-gu, Seoul 120-749,
Republic of Korea
GS E&C, GS Yeokjeon Tower, 537 Namdaemun-ro 5-ga, Joong-gu, Seoul 120-722, Republic of Korea
ABSTRACT: Liqueed natural gas (LNG) is attracting great interest as a clean energy alternative to other fossil fuels, mainly
due to its ease of transport and low carbon dioxide emissions, a primary factor in air pollution and global warming. It is expected
that this trend in the use of LNG will lead to steady increases in demand over the next few decades. To meet the growing
demand for LNG, natural gas liquefaction plants have been constructed across the globe. Furthermore, single train capacity has
been increased to strengthen price competitiveness. To achieve greater capacity, more complex refrigeration cycle designs that
combine two or more dierent conventional single refrigeration cycles are being developed to obtain synergistic eects in the
liquefaction process. At the same time, a variety of recent studies have focused on designing suitable processes for oshore and
small-scale plants to improve the protability of stranded gas elds. LNG plants are known to be energy/cost-intensive, as they
require a large amount of power for the processes of compression and refrigeration, and need special equipment such as
cryogenic heat exchangers, compressors, and drivers. Therefore, one of the primary challenges in the LNG industry is to improve
the eciency of the current natural gas liquefaction processes in combination with cost savings. In this paper, we review recent
developments in LNG processes, with an emphasis on commercially available refrigeration cycles. We also discuss recent research
and suggest future directions for natural gas liquefaction processes. Up to this point, most studies have focused on operating cost.
To achieve better results, future studies that investigate optimal design and operation of LNG technologies should consider both
capital cost and operating cost.
INTRODUCTION
natural gasb
oilc
coald
carbon dioxide
carbon monoxide
nitrogen oxides
sulfur dioxide
particulates
formaldehyde
mercury
117,000
40
92
0.6
7.0
0.750
0.000
164,000
33
448
1122
84
0.220
0.007
208,000
208
457
2591
2744
0.221
0.016
April 1, 2012
December 14, 2012
December 14, 2012
December 15, 2012
dx.doi.org/10.1021/ie302877g | Ind. Eng. Chem. Res. 2013, 52, 30653088
Review
past 5 years, there has been a 40% increase in the global LNG
production capacity. The liquefaction capacity is projected
to more than double from 8 trillion cubic feet in 2008 to 19
trillion cubic feet in 2035.2
A LNG project is considered one of the most expensive
energy projects and comprises a set of unique values in the
supply chain (known as the LNG value chain), as schematized
in Figure 2.6 The percentage of average capital costs for each
component in the LNG value chain is presented in Figure 3;7
there are noticeable dierences between the costs of each
element in conventional natural gas elds. The cost of a
liquefaction plant is the greatest in the value chain, accounting
for more than 40% of the total cost. The costs of the other
components account for nearly equal portions of the remaining
total. Among the components, the costs of exploration and
production vary greatly according to natural gas eld. Accurate
cost projection of a LNG project depends on a suite of factors
including site conditions, safety, and traded volumes. From an
economic perspective, the liquefaction plant is the most
important component in the LNG value chain.
Review
Review
Review
in the worlds rst LNG plant in CAMEL. This process comprises three separate refrigeration cycles as shown in Figure 10.13
The three refrigerant cycles are typically operated at three
evaporation temperature levels with multistage compression.
High-pressure propane is condensed by ambient air or cooling
water in the multistage compression step. In the propane cycle,
the propane is used to cool the natural gas and the other
two refrigerants to 30 C. The ethylene cycle then cools the
natural gas and methane to about 100 C. Finally, the methane
is used to produce LNG at 160 C.19
A kettle-type heat exchanger is employed in the propane
cycle, and a coil-wound heat exchanger (CWHE) is used in the
ethylene and methane cycles. Steam turbines contribute to drive
compressors for each refrigerant cycle and condensers uses
cooling water as a coolant. The three-train capacity is a mere 1.1
MTPA.
Phillips Cascade.19 The LNG plant in Kenai applied an early
version of the Phillips cascade process similar to that used in the
CAMEL plant. This process also uses propane, ethylene, and
methane cycles, but the single train capacity is 50% greater than
that of the three trains at CAMEL. This process is considered
to be the rst that employed gas turbine/compressor sets and a
plate-n heat exchanger (PFHE) in each refrigeration cycle.19
Phillips Optimized Cascade (POC).2023 A new version of
the cascade process, known as Phillips Optimized Cascade
(POC), was developed and applied to a Trinidad LNG plant in
1999 by ConocoPhillips as shown in Figure 11.21 This process
also uses three pure refrigerants (propane, ethylene, and methane),
and each cycle is operated separately at multiple pressure levels.
Review
Review
Review
for the precooling cycle. The main feature of the PMR process
is that two MR cycles for liquefaction are congured in parallel,
which reduces the pressure drop in the system and improves
the reliability of the plant, thereby improving process eciency;
the train capacity can reach 8 MTPA using existing
compressors.37
IFP/Axens Liquen.33,34 IFP/Axens developed the Liquen
process with two mixed refrigerant cycles, precooling and liquefaction cycles, as shown in Figure 17.33 The two refrigerants are
composed of methane, ethane, propane, butane, and nitrogen,
but the compositions dier in each cycle. The heavy MR
precooling cycle is used to cool the natural gas, and precool and
liquefy the other mixed refrigerant at three dierent pressure
levels. The light MR liquefaction cycle is used to liquefy and
subcool the natural gas. Both cycles are carried out in PFHE
3072
Review
liquefy and subcool the natural gas. Similar to the single cycle
processes, precooling, liquefaction, and subcooling are carried
out in the same heat exchanger.
APCI AP-X.39,40 The AP-X process was developed from the
C3MR process by APCI. As shown in Figure 19,40 this process
comprises three cycles: a propane precooling cycle, a mixed
refrigerant cycle, and a nitrogen subcooling cycle. A unique
feature of this process is that the LNG is subcooled using a
nitrogen expander cycle rather than a mixed refrigerant cycle.39
Natural gas precooled to about 30 C in the propane cycle
using kettle-type heat exchangers is cooled and liqueed to
about 120 C in the MCHE with a mixed refrigerant. The LNG
is subcooled using cold gaseous nitrogen from the nitrogen
expander. In the nitrogen cycle, nitrogen is compressed to a high
pressure and then cooled to near ambient temperature. The highpressure nitrogen is cooled in a nitrogen PFHE-type economizer
with low-pressure nitrogen returning to the compressor. The
high-pressure nitrogen passing through the nitrogen economizer
is expanded to a low pressure to further reduce its temperature in
the expander. Compared to the C3MR process, the nitrogen
expander subcooling cycle allows the ow of both propane and
mixed refrigerant to be reduced without aecting production,
enabling much higher capacities (approximately 8 MTPA) using
existing equipment.40 CWHEs are used for the MR and nitrogen
subcooling cycles.
Statoil-Linde Mixed Fluid Cascade (MFC).41,42 The mixed
uid cascade (MFC) process was developed by Linde in
collaboration with Statoil and was applied in the Snohvit LNG
project. The capacity of a single train that uses this process
is 4 MTPA. As shown in Figure 20,41 this process is similar
to the cascade process and also consists of the three cycles of
precooling, liquefaction, and subcooling.41 Compared to the
cascade process, the MFC process has higher eciency as it uses
three mixed refrigerants instead of three pure refrigerants. The
mixed refrigerants are composed of methane, ethane, propane,
and nitrogen, but the compositions dier in each cycle. Another
feature is that the power requirements for each cycle are not the
same, unlike the POC process. The precooling cycle uses PFHE,
while the liquefaction and subcooling cycles use CWHE.22
2.2.3. Expander. Single Nitrogen Expander.43,44 Nitrogen
expander processes, which are based on reverse-Brayton and
Review
Review
Review
Review
heat exchanger
process
precooling
liquefaction
subcooling
precooling
liquefaction
POC
PRICO
C3MR
DMR
Liquen
PMR
CII
AP-X
MFC
propane
MR
propane
MR
MR
propane or MR
MR
propane
MR
ethylene
methane
PFHE or core-in-kettle
cold box (PFHEs)
core-in-kettle
CWHE
PFHE
PFHE
MR
MR
MR
parallel MR
MR
MR
heat
exchanger
type
coil-wound
plate-n
compressor
centrifugal
axial
pros
robust/high
operability
competitive
vendors
low pressure drop
low temperature
dierences
robust/light/simple
design
low manufacturing
cost
high eciency
high compression
ratio
driver
steam turbine
gas turbine
aero-derivate
turbine
electric
motor
several vendors
high reliability and
availability
cost eective/high
eciency
small space/ease of
installation
suitable for high
ow rates
high eciency
high reliability and
availability
ease of installation/
small space
shorter
maintenance
period
high eciency/no
emissions
high operability and
availability
exible
maintenance
simple layout
PFHE
CWHE
CWHE
PFHE
N2
MR
subcooling
criteria
cons
thermal eciency
complexity
equipment count
hydrocarbon refrigerant
storage
overall space requirement
compactness and lightness
simplicity of operation
ease of start-up/shutdown
exibility
sensitivity to vessel motion
capital investment
proprietary/more
expensive
careful design
vulnerable to upsets
impossible at high ow
rates
low eciency and
compression ratio
suitable only at high
ow rates
more expensive
vulnerable to FODa
large space
requirements
more expensive
cascade
mixed
refrigerant
expander
high
high
high
large
mediumhigh
medium
lowmedium
mediumlarge
low
low
low
none
high
low
medium
medium
high
medium
high
medium
medium
medium
low
medium
medium
lowmedium
low
mediumhigh
high
high
high
low
low
Review
Review
Figure 28. Trend of U.S. patenting activities for natural gas liquefaction technologies.60
year
assignee
3,957,47361
4,445,91662
4,525,18536
4,755,20032
5,791,16063
6,250,10564
6,347,53265
6,658,89066
6,691,53167
6,722,15768
6,725,68869
6,789,39470
7,100,39971
7,234,32272
4,265,30273
4,566,88574
4,880,05575
6,640,58676
7,069,73377
7,266,97678
1976
1984
1985
1988
1998
2001
2002
2003
2004
2004
2006
process
process
process
process
process
process
process
process
process
process
process
objective
contents
2006
2007
1981
1986
1989
2003
2006
2007
ConocoPhillips
ConocoPhillips
Rosenthal Technik AG
Shell Oil
Sundstrand
ConocoPhillips
APCI
ConocoPhillips
process
process
equipment
equipment
equipment
equipment
equipment
equipment
Review
Figure 29. Technical trends in patents for natural gas liquefaction processes and related equipment.60.
process
cascade
SMR
C3-MR
DMR
MFC
single N2 expander
C3 precooled single N2
expander
double N2 expander
a
Dam et al.
32
32a
Finn et al.
(relative to cascade)
Dam et al.
(relative to DMR)
Foerg38
(relative to MFC)
Vink et al.39
(relative to C3-MR)
Barclay et al.46
(relative to C3-MR)
1.00 (1188)
1.25 (1485)
1.15 (1366)
1.39 (1382)
1.155
1.142
1.033
1.156 (1218)
1.189 (1253)
1.000 (1054)
1.000 (1054)
1.06 (1054)
1.09 (1083)
1.00 (994)
1.025 (1080)
1.000
2.00 (2376)
3.10 (3266)
3.32 (3499)
1.70 (2020)
1.70 (2020)
1.35 (1426)
Terry87 performed simulation and optimization of a typical liquefaction process in a peak shaving plant using HYSYS commercial
software. Li et al.88 designed small-scale LNG systems that used
a nitrogen expander cycle and mixed refrigerant cycle based on
numerical simulations and system optimization. Cao et al.89
designed and simulated two typical types of small-scale
liquefaction processes in a skid-mounted package. They reported
that the N2-CH4 expander cycle preceded the mixed refrigerant
cycle on the premise of lacking propane precooling. In addition,
it was found that large temperature dierences and high heat
exchange loads were the primary reasons for exergy loss in heat
exchangers.
Jensen and Skogestad90 studied design optimization of the
PRICO process. The process was modeled and optimized using
gPROMS, and Multiash was used for thermodynamic
calculations. The objective function included design parameters
(e.g., heat transfer area) and operating parameters (e.g., ow
rate, pressure, splits) with respect to thermodynamics and cost.
Further, a set of key constraints concerning compressor
feasibility was discussed. Li and Ju91 conducted research on
the design of three dierent liquefaction processes including
SMR, C3MR, and N2 expander for special oshore gases in the
South China Sea. A systematic analysis and comparison of these
Review
energy consumption. Their methodology is based on a mixedinteger nonlinear programming (MINLP) formulation. To
reduce the MINLP model complexity, thermodynamic calculations were carried out using a simplied model based on the
regression of rigorous simulation results. The optimization
problem was solved using the LINDOGloal solver in GAMS.
The optimization results were validated through rigorous
simulation using Aspen Plus. A case study of the C3MR process
showed that the proposed methodology reduced the energy
consumption by 13%.
Aspelund et al.103 developed a methodology for process
synthesis by extending traditional pinch analysis with exergy
analysis, that is, Extended Pinch Analysis and Design (ExPAnD).
ExPAnD showed great potential for improving subambient
processes. Energy requirements (total shaft work) were
minimized by optimizing the compression and expansion
work of process streams, as well as the work required to
generate necessary cooling utilities. The ecacy of the proposed
methodology was veried by applying it to design of LNG
process: exergy eciency increased from 49.7% to 85.7%
compared to standard pinch analysis. Shah and Hoadley104
proposed a shaft work targeting method for multistage gas-phase
auto refrigeration systems. This targeting method demonstrated
the relationship between the expansion/compression ratio and
the heat exchange design parameter delta Tmin. In the case of
natural gas liquefaction, a dual gas-phase system can achieve the
net shaft work requirements with values only slightly higher
than those of single mixed refrigerant systems. Jensen and
Skogestad105 warned that the method using specied delta Tmin
when designing heat exchangers could lead to wrong decisions.
The minimum temperature approach favors a more constant
temperature dierence prole; however, in the case of optimal
operation, it was found that the temperature dierence at one
end was small. These authors proposed a simplied total
annualized cost (TAC) method that considers both operating
and capital costs. In addition, the results showed that there is
a trade-o relationship between heat exchanger capital cost and
compressor power.
More recent studies have discussed mixed refrigerant systems
with a focus on mitigating the energy requirements for
refrigerant compression through optimizing operating conditions
such as pressure, ow rate, and the composition of mixed
refrigerants.
Cammarata et al.106 presented a genetic algorithm (GA)based optimization methodology for liquefaction/refrigeration
systems. Nogal et al.100 also used a GA-based approach for
optimal design of mixed refrigerant cycles. Shirazi and Mowla107
attempted to minimize energy consumption in the PRICO
process designed for a peak shaving plant using a GA
implemented in MATLAB. The set of design variables included
pressure, ow rate, and composition of the mixed refrigerant.
The PengRobinson (PR) equation of state (EOS) was used
for thermodynamic calculations of process streams. The
optimization results showed that the specic work of the
process could be reduced by 3% or 6.5% as compared to the
results of Lee et al.99 Taleshbahrami and Saari108 performed
thermodynamic simulation and optimization of the C3MR
process using a GA approach. Modeling and simulation of the
C3MR process was carried out using MATLAB. The thermodynamic properties were calculated by PR EOS. Minimization of
total compressor power was dened as the objective function.
The optimal power consumption was reduced by 23% as compared
to the base case. Furthermore, the hot and cold composite
Review
Review
Review
objective function
optimization formulation
process
Cao et al.89
shaftwork requirement
Jensen and
Skogestad90
Al-Sobhi et al.93
SRK (Multiash)
Vaidyaraman and
Maranas96
Vaidyaraman and
Maranas97
Kim et al.98
Lee et al.99
MILP [GAMS(CPLEX)]
SRK
shaftwork requirement
(i) crossover (ii) sum of crossover
(iii) shaftwork requirement
capital cost and shaftwork
requirement
shaftwork requirement
PR
GA
PR (WORK)
Wang et al.
Aspelund et al.103
shaftwork requirement
shaftwork requirement
PR
SRK
Shah and
Hoadley104
Shirazi and
Mowla107
Taleshbahrami and
Saari108
Alabdulkarem et
al.109
Aspelund et al.110
shaftwork requirement
shaftwork requirement
GA (MATLAB)
PR
cascade nitrogen
expander
PRICO
shaftwork requirement
GA
PR
C3MR
shaftwork requirement
C3MR
shaftwork requirement
PRICO
Morin et al.111
Tak et al.113
Wang et al.114
shaftwork requirement
shaftwork requirement
shaftwork requirement
94
Nogal et al.100
Nogal et al.101
102
GA
PR (Aspen Hysys)
PRICO, TEALARC
PRICO
C3MR
NLP: Nonlinear Programming; MILP: Mixed-Integer Linear Programming; MINLP: Mixed-Integer Nonlinear Programming; SQP: Sequential
Quadratic Programming; GA: Genetic Algorithm; TS: Tabu Search; NMDS: NelderMead Downhill Simplex; PR: PengRobinson; LKP: Lee
KeslerPloecker; SRK: SoaveRedlichKwong. bAspen HYSYS Optimizer (original mode) includes the following types of algorithms: Function
Setup, Box Method, SQP Method, Mixed Method, Fletcher Reeves Method, and Quasi-Newton Method. cgPROMS is used for process modeling,
simulation, and optimization, and Multiash is used for physical and thermodynamic properties calculations.
Review
(6) Liqueed Natural Gas: Understanding the Basic Facts; DOE NETL,
2005.
(7) The Global Liqueed Natural Gas Market: Status & Outlook; U.S.
Energy Information Administration (EIA), December 2003.
(8) Investors Handbook. http://www.investorshandbook.shell.com/
2010/servicepages/downloads/les/download.php?le=all_shell_
ih10.pdf (accessed September 3, 2012).
(9) LNG Technology. http://www.airproducts.com//media/Files/
PDF/industries/energy-lng-brochure-0408.ashx (accessed September
3, 2012).
(10) Castle, W. F. Cryogenics and Gas Separation Processes. Bull. IIR
2004, 515.
(11) World Energy Outlook 2009; International Energy Agency (IEA),
November 2009.
(12) Kirillov, N. G. Analysis of Modern Natural Gas Liquefaction
Technologies. Chem. Pet. Eng. 2004, 40 (78), 401406.
(13) Finn, A. J.; Johnson, G. L.; Tomlinson, T. R. Developments in
natural gas liquefaction. Hydrocarb. Process. 1999, 78 (4), 4759.
(14) Smith, R. Chemical Process Design and Integration; Wiley:
Chichester, West Sussex, England/Hoboken, NJ, 2005; p xxiii, 687 pp.
(15) Smith, J. M.; Van Ness, H. C.; Abbott, M. M. Introduction to
Chemical Engineering Thermodynamics, 7th ed.; McGraw-Hill: Boston,
MA, 2005; p xviii, 817 pp.
(16) Barron, R. F. Cryogenic Systems, 2nd ed.; Oxford University
Press/Clarendon Press: New York/Oxford, Oxfordshire, 1985; p xvii,
507 pp.
(17) Walker, G. Cryocoolers; Plenum Press: New York, 1983.
(18) Timmerhaus, K. D.; Flynn, T. M. Cryogenic Process Engineering;
Plenum Press: New York, 1989; p viii, 612 pp.
(19) Bosma, P.; Nagelvoort, R. K. In Liquefaction Technology;
Developments through History, 1st Annual Gas Processing Symposium,
Doha, Qatar, January 1012, 2009.
(20) Andress, D. L. The Phillips Optimized Cascade LNG Process: a
Quarter Century of Improvements; Phillips Petroleum Company:
Bartlesville, OK, 1996
(21) Martin, P.-Y.; Fischer, B. In Natural Gas Liquefaction Processes
Comparison, 14th International Conference and Exhibition on Liqueed
Natural Gas (LNG-14), Doha, Qatar, March 2124, 2004.
(22) Shukri, T. LNG Technology Selection. Hydrocarbon Eng.
February 2004.
(23) ConocoPhillips Optimized Cascade Process. http://
lnglicensing.conocophillips.com/EN/Documents/
ConocoPhillipsLNG_Brochure.pdf (accessed September 3, 2012).
(24) Michelsen, F. A.; Halvorsen, I. J.; Lund, B. F.; Wahl, P. E.
Modeling and Simulation for Control of the TEALARC Liquified
Natural Gas Process. Ind. Eng. Chem. Res. 2010, 49 (16), 73897397.
(25) Stebbing, R.; OBrien, J. An Updated Report on the PRICO
Process for LNG Plants. In Gastech 75: LNG & LPG Technology
Congress, Paris, France, September 30October 3, 1975.
(26) Singh, A.; Hovd, M. Dynamic Modeling and Control of the
PRICO LNG process. In 2006 AIChE Annual Meeting, San Francisco,
CA, November 1217, 2006.
(27) Swenson, L. K. Single mixed refrigerant, closed loop process for
liquefying natural gas. U.S. Patent 4,033,735, Jul. 5, 1977.
(28) Schmidt, W.; Kennington, B. Air Products meets requirements
of full range of Floating LNG concepts. LNG J. March 10, 2011.
(29) McKeever, J.; Pillarella, M.; Bower, R. An ever evolving
technology. LNG Industry Spring, 2008.
(30) Pillarella, M.; Liu, Y.-N.; Petrowski, J.; Bower, R. The C3MR
liquefaction Cycle: Versatility for a Fast Growing, Ever Changing LNG
Industry. In 15th International Conference on LNG (LNG-15),
Barcelona, Spain, April 2427, 2007.
(31) Longsworth, R. C. Cryostat with serviceable refrigerator. U.S.
Patent 4,277,949, Jul. 14, 1981.
(32) Liu, Y.-N.; Newton, C. L. Feed gas drier precooling in mixed
refrigerant natural gas liquefaction processes. U.S. Patent 4,755,200,
Jul. 5, 1988.
AUTHOR INFORMATION
Corresponding Author
ACKNOWLEDGMENTS
This research was supported by a grant from the GAS Plant
R&D Center funded by the Ministry of Land, Transportation
and Maritime Aairs (MLTM) of the Korean government and
also respectfully supported by BK 21 Program funded by the
Ministry of Education (MOE) of Korea.
REFERENCES
Review
Review
(85) Yin, Q. S.; Li, H. Y.; Fan, Q. H.; Jia, L. X. Economic analysis of
mixed-refrigerant cycle and nitrogen expander cycle in small scale
natural gas liqueer. In Cryogenic Engineering Conference, Chattanooga,
TN, July 1620, 2007.
(86) Kikkawa, Y.; Nakamura, M.; Sugiyama, S. Development of
liquefaction process for natural gas. J. Chem. Eng. Jpn. 1997, 30 (4),
625630.
(87) Terry, L. Comparison of liquefaction process. LNG J. 1998, 21
(3), 2833.
(88) Li, H. Y.; Jia, L. X.; Fan, Q. H.; Yin, Q. S. In Numerical
Simulation and Optimazation of Small Scale LNG Plant. In Cryogenic
Engineering Conference, Keystone, Colorado, August 29September 2,
2005.
(89) Cao, W. S.; Lu, X. S.; Lin, W. S.; Gu, A. Z. Parameter
comparison of two small-scale natural gas liquefaction processes in
skid-mounted packages. Appl. Therm. Eng. 2006, 26 (89), 898904.
(90) Jensen, J. B.; Skogestad, S. Single-cycle mixed-uid LNG process
Part I: Optimal design. In 1st Annual Gas Processing Symposium, Doha,
Qatar, January 1012, 2009.
(91) Li, Q. Y.; Ju, Y. L. Design and analysis of liquefaction process for
offshore associated gas resources. Appl. Therm. Eng. 2010, 30 (16),
25182525.
(92) Chang, H. M.; Chung, M. J.; Lee, S.; Choe, K. H. An efficient
multi-stage Brayton-JT cycle for liquefaction of natural gas. Cryogenics
2011, 51 (6), 278286.
(93) Al-Sobhi, S. A.; Alfadala, H. E.; El-Halwagi, M. M. Simulation
and Energy Integration of a Liqueed Natural Gas (LNG) Plant. In 1st
Annual Gas Processing Symposium, Doha, Qatar, January 1012, 2009.
(94) Barnes, F. J.; King, C. J. Synthesis of cascade refrigeration and
liquefaction systems. Ind. Eng. Chem., Process Des. Develop. 1974, 13
(4), 421433.
(95) Cheng, W. B.; Mah, R. S. H. Interactive Synthesis of Cascade
Refrigeration Systems. Ind. Eng. Chem., Process Des. Develop. 1980, 19
(3), 410420.
(96) Vaidyaraman, S.; Maranas, C. D. Optimal synthesis of
refrigeration cycles and selection of refrigerants. AICHE J 1999, 45
(5), 9971017.
(97) Vaidyaraman, S.; Maranas, C. D. Synthesis of mixed refrigerant
cascade cycles. Chem. Eng. Commun. 2002, 189 (8), 10571078.
(98) Kim, J. K.; Lee, G. C.; Zhu, F.; Smith, R. Cooling system design.
Heat Transfer Eng. 2002, 23 (6), 4961.
(99) Lee, G. C.; Smith, R.; Zhu, X. X. Optimal synthesis of mixedrefrigerant systems for low-temperature processes. Ind. Eng. Chem. Res.
2002, 41 (20), 50165028.
(100) Del Nogal, F.; Kim, J. K.; Perry, S.; Smith, R. Optimal Design
of Mixed Refrigerant Cycles. Ind. Eng. Chem. Res. 2008, 47 (22),
87248740.
(101) Del Nogal, F.; Kim, J. K.; Perry, S.; Smith, R. Synthesis of
Cryogenic Energy Systems. In 18th European Symposium on Computer
Aided Process Engineering, Lyon, France, June 14, 2008.
(102) Wang, M. Q.; Zhang, J.; Xu, Q. Optimal design and operation
of a C3MR refrigeration system for natural gas liquefaction. Comput.
Chem. Eng. 2012, 39, 8495.
(103) Aspelund, A.; Berstad, D. O.; Gundersen, T. An Extended
Pinch Analysis and Design procedure utilizing pressure based exergy
for subambient cooling. Appl. Therm. Eng. 2007, 27 (16), 26332649.
(104) Shah, N. M.; Hoadley, A. F. A. A targeting methodology for
multistage gas-phase auto refrigeration processes. Ind. Eng. Chem. Res.
2007, 46 (13), 44974505.
(105) Jensen, J. B.; Skogestad, S. Problems with specifying Delta Tmin in the design of processes with heat exchangers. Ind. Eng. Chem.
Res. 2008, 47 (9), 30713075.
(106) Cammarata, G.; Fichera, A.; Guglielmino, D. Optimization of a
liquefaction plant using genetic algorithms. Appl. Energy 2001, 68 (1),
1929.
(107) Shirazi, M. M. H.; Mowla, D. Energy optimization for
liquefaction process of natural gas in peak shaving plant. Energy 2010,
35 (7), 28782885.
Review
3088